Contents
Phase 1: Design, planning permission, and Building Regulations — what to confirm before tendering
Design and planning phase: the purpose of the design phase is to produce drawings and a specification that are: sufficiently developed for competitive tender (contractors need enough detail to price accurately — floor plans, elevations, sections, specification notes); compliant with planning policy and Building Regulations (so that the tender price reflects the actual regulatory requirements, not a simplified version of them); agreed and frozen by the homeowner before contractor pricing begins (scope and specification changes after tender increase cost and reduce price certainty). CHECKLIST — design and planning phase: 1. Appointment of architect or principal designer (confirm scope of the architect's appointment: feasibility only? Planning application? Building Regulations drawings? Construction information? Site inspection and certification?); 2. Feasibility study completed (do the proposed works fit within the planning policy context? Is the structural approach feasible? Are the costs likely to be within the homeowner's budget?); 3. Planning permission status confirmed: (a) works are permitted development (PD) — no planning application required; apply for a Lawful Development Certificate (LDC) if any doubt (£103 application fee; 8-week determination; provides legal certainty and satisfies mortgage lender requirements); (b) works require a planning application — application prepared and submitted; fee paid (£258 for householder; £462 per unit for new build); 8-week determination period completed; permission granted (if conditions attached to the permission: review conditions carefully — some conditions require discharge before works begin; confirm with the LABC which conditions are pre-commencement); planning permission granted but appealing or under judicial review — do NOT start works; wait for the appeal or review to conclude; 4. Listed building consent confirmed (if the property is listed Grade I, II*, or II: listed building consent required for all external AND internal works — apply to the LABC; free application; 8-week determination; do NOT carry out any works on a listed building without listed building consent — criminal offence; if in doubt, call the LABC's conservation officer); 5. Conservation area constraints checked (if in a conservation area: check Article 4 Directions that may have withdrawn permitted development rights; confirm with the LABC that the proposed works are acceptable in the conservation area context; if a heritage impact assessment is required, confirm it has been prepared and submitted); 6. Building Regulations application prepared and submitted: (a) Full Plans application (recommended for all projects — provides the most certainty; the LABC or approved inspector reviews the full structural, thermal, fire, and access drawings before works begin and issues a Plans Certificate or Notice of Approval; any issues identified at the Plans stage can be resolved before the contractor prices or begins work); (b) Building Notice (faster but less certain — no pre-approval of the detailed design; the inspector visits the site at each stage and may require remedial works if the design is not compliant; not suitable for structural works or complex thermal or fire compliance situations; Building Notice is NOT available for works that include a new bathroom, new drainage, or a loft conversion in a flat); 7. Structural engineer appointed and structural calculations completed (confirm: structural calculations completed; structural drawings produced for inclusion in the Building Regulations Full Plans application and the construction tender; all structural details coordinated with the architectural drawings — beam positions, padstone details, foundation design, floor-to-beam connections; structural engineer's drawings reviewed and signed off by the Building Control inspector as part of the Full Plans approval); 8. Energy and thermal compliance check (Part L 2021 — whole-dwelling SAP/BRUKL report where required; U-values for new and existing elements meeting Part L minimum standards; glazed areas within Part L limits; overheating check for Part O where required); 9. Drainage design completed (layout of all below-ground drainage from the proposed works to the existing drain connection; Thames Water build-over assessment completed where new drainage is within 3m of a public sewer; drainage design included in the Full Plans Building Regulations application); 10. Fire safety strategy confirmed (Part B — escape routes, protected stairway, fire doors, interlinked smoke alarm system to BS 5839-6; confirm all Part B requirements have been addressed in the Building Regulations Full Plans application).
Phase 2: Party wall, CDM, contractor selection, and contract — legal and commercial pre-start tasks
Party wall phase — CHECKLIST: 11. Party Wall Act compliance assessed by a party wall surveyor or experienced architect (confirm: which works are notifiable under the Party Wall etc. Act 1996? Section 1 notice for new wall on the line of junction? Section 2 notice for works to an existing party structure (party wall, party floor, party fence wall)? Section 6 notice for excavations within 3m or 6m of a neighbour's foundation?); 12. Party wall notices served to all affected adjoining owners (notice served with the correct notice period: Section 1 — 1 month; Section 2 — 2 months; Section 6 — 1 month; served in writing to the adjoining owner at their address or at the property if they are absent; note: party wall notices must be served 1-2 months before the intended start date of the notifiable works); 13. Adjoining owners' responses received and Party Wall Awards prepared where necessary (awaiting response — building owner must NOT commence notifiable party wall works until: the adjoining owner has consented in writing (within 14 days of receiving the notice), OR a Party Wall Award has been agreed between the appointed surveyors (typically 4-8 weeks after the surveyor is appointed); 14. Schedules of condition of adjoining properties completed and agreed (the schedule of condition — photographs and written description of the condition of the adjoining owner's property before works begin — is an important protection for the building owner as well as the adjoining owner; it provides the baseline against which any claims for damage caused by the works are assessed; ideally carried out by the party wall surveyor before works start); CDM (Construction, Design and Management Regulations 2015) — CHECKLIST: 15. CDM duty holder assessment: is this a notifiable project? (A project is notifiable to the Health and Safety Executive (HSE) if: the construction phase will last more than 30 working days AND have more than 20 workers simultaneously at any point; OR the construction work will exceed 500 person-days; most full London house refurbishments with extension involve multiple trades over 3-6 months and will exceed the 500 person-day threshold — check with the CDM Principal Designer); 16. CDM Principal Designer appointed in writing (for all projects with more than one contractor — and for any project where a client appoints a Principal Contractor — a CDM Principal Designer must be appointed in writing; the Principal Designer coordinates health and safety in the pre-construction phase and prepares the Pre-Construction Information pack for the Principal Contractor); 17. Pre-Construction Information pack prepared and issued to the Principal Contractor; 18. HSE notification (F10) submitted online if the project is notifiable; 19. Principal Contractor's Construction Phase Plan confirmed before works begin. Contractor selection — CHECKLIST: 20. Tender documents prepared (full tender pack issued to all tenderers: drawings, specification, schedule of works, contract conditions, programme requirements, contract sum analysis breakdown format); 21. Three or more compliant tender returns received and reviewed (all tenders are for the same scope and specification — like-for-like; all tenderers have visited the site; all tenders itemise exclusions and assumptions; all tenders include or clearly state their VAT status); 22. Tender clarification meeting held with preferred contractor (pre-award clarification of the scope, programme, specification assumptions, provisional sums, and any items priced as PC (Prime Cost) sums in the tender; confirm all PC sums are realistic and not underestimated to make the tender appear competitive); 23. Contractor's insurances confirmed: public liability insurance (minimum £2m — ideally £5m; check the certificate of insurance names the project address or is a general policy); employer's liability insurance (where the contractor employs staff); contract works insurance (all-risks cover for the works during the construction phase — confirm this is in place before work begins); 24. Contractor's regulatory compliance confirmed: CIS (Construction Industry Scheme) registration (confirm the contractor is registered under HMRC's CIS scheme as a subcontractor or contractor); HMRC CIS deduction where required (the homeowner may not be a CIS payer in their private capacity — confirm the contractor's CIS position); Gas Safe registration (where gas works are proposed — confirm the contractor's Gas Safe registered engineer's registration number); NICEIC or similar approved body registration (where electrical works are proposed — confirm the contractor's Part P certification scheme membership). Contract — CHECKLIST: 25. Contract signed by both parties (a suitable written contract is in place before work begins; suitable contract forms for a London home renovation include: JCT Home Owner Contract 2011 (JCT HOC 2011 — a simple, short form designed for homeowner projects without an architect contract administrator); JCT Minor Works Building Contract 2016 (JCT MW 2016 — a more formal contract with a contract administrator; suitable where an architect or project manager is administering the contract on behalf of the homeowner); JCT Intermediate Building Contract 2016 (JCT IC 2016 — for larger projects); 26. Contract sum confirmed (the agreed contract sum, based on the tender return and the pre-award clarifications, is clearly stated in the contract); 27. Contract sum analysis / schedule of values received from contractor (the breakdown of the contract sum by work package or stage — required for the stage payment schedule); 28. Payment schedule agreed (the timing and method of interim payments — typically stage payments aligned to construction progress milestones; or monthly valuations certified by the architect; the contract must comply with the Housing Grants, Construction and Regeneration Act 1996 payment provisions); 29. Retention agreed (where a retention is to be held: amount (typically 3-5% of the contract sum); release mechanism (50% of the retention released at practical completion; 50% at the end of the defects liability period); 30. Defects liability period confirmed (typically 6-12 months from practical completion — the period during which the contractor is obligated to return to make good any defects that appear in the works).
Phase 3: Pre-start on-site tasks — the week before work begins
Logistics and preparation — CHECKLIST: 31. Site access route confirmed and agreed with the contractor (for a London terraced house, the primary site access is often through the house, through a side gate, or through the rear garden; the route for skips, materials deliveries, concrete truck access (where required — for foundation concrete or screed), and scaffold erection must be planned and confirmed before work begins; any access restrictions — underground utilities, narrow road access, residents' parking restrictions, skip permit requirement — must be resolved); 32. Skip permit obtained (in London, a skip placed on the public highway requires a skip licence from the London Borough — apply through the LABC or the skip hire company; lead time typically 5-10 working days; the permit specifies the permitted size and the permitted location of the skip); 33. Scaffolding permit obtained where required (for scaffolding that occupies the public highway or a parking space — a Section 169 licence from the London Borough; apply at least 4 weeks before scaffold erection date); 34. Neighbours notified (in addition to the legal requirements of the party wall notices, it is good practice to write to all immediately adjacent neighbours — within 2-3 properties each side and across the rear — before works begin: brief letter explaining the works, the approximate duration, the working hours, and a contact number for concerns; this reduces neighbourly disputes during the construction phase); 35. Working hours agreed with the contractor and compliant with the London Borough's Code of Construction Practice: standard permitted working hours for a London renovation project: Monday to Friday 08:00-18:00; Saturday 08:00-13:00; no works on Sundays or Bank Holidays; noisy works (drilling, breaking out, concrete cutting): typically restricted to Monday to Friday 08:00-17:00; the contractor must comply with the Borough's Code of Construction Practice — confirm the specific permitted hours for the Borough in which the property is located); 36. Existing utility services located and protected (gas, water, electricity, and telecoms services entering the property must be identified, marked, and — where they pass through the area of the works — protected from accidental damage; CCTV survey of the drain (pre-start drain CCTV) is strongly recommended before any excavation near existing drains — to establish the pre-start condition of the drain and to identify any pre-existing defects that would otherwise be attributed to the construction works); 37. Party wall surveyor site visit before works (the party wall surveyor carries out a schedule of condition inspection of the adjoining owner's property immediately before any notifiable party wall works begin — to photograph and record the pre-start condition as the baseline for any future claims); 38. Materials procurement confirmed (where the contractor is responsible for procuring long-lead-time materials — structural steel (typically 3-6 weeks from order to delivery), windows and glazed doors (8-16 weeks for proprietary aluminium bi-fold or sliding patio doors; 12-20 weeks for bespoke timber windows), roof lanterns (6-12 weeks for proprietary; 12-20 weeks for bespoke), kitchen and sanitary ware (4-12 weeks) — confirm these items have been ordered before work begins; a long-lead-time structural steel order placed too late will halt the project when the structural opening stage is reached); 39. Formal start on site confirmed in writing with the contractor (the date of the formal commencement of the construction phase should be confirmed in writing — this is the date from which: the construction phase begins under CDM; the construction phase plan is effective; interim payment dates are calculated; the programme milestones run); 40. Building Control inspector notified of commencement (the LABC must be notified of the intended commencement of building works at least two days before work starts — this is a legal requirement under the Building Regulations; notify the LABC or the approved inspector by the method specified in the Building Regulations approval).
Frequently Asked Questions
Do I need a written contract for a London home renovation?▼
When do I need to serve party wall notices for a London home renovation?▼
What insurances must a contractor have for a London home renovation?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.