⭐ 9.96/10 Checkatrade
📞 07359 872594

How Long Does a London Renovation Take? A Room-by-Room Timeline Guide

Why Timelines Matter

A clear, realistic programme is one of the most valuable documents a contractor can provide. It:

  • Sets client expectations correctly
  • Allows coordinated procurement of materials and appliances
  • Identifies key decision points and the information needed at each stage
  • Helps clients plan around the works (moving out, alternative kitchen arrangements, etc.)

An unrealistic programme — one that promises the works will complete too quickly — causes more problems than a realistic one. Build in contingency from the start.

Stage-by-Stage: Single-Storey Kitchen Extension (No Planning)

Assuming planning is not required (permitted development), the programme for a standard single-storey kitchen extension in London is:

Stage Duration
Design and drawings 2–4 weeks
Structural engineer 1–2 weeks (alongside design)
Building Control application 2–4 weeks (full plans route)
Kitchen planning and order 8–12 weeks (order lead time)
Groundworks and foundations 1–2 weeks
Superstructure (walls, steels) 2–3 weeks
Roof (flat or pitched) 1–2 weeks
First-fix M&E 1–2 weeks
Insulation and screed 1 week + 4 weeks drying
Internal walls and plastering 1–2 weeks
Second-fix M&E 1 week
Kitchen installation 1–2 weeks
Tiling, decoration, finishes 2–3 weeks

Total on-site programme: 14–22 weeks (including screed drying) Total project duration including pre-construction: 6–9 months

Stage-by-Stage: Rear Dormer Loft Conversion (Permitted Development)

Stage Duration
Design and drawings 2–4 weeks
Structural engineer 1–2 weeks
Party wall notices (if applicable) 2 months (minimum statutory period)
Building Control application 2–4 weeks
Scaffold erection 1 week
Roof structure and dormer 3–5 weeks
Roof waterproofing and windows 1–2 weeks
Staircase installation 1–2 weeks
First-fix M&E 1–2 weeks
Insulation and plastering 2–3 weeks
Bathroom fit-out 2–3 weeks
Second-fix and decoration 2–3 weeks
Scaffold removal 1 week

Total on-site programme: 14–20 weeks Total project duration including pre-construction: 5–8 months

Stage-by-Stage: Full House Refurbishment (3-Bed Terrace)

Stage Duration
Scope finalisation and procurement 2–4 weeks
Structural works (if any) 2–4 weeks
First-fix electrics 2–3 weeks
First-fix plumbing 2–3 weeks
Plastering 2–3 weeks
Drying out 2–4 weeks
Second-fix electrics 1–2 weeks
Second-fix plumbing and bathrooms 2–4 weeks
Kitchen installation 1–2 weeks
Flooring 1–2 weeks
Decoration 2–4 weeks
Snagging and completion 1–2 weeks

Total on-site programme: 20–32 weeks Total project duration including pre-construction: 6–10 months

Extensions + Loft Conversion Combined

Combining a kitchen extension and a loft conversion on the same project extends the programme slightly (some trades overlap) but is more efficient than doing them sequentially.

Total on-site programme: 20–30 weeks Total including pre-construction: 7–12 months

The Most Common Cause of Delays

  • Decision delays: Kitchens, tiles, and bathroom finishes not chosen before works start
  • Material lead times: Bespoke kitchens, windows, and steels have 6–12+ week lead times
  • Party wall delays: The statutory period adds up to 2 months if not started early
  • Planning conditions: Discharge applications can take 8 weeks+
  • Unforeseen structural issues: Discovered during strip-out
  • Weather: Affects external works, particularly during screed and roof stages

RCB Design & Build

RCB produces project programmes at the pre-construction stage for every project, identifying critical-path items and procurement lead times from the outset. We flag potential delays early and build contingency into the programme rather than overpromising and underdelivering.

Get a free site survey

Ready to discuss your project? We offer a free, no-obligation site survey across London. Call, WhatsApp, or email — we respond within the hour during working hours.

📞 Call now💬 WhatsAppFree Quote