Contents
- 1. JCT Minor Works building contract for London homeowners, scope of works as a contract document, and contractor selection and verification in 2025
- 2. Deposits, payment stages, retention, variation orders, and what to do when a contractor abandons a London project in 2025
- 3. Frequently Asked Questions
JCT Minor Works building contract for London homeowners, scope of works as a contract document, and contractor selection and verification in 2025
The JCT Minor Works building contract, scope of works as a contract document, and contractor selection and verification for London home building projects in 2025: JCT MINOR WORKS BUILDING CONTRACT — THE RIGHT CONTRACT FOR LONDON RESIDENTIAL PROJECTS: the JCT (JOINT CONTRACTS TRIBUNAL) produces a family of standard building contracts that are widely used across the UK construction industry; for LONDON RESIDENTIAL PROJECTS (extensions, loft conversions, refurbishments — typically £20,000-£500,000) the most appropriate JCT contract is the JCT MINOR WORKS BUILDING CONTRACT (MW); JCT MW 2016 (OR 2019 EDITION): a simple, widely understood contract designed for smaller building projects; it covers: a clear ARTICLES OF AGREEMENT identifying the contractor and employer, the contract documents (drawings, specification/scope, bills of quantities if used), the contract sum, and the contract period; CLAUSE 1: CONTRACT DOCUMENTS — defines what documents form the contract (the agreement, conditions, drawings, specification/scope); CLAUSE 2: CONTRACTOR'S OBLIGATIONS — sets out what the contractor must do and the standard to which the work must be completed (GOOD AND WORKMANLIKE MANNER, IN ACCORDANCE WITH THE CONTRACT DOCUMENTS, BUILDING REGULATIONS, AND STATUTORY REQUIREMENTS); CLAUSE 3: PAYMENT — sets out the payment mechanism (valuations, interim payments, final payment); CLAUSE 4: EMPLOYER'S INSTRUCTIONS — the mechanism by which the employer (homeowner) can issue instructions, including instructions for VARIATIONS; CLAUSE 5: POSSESSION AND COMPLETION — sets out the contract period, start date, and COMPLETION DATE; LIQUIDATED AND ASCERTAINED DAMAGES (LADs): if the contractor does not complete by the completion date, the employer can deduct LADs (pre-agreed daily or weekly sum for delay) — however, LADs are rarely enforced on residential projects without professional administration; DEFECTS LIABILITY PERIOD: typically 6-12 months after completion; the contractor is required to return and make good any DEFECTS arising within this period; CLAUSE 6: INJURY, DAMAGE AND INSURANCE — the contractor must maintain employer's liability insurance (£5-10m minimum), public liability insurance (£1-5m minimum), and CONTRACTOR'S ALL RISKS (JCT Works Insurance Policy or equivalent — covers the works themselves against fire, flood, and damage during construction); CHECK CONTRACTOR'S INSURANCE: always request and verify CERTIFICATES OF INSURANCE before work starts; an uninsured contractor means an uninsured project; WHERE TO OBTAIN THE JCT MINOR WORKS CONTRACT: jctltd.co.uk — available to purchase and complete online; a BLANK JCT MW FORM must be filled in with the project-specific details (employer and contractor details, contract sum, contract drawings and specification, completion date, insurance amounts, LADs rate, retention percentage); JCT MW WITH CONTRACTOR'S DESIGN (MWD): a variant of JCT MW where the contractor is also responsible for the design of some or all of the works; appropriate for DESIGN AND BUILD ARRANGEMENTS (where the contractor is providing both the design and the build); WHEN TO USE JCT MWD: if the contractor is taking design responsibility (e.g. a design-and-build principal contractor); SCOPE OF WORKS AS A CONTRACT DOCUMENT: a SCOPE OF WORKS (also called a SPECIFICATION OR SCHEDULE OF WORKS) is the written description of what the contractor is required to build; it is the MOST IMPORTANT CONTRACT DOCUMENT because it defines the quality of work, the materials to be used, the standard to be achieved, and what is EXCLUDED; a well-written scope of works prevents the vast majority of contractor disputes; WHAT A GOOD SCOPE OF WORKS COVERS: PROJECT DESCRIPTION AND PROGRAMME (start date, expected duration, key milestones); DEMOLITION AND ENABLING WORKS (what is to be demolished, what is to be retained, how demolition waste is to be disposed of); STRUCTURAL WORKS (foundation specification, structural steels, structural opening sizes); EXTERNAL SHELL (external wall specification — materials, insulation, ties, DPC position; roof — flat GRP or pitched, covering, insulation, drainage; windows and doors — material, performance specification, brand/range if specified); INTERNAL FIRST FIX (partition walls — material and thickness; insulation and boarding; first fix plumbing specification; first fix electrical specification; soil and waste drainage); INTERNAL SECOND FIX (plastering specification; floor finish; second fix electrics; second fix plumbing; joinery); MATERIALS RESPONSIBILITIES (which items are contractor-supplied and which are client-supplied — the standard RCB position is that SECOND-FIX MATERIALS ARE CLIENT-SUPPLIED unless specifically agreed otherwise); EXCLUSIONS (what is NOT included in the price); PROVISIONAL SUMS AND PRIME COST SUMS (where the final specification is not yet known); CONTRACTOR SELECTION AND VERIFICATION IN LONDON: CHECKING A CONTRACTOR'S CREDENTIALS: FMB MEMBERSHIP (FEDERATION OF MASTER BUILDERS): FMB members are independently inspected; TRUSTMARK: Government-endorsed quality mark; CHECKATRADE / TRUSTATRADER: independently verified reviews; NICEIC (ELECTRICAL): nationally recognised certification body for electrical contractors; GAS SAFE REGISTER: legally required for gas work; NHBC OR LABC WARRANTY: new build only; COMPANIES HOUSE: check the company is registered and not in liquidation; DIRECTOR HISTORY: directors of repeatedly failed or insolvent companies carry a pattern that Companies House reveals; VAT REGISTRATION: contractors with a turnover above the VAT threshold (currently £90,000) must be VAT registered; a larger contractor offering cash in hand without VAT is potentially VAT-registered and avoiding tax — this exposes the homeowner to HMRC risk; PLANNING AND BUILDING REGS COMPLIANCE: a contractor who suggests building without Building Control approval is putting the homeowner at serious risk — the homeowner is legally responsible for obtaining compliance; REQUEST AND CHECK: public liability insurance certificate; employer's liability insurance certificate; Company Registration Number (check on Companies House); examples of similar recent work with verifiable references; projected programme (start date, key milestones, expected completion).
Deposits, payment stages, retention, variation orders, and what to do when a contractor abandons a London project in 2025
Deposits and payment stages, retention, variation orders, and what to do when a contractor abandons or goes insolvent part-way through a London building project in 2025: DEPOSITS AND PAYMENT STAGES — PROTECTING THE HOMEOWNER: DEPOSITS: THE GOLDEN RULE ON DEPOSITS IS: DO NOT PAY MORE THAN 10% OF THE CONTRACT SUM AS A DEPOSIT BEFORE WORK STARTS; A MAXIMUM DEPOSIT OF £2,000-£5,000 IS APPROPRIATE FOR SMALLER PROJECTS (£30,000-£80,000); any contractor who demands a deposit of 30-50% of the contract sum before work starts is presenting a significant financial risk; WHAT IS A DEPOSIT FOR? a deposit covers the contractor's material procurement for the first phase of works (materials cannot usually be purchased before start because they need to be available when needed); it is NOT a payment for work not yet done; WHAT IF A CONTRACTOR INSISTS ON A LARGE DEPOSIT? this is a red flag; a well-capitalised, established contractor with material accounts (trade accounts with builders merchants) should not need a large deposit; a contractor who needs a large upfront payment may have cash flow problems; PAYMENT STAGES: GOOD PRACTICE FOR A £60,000-£80,000 EXTENSION CONTRACT IS: DEPOSIT (BEFORE MOBILISATION): 10% = £6,000-£8,000 (covers material procurement for phase 1); FIRST INTERIM PAYMENT (FOUNDATIONS COMPLETE AND INSPECTED): 20% = £12,000-£16,000; SECOND INTERIM PAYMENT (STRUCTURAL SHELL WEATHERTIGHT — ROOF ON, WINDOWS AND DOORS IN): 25% = £15,000-£20,000; THIRD INTERIM PAYMENT (FIRST FIX COMPLETE — PARTITIONS, BOARDING, FIRST FIX M&E): 20% = £12,000-£16,000; FOURTH INTERIM PAYMENT (SECOND FIX AND PLASTERING COMPLETE): 15% = £9,000-£12,000; FINAL PAYMENT LESS RETENTION (PRACTICAL COMPLETION): 5% = £3,000-£4,000 (the balance after retention has been deducted); RETENTION RELEASE (END OF DEFECTS LIABILITY PERIOD — TYPICALLY 6 MONTHS AFTER COMPLETION): retained 5% = £3,000-£4,000; RETENTION: RETENTION IS A PERCENTAGE OF EACH PAYMENT THAT THE EMPLOYER (HOMEOWNER) WITHHOLDS FROM THE CONTRACTOR UNTIL THE END OF THE DEFECTS LIABILITY PERIOD; TYPICAL RETENTION RATE: 5% on all interim payments (released half at practical completion, half at end of defects liability period) or a simpler 5% withheld on all payments until practical completion, then released at end of defects period; WHAT DOES RETENTION PROTECT? it gives the contractor a financial incentive to return and make good defects; without retention, contractors who have been fully paid have little incentive to return; VARIATION ORDERS — THE CRITICAL DISCIPLINE FOR MANAGING SCOPE CHANGES: VARIATIONS (CHANGES TO THE AGREED SCOPE OF WORKS) ARE THE PRIMARY CAUSE OF PROJECT COST OVERRUNS; they are also frequently a source of dispute; THE DISCIPLINE: EVERY CHANGE TO THE AGREED SCOPE OF WORKS MUST BE AGREED IN WRITING BEFORE THE WORK IS DONE; the process is: homeowner or contractor identifies a potential change; WRITTEN VARIATION ORDER REQUEST from one party to the other; WRITTEN QUOTATION from the contractor detailing the additional or reduced cost; WRITTEN APPROVAL from the homeowner before the work starts; WRITTEN RECORD of the approved variation order in a VARIATION ORDER LOG (a running total of all approved variations, the cumulative effect on the contract sum, and the effect on the programme); WHAT HAPPENS WITHOUT VARIATION ORDERS: contractors add work without explicit instruction, then claim additional cost at the end; homeowners instruct additional work verbally on site and are surprised by the additional cost; this situation regularly leads to formal disputes; IMPORTANT NOTE ON VARIATIONS: under JCT MW, the employer can issue INSTRUCTIONS to vary the works; the contractor must carry out instructed variations; the additional cost is assessed on a FAIR AND REASONABLE BASIS (using rates in the original contract, or, where no relevant rate exists, daywork or a negotiated lump sum); WHAT TO DO IF A CONTRACTOR ABANDONS THE PROJECT: CONTRACTOR ABANDONMENT (where the contractor simply stops turning up and stops communicating) is an unfortunately common occurrence in London residential construction; THE LEGAL POSITION: the contractor is in BREACH OF CONTRACT; the homeowner is entitled to: SERVE A FORMAL WRITTEN NOTICE giving the contractor a reasonable period (typically 7-14 days) to return and complete, or agree a programme for completion; if the contractor does not respond or return, the homeowner can DETERMINE (TERMINATE) THE CONTRACT UNDER CLAUSE 6 OR CLAUSE 7 OF JCT MW (or under the common law right to terminate for repudiatory breach); upon termination, the homeowner is entitled to: APPOINT A REPLACEMENT CONTRACTOR to complete the works; recover from the original contractor the ADDITIONAL COST ABOVE THE ORIGINAL CONTRACT SUM incurred by completing with a replacement; PRACTICAL STEPS WHEN A CONTRACTOR ABANDONS: DOCUMENT EVERYTHING: photograph the state of the works; document outstanding payments; recover and secure any site materials that the homeowner has paid for; SECURE THE SITE: the works are often in a dangerous, weathertight-incomplete, or structurally incomplete state — make the site safe; DO NOT PAY FURTHER: if the contractor has abandoned, do not make further payments (the outstanding amounts will be needed to fund the replacement contractor); SEEK LEGAL ADVICE: a SOLICITOR with construction experience or the use of the RICS DISPUTE RESOLUTION SERVICE (DRS) is appropriate for disputes above approximately £10,000; for disputes under £10,000, SMALL CLAIMS COURT (COUNTY COURT) is more appropriate; CONTRACTOR INSOLVENCY: if the contractor becomes INSOLVENT (enters administration or liquidation) PART-WAY THROUGH WORKS: notify the insolvency practitioner/administrator that you are a creditor (for any amounts overpaid or materials paid for that have not been supplied); appoint a replacement contractor as above; check whether you have CREDIT CARD PAYMENT PROTECTION (Section 75 of the Consumer Credit Act 1974 — if any payment was made by credit card over £100, the card company shares liability for the contractor's failure); WHAT TO DO ABOUT BUILDING REGULATIONS AND COMPLETION: a project abandoned or completed by a replacement contractor still requires a BUILDING CONTROL COMPLETION CERTIFICATE; if the original contractor was self-certifying any elements (electrics, plumbing), the replacement contractor must issue their own certificates; costs of the building works already completed (to assess the COST TO COMPLETE) should be assessed by an independent RICS CHARTERED QUANTITY SURVEYOR; CONTRACTOR INSURANCE: check the original contractor's insurance — if the works were insured under a JOINT NAMES POLICY (the contractor's CONTRACTOR'S ALL RISKS covers both contractor and employer as named insured), the employer can make a claim directly against the insurer for damage or incomplete works; PROFESSIONAL ADVICE: if the project was being administered by an architect under JCT MW (the architect as Contract Administrator), the architect can assist with the termination procedure, assessment of the cost to complete, and appointment of the replacement contractor.
Frequently Asked Questions
What is the maximum deposit I should pay to a building contractor in London in 2025?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.