Snagging at the End of a London Building Project: What to Check and How

Snagging is the process of identifying and recording defects, incomplete works, or items that do not meet specification at the end of a building project — before formal handover. It is one of the most important stages of any London renovation or extension, and one that is frequently rushed or poorly managed. This guide explains what snagging covers, what to look for, and how to protect your position as a client.

Key Takeaways

  • ✓Snagging is the systematic identification of defects before practical completion — a conscientious contractor should produce their own snagging list before the client walk-through
  • ✓Check every element systematically: external, floors, walls/ceilings, joinery, kitchen, bathrooms, and M&E
  • ✓Document all snags in writing with photographs, agreed remediation, and target dates — verbal agreements are not sufficient
  • ✓Withhold retention (typically 5%) until all snagging items are resolved and the defects liability period has passed
  • ✓Shrinkage cracking at plasterboard joints in the first heating season is a valid defects liability call-back — not a reason to withhold practical completion
Carpenter cutting timber with a mitre saw inside a house under renovationIllustrative image

What Snagging Is and When It Happens

Snagging refers to the systematic identification of defects, incomplete works, and non-conformances at the end of a construction project — before practical completion is formally certified.

  • **Practical completion vs. final completion:**
  • In most standard building contracts, there are two key completion milestones:
  • •**Practical completion** — the point at which the works are substantially complete and the client can take possession and use the property. Minor snags may remain at this point.
  • •**Final completion** — the point at which all outstanding snagging items have been resolved and the contractor's liability for defects under the contract is satisfied.

Between practical completion and final completion, a 'defects liability period' (typically 6–12 months in residential contracts) runs during which the contractor is obliged to return and rectify defects that appear.

**Who should produce the snagging list:** A conscientious contractor should produce their own internal snagging list and resolve all items before presenting the works to the client. The client walk-through should then be the final check — not the first time defects are being recorded. A contractor who presents works with obvious unresolved defects and waits for the client to find them is not operating to a professional standard.

What to Check at the Snagging Walk-Through

A thorough snagging walk-through should cover every room and every element of the works systematically. The following is a room-by-room and element-by-element guide:

  • **External and structural:**
  • •External finish — render, masonry, or cladding: no cracks, missing pointing, or poorly finished sections
  • •Roof covering — no missing tiles/slates visible, no poorly dressed flashing, lead correctly formed at abutments and valleys
  • •Rooflights and dormer windows — operation tested, no condensation between panes, flashings correctly formed
  • •External doors — opening, closing, and locking correctly; threshold weathertight
  • •Windows — opening lights operate correctly; no visible gaps in seals
  • **Floors:**
  • •No hollow or loose tiles (tap test)
  • •No squeaking boards (walk test)
  • •Junctions between different floor finishes are neat and level
  • •No chipping or cracking of floor tiles at waste positions, door thresholds, or heavy furniture positions
  • **Walls and ceilings:**
  • •No cracking at joints between plasterboard sheets (hairline cracking at taped joints is common and almost always opens up in the first heating season — but significant cracks, hollowing plaster, or cracking at structural junctions should be flagged)
  • •No visible shadows on painted surfaces from poor plasterboard fixing
  • •Ceiling/wall junctions: neat, no gaps at coving or no-coving junction
  • •Outlet and switch face plates: level, flush, fully fixed — no exposed gap at back box
  • **Joinery:**
  • •All doors open and close smoothly without catching or rattling
  • •Door furniture (handles, hinges, latches) complete and tight
  • •Skirting board and architrave: mitred corners tight, no visible gaps, fully fixed — no movement
  • •Staircase: balustrade rigid (no movement), baluster spacing compliant (must not allow a 100mm sphere to pass through — Building Regulations requirement), tread and riser joints tight
  • **Kitchens:**
  • •All cabinet doors and drawers open and close without catching; soft-close mechanisms operating correctly
  • •Worktop joints tight and sealed
  • •Upstand seal between worktop and wall tile fully sealed — no gap
  • •Appliances connected and operational
  • •Splash-back complete and fully grouted/sealed
  • **Bathrooms:**
  • •All grout lines complete — no voids or cracked grout, particularly at shower enclosures
  • •Silicone seal complete at all junctions — bath-to-wall, shower tray-to-wall, basin-to-wall. Silicone should not be cracked, gapped, or missing
  • •WC pan firmly fixed to floor — no movement
  • •All tap and valve fittings: tight, no drips
  • •Shower enclosure: glass panels fully installed and sealed; door opens and closes without dragging on tray
  • •Towel rail and accessories: fixed and in correct position
  • **Mechanical and electrical:**
  • •All sockets and switches: operational (test with a phone charger)
  • •All light fittings: operational and correctly fitted
  • •Heating system: operational, all radiators or UFH zones confirmed working
  • •Ventilation: extractor fans operational in kitchen and bathrooms
  • •Any alarm systems: operational and installed as specified

How to Document and Manage Snagging Items

  • **Documenting snags:**
  • Snags should be documented in writing — not verbally. The best approach is a written (or photographed) snagging list with:
  • •Item description
  • •Location (room/element)
  • •Photograph where helpful
  • •Agreed remediation (what will be done)
  • •Target date for completion

**Agreeing the snagging list:** Both client and contractor should agree the snagging list before it is finalised. Items where there is a disagreement about whether something is a defect or a design/specification issue should be identified and discussed explicitly — not left ambiguous.

**Retention:** In most standard residential building contracts, a proportion of the contract sum (typically 5%) is retained by the client until the defects liability period has passed and all snagging items are complete. This gives the contractor a financial incentive to complete the snagging and return for any post-completion defects. If no retention is provided for in your contract, the leverage to get snagging items completed is reduced.

  • **What is NOT a snag:**
  • Some things that clients sometimes raise as snags are actually:
  • •**Shrinkage cracking** at plasterboard joints — almost universal in the first heating season; the contractor should return to fill and redecorate (this is a valid defect liability call-back, not something that should hold up practical completion)
  • •**Naturally occurring variation** in natural materials (stone, slate, timber) — variation in colour and character is inherent; it is only a defect if it falls outside the agreed specification or sample
  • •**Client change of mind** about design decisions that were agreed before works began — this is a variation, not a snag, and will typically require payment

**When snagging reveals more significant issues:** If the snagging walk-through reveals defects that go beyond minor finishing items — significant structural cracking, failed waterproofing, non-compliant work — these should be treated as a dispute rather than a snagging item, and independent advice should be sought. An independent building surveyor or specialist can assess whether the defect is within acceptable tolerance, requires remediation, or constitutes a contract breach.

Frequently Asked Questions

Should I pay the final amount before snagging is complete?▼
No. Payment of the final contract sum (or the retained amount, if your contract provides for retention) should follow satisfactory completion of all snagging items, not precede it. Once the final payment is made and the contractor leaves site, your leverage to get remaining items completed significantly reduces. The standard approach is to withhold the retention (typically 5%) until the defects liability period has passed and all call-back items are resolved.
How long should a snagging list take to resolve?▼
Minor snagging items (touch-up decoration, adjusting a door catch, applying a silicone bead) should be resolved within 2–4 weeks of practical completion. More significant snags that require ordering materials or coordinating a trade should be resolved within 4–8 weeks. If a contractor leaves snagging items unresolved for more than 8 weeks without a clear plan and timeline, you should seek independent advice on your contractual options.
Can I use an independent snagging inspector?▼
Yes. Independent snagging inspectors are available (typically £300–£600 for a residential property inspection) and produce a professional photographic snagging report. An independent report is particularly useful on larger projects (over £100,000 in contract value) or where the client does not feel confident assessing the quality of work themselves. Some clients commission an independent report before the contractor's own snagging walk-through, which can be a useful benchmark.

Important Note

This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. To talk through your own project, book a project review.

Was this guide helpful? Share it:

Have a question about your project?

Message us on WhatsApp or call — we reply during working hours (Mon–Fri 8am–6pm, Sat 9am–2pm).

Ready to Discuss Your Project?

Project review, scope clarity and a clear next step. Greater London and the M25.

Call nowWhatsAppProject Review