Why London Homes Experience Foundation Problems
LONDON CLAY IS A HIGHLY PLASTIC, SHRINK-SWELL CLAY (PLASTICITY INDEX TYPICALLY 25-40%) THAT CHANGES VOLUME SIGNIFICANTLY WITH MOISTURE CONTENT CHANGES. THIS CREATES TWO DISTINCT FOUNDATION FAILURE MECHANISMS:
SHRINKAGE SUBSIDENCE (MOST COMMON IN LONDON): DURING PROLONGED DRY PERIODS (DROUGHTS), LONDON CLAY LOSES MOISTURE AND SHRINKS. WHERE TREE ROOTS EXTRACT MOISTURE FROM THE CLAY ADJACENT TO OR BENEATH A FOUNDATION, THE CLAY SHRINKS AND THE FOUNDATION SETTLES. THE SETTLEMENT IS TYPICALLY GREATEST NEAR THE TREE AND REDUCES AWAY FROM IT — CREATING DIFFERENTIAL SETTLEMENT, WHICH CAUSES CRACKING IN THE SUPERSTRUCTURE.
TREE SPECIES MOST ASSOCIATED WITH LONDON RESIDENTIAL SUBSIDENCE: - POPLARS AND WILLOWS (GREATEST MOISTURE DEMAND — HIGH-RISK WITHIN 25-35M OF BUILDING) - OAKS (HIGH MOISTURE DEMAND — HIGH-RISK WITHIN 20-25M) - LIMES, HORSE CHESTNUTS, ELMS, ASH (MEDIUM-HIGH RISK) - FRUIT TREES, APPLE, PLUM, CHERRY (LOWER RISK — USUALLY 3-6M INFLUENCE)
NHBC APPENDIX A (HOUSE-BUILDING STANDARDS RELATING TO TREES) PROVIDES TABLES OF SAFE DISTANCES BETWEEN TREE SPECIES AND FOUNDATIONS IN SHRINKABLE CLAY.
HEAVE: THE REVERSE PROBLEM — WHERE A TREE IS REMOVED, THE CLAY GRADUALLY REHYDRATES AND SWELLS OVER A PERIOD OF YEARS TO DECADES. HEAVE CAN CAUSE UPWARD MOVEMENT OF FOUNDATIONS — PARTICULARLY DAMAGING WHERE FOUNDATIONS ARE SHALLOW AND THE HEAVE FORCES ARE SIGNIFICANT. HEAVE IS PARTICULARLY DANGEROUS FOR BASEMENT SLABS AND GROUND FLOOR SLABS ON LONDON CLAY.
BRICKWORK CRACKING — IDENTIFYING SEVERITY: THE BRE\'S CLASSIFICATION OF CRACK WIDTH IN BUILDINGS (BRE DIGEST 251) PROVIDES A USEFUL FRAMEWORK: - CATEGORY 0: HAIRLINE — NOT SIGNIFICANT - CATEGORY 1: FINE (UP TO 1MM) — MINOR - CATEGORY 2: SLIGHT (UP TO 5MM) — EASILY FILLED, MAY BE COSMETIC OR MAY INDICATE MOVEMENT - CATEGORY 3: MODERATE (5-15MM) — REQUIRES INVESTIGATION BY STRUCTURAL ENGINEER - CATEGORY 4: SEVERE (15-25MM) — STRUCTURAL DAMAGE POSSIBLE, STRUCTURAL ENGINEER ESSENTIAL - CATEGORY 5: VERY SEVERE (OVER 25MM) — SERIOUS STRUCTURAL DAMAGE, IMMEDIATE STRUCTURAL ENGINEER AND BUILDING CONTROL NOTIFICATION CATEGORY 3 AND ABOVE SHOULD ALWAYS INVOLVE A CHARTERED STRUCTURAL ENGINEER AND TYPICALLY A GEOTECHNICAL ASSESSMENT.
Investigation Before Underpinning
UNDERPINNING IS AN IRREVERSIBLE AND EXPENSIVE PROCESS — IT SHOULD NEVER BE UNDERTAKEN WITHOUT THOROUGH INVESTIGATION CONFIRMING IT IS THE CORRECT SOLUTION.
STRUCTURAL SURVEY: A RICS LEVEL 3 (FULL BUILDING SURVEY OR STRUCTURAL SURVEY) FROM A CHARTERED STRUCTURAL ENGINEER OR BUILDING SURVEYOR — NOT A LEVEL 2 (HOMEBUYER REPORT) WHICH IS INSUFFICIENT FOR ASSESSING SUBSIDENCE. THE SURVEY SHOULD INCLUDE: CRACK MONITORING (CRACK GAUGES APPLIED OVER A MONITORING PERIOD OF 3-12 MONTHS TO ESTABLISH WHETHER MOVEMENT IS ONGOING, HISTORIC, OR CYCLICAL SEASONAL); INVESTIGATION OF DRAINAGE (FAILED DRAINS ARE A COMMON CAUSE OF FOUNDATION SOFTENING — DRAIN CAMERA SURVEY RECOMMENDED); AND ASSESSMENT OF TREE PROXIMITY.
GEOTECHNICAL INVESTIGATION: FOR SIGNIFICANT FOUNDATION PROBLEMS, A GROUND INVESTIGATION IS REQUIRED — TRIAL PITS TO EXPOSE THE EXISTING FOUNDATION BEARING LEVEL AND CLAY CONDITION; BOREHOLES FOR DEEPER INVESTIGATION; AND LABORATORY TESTING OF CLAY SAMPLES FOR PLASTICITY INDEX, SHRINKAGE LIMIT, AND MOISTURE CONTENT PROFILE.
DRAIN CAMERA SURVEY: UNDERGROUND DRAIN FAILURE IS A COMMON CAUSE OF FOUNDATION SOFTENING IN LONDON — PARTICULARLY WHERE OLD CLAY PIPE DRAINAGE HAS DETERIORATED OR BEEN DISPLACED BY ROOT PENETRATION. A CCTV DRAIN CAMERA SURVEY (DYNO-ROD, ENV-SURVEY, OR LOCAL DRAINAGE SURVEYOR — £150-350) IS HIGHLY RECOMMENDED BEFORE ATTRIBUTING FOUNDATION PROBLEMS TO CLAY SHRINKAGE.
INSURANCE NOTIFICATION: BEFORE COMMISSIONING INVESTIGATION WORKS ON SUSPECTED SUBSIDENCE, NOTIFY YOUR BUILDINGS INSURANCE COMPANY. MOST POLICIES COVER SUBSIDENCE — FAILURE TO NOTIFY PROMPTLY CAN RESULT IN THE INSURER DECLINING THE CLAIM. THE INSURER MAY APPOINT THEIR OWN LOSS ADJUSTER AND STRUCTURAL ENGINEER. DO NOT START UNDERPINNING OR SIGNIFICANT REPAIR WORKS WITHOUT INSURER APPROVAL IF A CLAIM IS BEING MADE.
Underpinning Methods
WHERE UNDERPINNING IS CONFIRMED AS NECESSARY, THE FOLLOWING METHODS ARE IN USE FOR LONDON RESIDENTIAL BUILDINGS:
MASS CONCRETE UNDERPINNING (TRADITIONAL PIT METHOD): THE OLDEST AND MOST WIDELY USED METHOD FOR LONDON VICTORIAN TERRACES. THE PROCESS: EXCAVATE IN ALTERNATE SHORT BAYS (TYPICALLY 1.0-1.5M LENGTH) BENEATH AND BEYOND THE EXISTING FOUNDATION; FORM A CONCRETE STUB OF SUFFICIENT DEPTH AND WIDTH TO BEAR ON DEEPER, LESS SUSCEPTIBLE CLAY; BACKFILL WITH WEAK MIX CONCRETE (C20/P OR ST2) TO FILL THE VOID BETWEEN THE NEW CONCRETE TOP AND THE EXISTING FOUNDATION SOFFIT; LET EACH BAY CURE BEFORE WORKING ON ADJACENT BAYS. THE ALTERNATING BAY SEQUENCE ENSURES THE EXISTING FOUNDATION IS NEVER UNSUPPORTED FOR MORE THAN ONE BAY LENGTH AT A TIME.
DEPTH: MASS CONCRETE UNDERPINNING IS TYPICALLY TAKEN TO 1.5-3.0M BELOW GROUND LEVEL IN LONDON CLAY SITUATIONS — BELOW THE ACTIVE ZONE OF SEASONAL MOISTURE VARIATION (APPROXIMATELY 1.0-1.5M IN LONDON).
COST: £500-1,500 PER LINEAR METRE OF UNDERPINNED WALL, DEPENDING ON DEPTH AND ACCESS. TYPICAL FULL TERRACE FRONT WALL UNDERPINNING (10-12M): £8,000-20,000.
MINI-PILE UNDERPINNING: SMALL-DIAMETER PILES (TYPICALLY 150-200MM DIAMETER) DRILLED THROUGH OR ADJACENT TO THE EXISTING FOUNDATIONS, SOCKETED INTO A STABLE STRATUM BELOW THE ACTIVE CLAY ZONE OR INTO THE UNDERLYING SAND/GRAVEL/TERRACE DEPOSITS. CONNECTED TO THE EXISTING FOUNDATION VIA A NEW REINFORCED CONCRETE NEEDLE BEAM OR HEADPLATE.
ADVANTAGES OVER MASS CONCRETE: CAN BE USED WHERE EXCAVATION DEPTH IS LIMITED (ADJACENT PARTY WALL, HIGH GROUNDWATER, EXISTING SERVICES); LESS DISRUPTION TO OCCUPIED BUILDINGS; FASTER INSTALLATION; CAN TREAT DEEPER PROBLEMS INACCESSIBLE TO MASS CONCRETE PITS.
COST: £1,500-3,500 PER PILE (TYPICALLY 5-20 PILES PER PROJECT). TOTAL PROJECT COST £15,000-50,000+ FOR COMPLEX SITUATIONS.
RESIN INJECTION: A NEWER TECHNIQUE — TWO-PART EXPANDING STRUCTURAL RESIN INJECTED UNDER LOW PRESSURE INTO THE GROUND VIA THIN TUBES. THE RESIN EXPANDS AND SETS, INCREASING GROUND DENSITY AND LIFTING THE FOUNDATION. SUITABLE FOR UNIFORMLY SETTLING FOUNDATIONS (NOT DIFFERENTIAL SETTLEMENT ON CLAY DUE TO TREES). NOT WIDELY ACCEPTED BY UK STRUCTURAL ENGINEERS FOR CLAY SHRINKAGE PROBLEMS. COST: £5,000-20,000 DEPENDING ON SCALE.
Basement Underpinning for Extensions
UNDERPINNING FOR BASEMENT CONVERSION IS A SPECIFIC AND VERY DIFFERENT USE OF THE TECHNIQUE — HERE, UNDERPINNING IS NOT A REMEDIAL MEASURE BUT AN INTENTIONAL STRUCTURAL METHOD TO LOWER THE FLOOR LEVEL BENEATH AN EXISTING HOUSE.
THE PROCESS (SIMPLIFIED): EXCAVATE IN ALTERNATING BAYS BENEATH THE EXISTING FOUNDATION AND LOWER THE FLOOR LEVEL TO THE DESIRED BASEMENT DEPTH; FORM REINFORCED CONCRETE UNDERPINNING BEAMS (NOT MASS CONCRETE) CONNECTED TO THE EXISTING FOUNDATION; CAST A REINFORCED CONCRETE RAFT FLOOR SLAB AT THE NEW LOWER LEVEL; INSTALL WATERPROOFING SYSTEM (NEWTON SYSTEM 500 CDPM MEMBRANE, BASEDRAIN DRAINAGE CAVITY, AND SUMP PUMP TITAN 210 OR SIMILAR); COMPLETE THE BASEMENT FIT-OUT.
BASEMENT UNDERPINNING IS HIGHLY SPECIALIST WORK REQUIRING: CHARTERED STRUCTURAL ENGINEER DESIGN; PARTY WALL ACT SECTION 6 NOTICES (FOUNDATION EXCAVATION WITHIN 3M OF NEIGHBOURS); BUILDING REGULATIONS FULL PLANS APPROVAL; CDPHB HEALTH AND SAFETY COMPLIANCE (SIGNIFICANT EXCAVATION); AND SPECIALIST CONTRACTORS WITH RELEVANT EXPERIENCE (LOOK FOR MEMBERSHIP OF THE SPECIALIST ENGINEERING CONTRACTORS\' GROUP OR GROUND ENGINEERING CONTRACTORS ASSOCIATION).
COST: LONDON BASEMENT CONVERSION INCLUDING UNDERPINNING — £70,000-150,000+ FOR A TYPICAL 3-BEDROOM TERRACE GROUND FOOTPRINT. NOT UNIVERSALLY COST-EFFECTIVE — REQUIRES CAREFUL FEASIBILITY ASSESSMENT.
Insurance, Costs, and Finding Contractors
INSURANCE IMPLICATIONS OF SUBSIDENCE:
BUILDINGS INSURANCE COVERAGE: STANDARD UK BUILDINGS INSURANCE POLICIES COVER SUBSIDENCE AS A NAMED PERIL. TYPICAL EXCESSES FOR SUBSIDENCE CLAIMS ARE HIGHER THAN FOR OTHER PERILS — £1,000-2,500 EXCESS IS COMMON. THE INSURER WILL APPOINT A LOSS ADJUSTER AND MAY APPOINT THEIR OWN STRUCTURAL ENGINEER AND GEOTECHNICAL ASSESSOR.
FUTURE INSURANCE AFTER SUBSIDENCE: ONCE A PROPERTY HAS A HISTORY OF SUBSIDENCE (WHETHER CLAIMED OR REMEDIATED), IT IS CONSIDERED HIGH-RISK BY INSURERS. STANDARD POLICIES MAY EXCLUDE SUBSIDENCE GOING FORWARD. SPECIALIST INSURERS (AVIVA SPECIALIST PROPERTY, HISCOX, OR SUBSIDENCE-SPECIALIST BROKERS) PROVIDE COVER FOR PROPERTIES WITH SUBSIDENCE HISTORY — AT HIGHER PREMIUMS.
CONVEYANCING IMPLICATIONS: SUBSIDENCE HISTORY MUST BE DISCLOSED ON PROPERTY INFORMATION FORMS (TA6) AT RESALE. A CLOSED SUBSIDENCE CLAIM (FULLY REMEDIATED AND MONITORED CLEAR OF MOVEMENT) IS MORE SALEABLE THAN AN UNRESOLVED ONE. ENSURE ALL STRUCTURAL ENGINEER REPORTS, MONITORING DATA, COMPLETION CERTIFICATES, AND GUARANTEES ARE RETAINED.
FINDING COMPETENT UNDERPINNING CONTRACTORS: - GROUND ENGINEERING SPECIALISTS: KELLER, AARSLEFF GROUND ENGINEERING, WSB GROUP, BALFOUR BEATTY GROUND ENGINEERING FOR LARGE PROJECTS - RESIDENTIAL SPECIALISTS: LOCAL CONTRACTORS RECOMMENDED BY STRUCTURAL ENGINEERS — AVOID GENERALIST BUILDERS FOR UNDERPINNING WORK - QUALIFICATIONS: LOOK FOR NHBC REGISTERED BUILDERS; CIOB OR ICE MEMBERSHIP RELEVANT FOR PROJECT OVERSIGHT; MEMBERSHIP OF SPECIALIST ENGINEERING CONTRACTORS\' (SEC) GROUP
COST SUMMARY: - STRUCTURAL SURVEY AND MONITORING: £500-1,500 - GEOTECHNICAL INVESTIGATION: £1,500-5,000 - DRAIN SURVEY: £150-350 - MASS CONCRETE UNDERPINNING (PER LINEAR METRE): £500-1,500 - MINI-PILE UNDERPINNING (PER PILE): £1,500-3,500 - FULL FRONT WALL UNDERPINNING (10-12M, LONDON TERRACE): £8,000-20,000
Frequently Asked Questions
How do I know if my Victorian terrace needs underpinning?▼
Does my insurance cover underpinning?▼
Do I need planning permission for underpinning?▼
How long does underpinning take?▼
How much does underpinning cost in London?▼