What Do Building Regulations Cover?
Building Regulations in England are contained in the Building Regulations 2010 and associated Approved Documents (A through S). Each Approved Document covers a different aspect of construction:
- •Part A — Structure (loads, foundations, walls, roofs)
- •Part B — Fire Safety (means of escape, fire resistance, smoke alarms, fire doors)
- •Part C — Site preparation and resistance to contaminants and moisture
- •Part D — Toxic substances
- •Part E — Resistance to sound
- •Part F — Ventilation (mechanical and natural)
- •Part G — Sanitation, hot water safety and water efficiency
- •Part H — Drainage and waste disposal
- •Part J — Combustion appliances and fuel storage systems
- •Part K — Protection from falling, collision and impact
- •Part L — Conservation of fuel and power (energy efficiency, insulation)
- •Part M — Access to and use of buildings (disabled access)
- •Part O — Overheating (from 2022)
- •Part P — Electrical safety in dwellings
- •Part Q — Security — dwellings
- •Part S — Infrastructure for charging electric vehicles (from 2022)
For most domestic projects, the relevant parts are A (structure), B (fire), F (ventilation), G (sanitation), H (drainage), L (energy), and P (electrical).
When Do I Need Building Regulations?
Building Regulations approval is required for:
- •All extensions (of any size)
- •All loft conversions
- •All garage conversions
- •All structural alterations (wall removals, new openings, steels)
- •New electrical circuits
- •New heating systems or boiler replacements
- •Replacement windows and doors (if not carried out by a FENSA or Certass registered installer)
- •Conversion of a building from one use to another
Some works are 'exempt' — minor repairs, like-for-like replacements, and certain outbuildings under 30m² are typically exempt. Confirm with Building Control if you are unsure.
How Do You Apply for Building Regulations?
There are two main routes:
1. Full Plans Approval: You submit drawings and specifications to Building Control before work starts. Building Control checks the plans and approves or requests amendments. Inspections are then carried out at key stages during the build. At completion, a Completion Certificate is issued. This is the preferred route for complex or larger projects.
2. Building Notice: You notify Building Control before work starts but do not submit detailed drawings. Inspections are carried out on site. The inspector assesses compliance during the build and at completion. This is suitable for straightforward smaller works (small extensions, simple alterations) where the scope is clear. No formal approval is issued before work starts.
Building Control services are provided by either the local council's Building Control department or an Approved Inspector (a private company). RCB has established relationships with both routes and coordinates the application on your behalf.
What Are the Inspection Stages?
For a standard loft conversion or extension, Building Control inspects at key stages:
- •Commencement (before excavation starts, if applicable)
- •Foundation (inspection of trench before concrete is poured)
- •Oversite (concrete floor slab before screed)
- •DPC (damp proof course level)
- •Structural steel / frame (before walls built around it)
- •Drainage (before backfilling)
- •Roof structure (before roofing materials)
- •Insulation (before plasterboard)
- •Fire stopping (before second-fix, to verify fire compartmentation)
- •First-fix electrical and plumbing
- •Completion (final inspection — all finishes, staircase, fire doors, etc.)
If Building Control inspections are missed, the inspector may require opening up works that have been covered — a costly and disruptive exercise. RCB coordinates all inspection bookings as part of the project programme.
What is a Completion Certificate?
A Completion Certificate is issued by Building Control at the end of the project, confirming that the work has been inspected and complies with Building Regulations. It is:
- •Essential for future property sales (solicitors will ask for it)
- •Required by mortgage lenders
- •Evidence that the work has been carried out to the required standard
- •Increasingly required for insurance purposes
If you buy a property where significant work has been done without a Completion Certificate, you may face problems when you come to sell. Some buildings insurers will not cover properties where extensions or conversions were done without Building Regulations.
What Happens if Work is Done Without Building Regulations?
Carrying out work that requires Building Regulations approval without obtaining that approval is a contravention of the Building Act 1984. The consequences include:
- •The council can issue an Enforcement Notice requiring rectification or demolition of the work
- •Enforcement action has a time limit of one year for most residential works (12 months from completion)
- •After 12 months, a Regularisation application can be made — but this often requires opening up work for inspection
- •Indemnity insurance is commonly used in property sales to protect against the risk of enforcement, but it does not confirm that the work is safe or compliant
- •Future buyers, solicitors, and lenders will identify the missing certificate — it is a common issue in conveyancing
Building Regulations and Energy Efficiency
Part L of the Building Regulations (Conservation of Fuel and Power) has been progressively tightened in recent years. As of 2023, new extensions must meet higher insulation standards than was required even five years ago:
- •External walls: typically U-value of 0.18 W/m²K or better
- •Flat roof: typically 0.15 W/m²K
- •Pitched roof insulation: 0.13 W/m²K
- •Ground floor: 0.13 W/m²K
- •New windows: typically U-value of 1.4 W/m²K
Future regulations (the 'Future Homes Standard') will require even higher standards from 2025 onwards for new dwellings. Extensions and conversions are partially exempt but will face tighter requirements in future updates.
Frequently Asked Questions
Is planning permission the same as Building Regulations?▼
Can I sell my house if a previous extension was done without Building Regulations?▼
Who submits the Building Regulations application — me or the contractor?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.