🏗️ rcbGroup · Property Project Delivery
📞 +44 7359 872594
Choosing a Contractor9 min

Contracts with Building Contractors in London: What to Check Before You Sign

A building contract is the legal backbone of your construction project. It defines what the contractor will build, how much they will be paid, when they will be paid, what happens if the scope changes, and what happens if something goes wrong. Many construction disputes arise because homeowners signed a contractor's standard terms without scrutiny — or had no written contract at all. This guide explains what every London homeowner should check before signing a building contract.

Key Takeaways

  • A signed contract protects both you and the contractor — it is not adversarial; it is the clearest way to ensure both parties have the same understanding of the project
  • The most important document in the contract is the scope of works — the more detailed and specific it is, the fewer disputes there will be about what is included in the price
  • Payment terms should be stage-based (linked to completion of defined stages of work) rather than time-based — never pay more than 10–15% of the total contract value in advance
  • The contract should define a clear variation process — any changes to the agreed scope must be agreed in writing, with a price, before they are carried out
  • Retention (typically 2.5–5% of the contract value, held back until the defects liability period has ended) protects the client against defective work that emerges after practical completion
  • Standard form building contracts (JCT Minor Works, JCT Home Owner Contracts) are balanced and widely understood by contractors — using a standard form is usually better than a contractor's own bespoke terms

Why a Written Contract Matters

Many residential building projects in London proceed on the basis of a written quotation and a handshake — particularly for smaller works. This is a significant risk for both the homeowner and the contractor.

Without a written contract, disputes about what was included in the price, what constitutes a variation, what the payment terms are, and when the project is complete can only be resolved by reference to email exchanges, verbal conversations, and inference from the quotation document — all of which are open to interpretation and dispute.

A written contract that is agreed and signed before work starts: Defines the scope of the project (what is included). Establishes the contract sum (how much the contractor will be paid for the agreed scope). Sets the payment terms (how and when the contractor will be paid, and in what amounts). Defines the process for variations (changes to the agreed scope). Establishes the programme (when the contractor expects to start and complete). Defines the defects liability period and retention provisions (how defective work will be remedied after completion). Provides a dispute resolution process (how disagreements will be resolved if they cannot be agreed between the parties). Identifies the contractor's insurance obligations.

A contract does not guarantee that a project will go smoothly — but it dramatically improves the chances of resolving problems quickly and fairly when they arise.

Which form of contract to use: standard form contracts developed by the JCT (Joint Contracts Tribunal) are the most widely used in the UK residential sector. The JCT Home Owner Contract (for homeowners dealing directly with a builder without professional consultants) and the JCT Minor Works Building Contract (for projects with a contract administrator, typically an architect or project manager) are the most appropriate for residential extensions and refurbishments. Both are available from the JCT website and are balanced between the interests of employer (client) and contractor.

If the contractor proposes their own bespoke contract terms, read them carefully — particularly the payment terms, variation provisions, and dispute resolution clauses. Bespoke contractor terms frequently favour the contractor in ways that standard JCT terms do not.

The Scope of Works: The Most Important Document

The scope of works (or works specification) defines exactly what the contractor is being engaged to build. It is the document that determines whether a particular item of work is included in the contract price or is an "extra" (variation).

A well-written scope of works will: Describe every element of the project in sufficient detail to allow the work to be carried out and checked. Specify the materials to be used (brand, type, specification, colour, finish — not just "good quality"). Specify the standards to which the work must be carried out (Building Regulations Part L compliance, for example; or a specific surface finish standard for plastering). Identify items that are client-supplied (materials or fittings that the client will procure and the contractor will install — known as "client-supplied items" or "free-issue" items). Identify items that are specifically excluded (work that the contractor is not responsible for — for example, decoration after the extension is built, if the client intends to decorate themselves). Identify items that are "provisional sums" (elements of the work where the scope or cost is not yet certain at the time of contracting — for example, foundation depth pending a site investigation, or kitchen appliances not yet selected). Provisional sums are estimates that will be replaced with actual costs as the project progresses.

Vague scope descriptions are the most common source of disputes: "new kitchen extension including all works" is not a scope description. "New single-storey rear extension approximately 4m x 5m as shown on drawing X Rev B, constructed in brick to match existing to rear elevation and timber-framed to side elevation, with reinforced concrete slab to engineer's design (drawing Y), structural steel frame to engineer's specification (drawing Z), flat GRP roof with proprietary rooflight, bi-fold doors to rear elevation (make/model/specification as specified), all to Building Regulations compliance" is closer to an adequate scope.

Payment Terms: Stage Payments, Advance Payments, and Retention

Payment terms are the most frequently contested element of building contracts. Understanding what is reasonable — and what represents an unacceptable risk — protects the homeowner.

Stage payments (the standard approach): payments linked to the completion of defined stages of the work (for example: 10% on mobilisation; 20% on completion of groundworks; 20% on completion of external structure; 20% on first fix; 20% on second fix; 10% on practical completion, minus retention). Stage payments link money to progress — the contractor earns each stage payment by completing the relevant stage of work.

Time-based payments (higher risk): some contractors request weekly or monthly payments regardless of progress. These arrangements give the contractor less incentive to progress the work and give the homeowner less protection if progress stalls.

Advance payments (use with caution): paying a large advance (deposit) before work starts is normal and reasonable to a limited extent — typically 10–15% to cover mobilisation, material orders, and initial costs. Paying more than this upfront is a significant financial risk. If the contractor fails to start or abandons the project, recovering an advance payment is difficult and expensive.

Practical completion: the point at which the works are substantially complete (all specified works done, only minor snagging items outstanding). On practical completion, the main contract sum is paid, less any retention.

Retention: a small percentage of each interim payment (typically 2.5–5% of the contract value) is withheld by the client throughout the contract and for a defined period after practical completion (the defects liability period, typically 6–12 months). At the end of the defects liability period, the contractor returns to make good any defects that have emerged after completion, and the retention is then released. Retention protects the client's ability to fund rectification of defects if the contractor fails to return.

Red flags in payment terms: Request for more than 15–20% advance payment before work starts. No defined stages — payment linked only to time (weekly or monthly) regardless of progress. No retention provision. Payment terms that require the client to pay before inspecting completed work at each stage.

Variations: Agreeing Changes to the Scope

Variations (or change orders) are changes to the agreed scope of works — additional work outside the original scope, or changes to the specification. Variations are one of the most common sources of dispute in construction contracts.

The essential principle: every variation must be agreed in writing, with a price, before it is carried out. "Verbal agreement to change orders" is a disputed territory — if not documented, there will almost always be a dispute about whether the change was agreed, what the agreed price was, and whether the additional cost was authorised.

What a good variation clause should include: A requirement for all variations to be instructed in writing by the client. A requirement for the contractor to price the variation before carrying it out (or, for urgent variations, as soon as practicable after). A requirement for the client to approve the variation price in writing before the contractor proceeds. A mechanism for valuing variations that cannot be priced in advance (using the contract rates, or on a daywork basis at agreed rates).

Common variation problems: Scope creep: the project grows incrementally as the client adds small additional items ("while you're there, can you also..."). Each individual item seems trivial, but cumulatively they add significant cost and time. Good practice: formally instruct and price every change, however small. Omissions: where the contractor omits work from the original scope, the contract sum should be reduced accordingly. Contractors sometimes resist this — the contract should make clear that omissions are also variations. Unforeseen conditions: conditions discovered on site that were not anticipated when the contract was priced (hidden structural defects, unexpected ground conditions, asbestos) — these are typically variations, but the contract should be clear about who bears the risk of unforeseen conditions.

Insurance, Defects, and Dispute Resolution

Three further areas that every building contract should address clearly:

Insurance obligations: the contract should specify the insurance that the contractor is required to maintain: Public liability insurance: covers the contractor's liability for injury to third parties and damage to third party property arising from the works. Minimum £2 million — typically £5 million or more for domestic projects. Employers' liability insurance: required by law if the contractor employs anyone (even subcontractors). £10 million minimum. Contract works (all risks) insurance: covers loss or damage to the works themselves while under construction (fire, flood, theft, accidental damage). Either the contractor or the client should take out this policy — the contract should specify which party is responsible. Check your home buildings insurance policy — most home policies exclude works under construction above a certain value. Professional indemnity insurance: relevant where the contractor is also providing design services (design-and-build). Covers defects in the design rather than defects in the physical construction.

The homeowner should request certificates of insurance from the contractor before work commences and at each renewal date.

Defects liability period (DLP): a period (typically 6–12 months after practical completion) during which the contractor is obliged to return to site to make good any defects that emerge after completion. During the DLP, the client should maintain a running "snagging list" and issue it to the contractor formally at the end of the period. The DLP is not a warranty against all defects — it is a specific contractual obligation for the contractor to remedy defects arising from the contractor's workmanship or materials within the DLP. Latent defects (defects that were not discoverable on reasonable inspection at the time) may give rise to claims under law for longer periods (typically up to 6 years in contract, or 12 years if the contract is executed as a deed).

Dispute resolution: building contracts should specify how disputes will be resolved: Adjudication: a quick and relatively cheap dispute resolution process available under the Housing Grants, Construction and Regeneration Act 1996 for most construction contracts. An adjudicator makes a binding (but not final) decision within 28 days. Adjudication decisions are enforceable in court. Mediation: a non-binding process where an independent mediator helps the parties reach a negotiated settlement. Faster and cheaper than litigation. Arbitration or litigation: for disputes that cannot be resolved by adjudication or mediation, arbitration (using an arbitrator) or litigation (through the courts) provides a final binding determination.

A standard JCT contract will include appropriate dispute resolution provisions. A homeowner's bespoke contract should also include these.

Frequently Asked Questions

Do I need a contract for a small job, like a bathroom refurbishment?
Yes — even for relatively small works (£5,000–£20,000), a written contract significantly reduces the risk of dispute. At a minimum, you should have a detailed written quotation specifying what is included, a payment schedule, and an agreed start date. For bathroom refurbishments and similar trades-only packages, a JCT Home Owner Contract or even a detailed written quotation with payment stages and a clear scope is a significant improvement over a handshake agreement.
The contractor wants a large deposit (40%) before starting. Is this normal?
No. A 10–15% mobilisation payment is reasonable; 40% is not. A large upfront deposit represents a significant financial risk — if the contractor fails to start, delays, or abandons the project, recovering the advance is difficult and expensive. Push back on any advance payment request above 15–20%. If the contractor insists on a larger advance, treat this as a red flag and reconsider whether to engage them.
The contractor has done extra work and is now claiming it as an additional cost. What are my rights?
If you did not instruct the additional work in writing, and did not agree the price before it was carried out, the contractor's ability to claim additional costs depends on the contract and the circumstances. If the additional work was genuinely necessary (hidden structural defect, for example) and the contractor notified you before carrying it out, a reasonable additional cost claim may be valid. If the contractor carried out additional work without your instruction or agreement on price, you are entitled to challenge the claim — the burden is on the contractor to show the instruction and the agreed price. This is why the written variation process matters.
The contractor is threatening to walk off site unless I pay more than the contract says. What should I do?
Do not pay outside the agreed contract terms under threat. Seek immediate specialist legal advice from a solicitor experienced in construction disputes. If the contractor abandons the project, you may have rights to terminate the contract, recover the additional costs of completing the works with another contractor, and pursue the original contractor for losses — but this is an expensive and difficult process. Adjudication (if your contract provides for it) can provide a quick binding decision on the payment dispute within 28 days.
Should I use a solicitor to check the building contract before I sign?
For contracts above approximately £50,000, yes — a construction solicitor review is worthwhile. For smaller contracts, using a standard JCT Home Owner Contract or JCT Minor Works Contract (rather than a bespoke contractor document) is a more cost-effective way to ensure the contract terms are balanced. If you are being asked to sign the contractor's own bespoke terms, have them reviewed — the payment terms, variation clause, and dispute resolution provisions are the areas most likely to be one-sided.

Important Note

This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. rcbGroup offers free initial consultations — book your free survey.

Was this guide helpful? Share it:

Have a question about your project?

Chat with us on WhatsApp — Faith usually replies within the hour.

Ready to Discuss Your Project?

Free site survey. No obligation. Covering all Greater London & M25.

📞 Call now💬 WhatsAppFree Quote