Contents
What the Party Wall Act covers and who needs to serve notices
**What the Act is for**:
The Party Wall etc. Act 1996 is a piece of civil legislation that provides a framework for resolving disputes between neighbours in advance of construction work. Its purpose is not to prevent building work — it is to ensure that work affecting shared walls, boundary walls, and excavations near neighbouring foundations is properly notified, the existing condition of neighbouring property is documented before the work starts, and any dispute about how the work should proceed is resolved by an Award (a legally binding document) rather than by litigation.
The Act applies to England and Wales. It does not apply in Scotland or Northern Ireland (which have different arrangements).
**What the Act covers — the three sections**:
*Section 2 — Works to a party wall or party structure*:
A party wall is a wall that stands on the boundary between two properties and is used by both owners — typically the shared wall between two terraced or semi-detached properties. A party structure can also include a floor or ceiling separating flats. Works covered by Section 2 that require a notice include:
- •Cutting into the party wall (for example, to carry a new steel beam on the wall, or to insert a new padstone for a steel)
- •Raising the party wall (building the wall higher)
- •Demolishing and rebuilding the party wall
- •Underpinning the party wall
- •Weathering the party wall (applying new render or coping to the top of a shared boundary wall)
- •Removing projections of a chimney breast from the party wall
- •Making good the faces of the party wall to the required fire resistance and sound insulation standard after adjacent works
Most loft conversions and rear extensions trigger Section 2 if the party wall is being cut into for new steels, raised, or altered. Simply building up to the party wall without cutting into it does not trigger Section 2.
*Section 1 — Building a new wall at or astride the boundary*:
If a building owner wants to build a new wall at the line of junction between their property and the adjoining owner's property (or astride the line — partly on both properties by agreement), a Section 1 notice is required. For most London extension projects, the new extension wall is built entirely within the building owner's property (not at or astride the boundary), so Section 1 is not commonly triggered. It becomes relevant when the design requires a new wall to sit on or close to the boundary.
*Section 6 — Excavation within 3m or 6m of an adjoining structure*:
- Section 6 requires notice when a building owner proposes to excavate:
- •Within 3m of the adjoining owner's structure (house, outbuilding, garden wall) AND the excavation will go deeper than the bottom of the adjoining owner's foundations
- •Within 6m of the adjoining owner's structure AND the excavation will intersect a 45-degree line drawn down from the bottom of the adjoining owner's foundations
In London, where foundations of Victorian and Edwardian terraces are typically 0.9–1.5m deep, most rear extension excavation (strip foundations at 0.9–1.2m) within 3m of the party wall will trigger Section 6. Basement excavations almost always trigger Section 6. This is the most commonly missed party wall trigger in London domestic projects.
**Who serves the notice and who pays**:
The building owner (the person undertaking the works) is legally responsible for serving the party wall notices. The building owner pays the costs of the party wall process — including the adjoining owner's surveyor's fees if the adjoining owner appoints one (the building owner pays both surveyors).
The notices must be served on all adjoining owners — 'adjoining owner' means any owner of land, buildings, storeys, or rooms adjoining the premises where the works are to be carried out. In a mid-terrace property, there are typically two adjoining owners (one each side); each must receive their own notice.
**The notice periods**:
| Notice type | Minimum notice period before work can start | |---|---| | Section 2 (party wall works) | 2 months | | Section 1 (new wall at boundary) | 1 month | | Section 6 (excavation) | 1 month |
These are minimum periods — the work cannot start until either the adjoining owner consents in writing (concurs) or an Award has been made. The notice periods run from the date of service of the notice (not from the date of the response).
The party wall process — consent, dispute, surveyors, and the Award
**The response options after a notice is served**:
Once a party wall notice is served, the adjoining owner has three options:
*Option 1 — Consent (concur)*: The adjoining owner signs and returns the consent form acknowledging the notice and agreeing to the proposed works. Where the adjoining owner consents, no surveyors are needed and no Award is produced — the works can proceed after the notice period expires. Consent is free and fast. However, even when consent is given, the building owner should still commission a Schedule of Condition (a photographic and written record of the adjoining property's existing condition) before works start — this is not a legal requirement where consent is given, but it protects both parties by documenting the pre-works condition of the neighbour's property.
*Option 2 — No response (deemed dispute)*: If the adjoining owner does not respond within 14 days of service of the notice, a dispute is deemed to have arisen under the Act. The building owner can then proceed as if a dispute has arisen — appointing a party wall surveyor.
*Option 3 — Dissent (dispute)*: The adjoining owner formally dissents (objects) to the proposed works. A dispute is now in progress. This does not mean the works are stopped — it means the dispute must be resolved by the surveyor process before work on the party wall elements can proceed.
**The surveyor appointment process in a dispute**:
When a dispute arises (by dissent or deemed dispute), the Act provides for the dispute to be resolved by surveyors:
*Option A — Agreed surveyor*: Both the building owner and adjoining owner appoint the same surveyor to act for both parties. This is the most efficient and cost-effective option. The agreed surveyor acts impartially and produces the Award. Agreed surveyor fees: typically £900–£1,600 for a standard London domestic project (all in — Schedule of Condition, Award, inspections); paid by the building owner.
*Option B — Two surveyors*: The building owner appoints their own surveyor; the adjoining owner appoints their own surveyor. The two surveyors (who must be party wall surveyors — they do not have to be chartered surveyors, but they must understand the Act) work together to agree and produce the Award. If they cannot agree, they appoint a third surveyor (selected in advance at the start of the process) who makes the binding decision. Building owner's surveyor fees: £800–£1,500; adjoining owner's surveyor fees: £700–£1,400 (both paid by the building owner). Total cost in a standard domestic project: £1,500–£2,900 for a single adjoining owner. Each additional adjoining owner adds approximately £400–£900.
**The Schedule of Condition**:
A Schedule of Condition is a photographic and written record of the current condition of the adjoining owner's property — typically the rooms, walls, ceilings, and floors most likely to be affected by the proposed works. The schedule is produced by the party wall surveyor (or the agreed surveyor) before works commence. Its purpose: if the adjoining owner claims damage was caused by the building works, the schedule is the baseline — any damage that appears in the schedule was pre-existing and cannot be attributed to the building works; damage that is absent from the schedule but present after the works can be attributed to the works and the building owner is liable to make good.
**The Award**:
The Party Wall Award (or Award of Party Wall Surveyors) is a legally binding document produced by the surveyor(s) under the Act. A typical Award:
- •Describes the works proposed
- •Sets out the method and conditions under which the works are to be carried out (working hours, access arrangements, noise restrictions, protection measures)
- •Records the Schedule of Condition by reference to the attached photographs and condition record
- •Confirms the building owner's obligations (to make good any damage caused by the works, and to pay the surveyors' fees)
- •Specifies any special conditions relevant to the specific project (e.g., protection of the adjoining owner's drain, requirements for temporary support)
The Award is served on both building owner and adjoining owner. Either party can appeal the Award to the County Court within 14 days of service — in practice, appeals are rare in domestic cases.
**Who cannot be a party wall surveyor**:
The Act states that the parties' own architects, structural engineers, or contractors cannot act as party wall surveyors for that party (because they are not independent). A surveyor instructed by the contractor or architect to act as party wall surveyor should not be relied upon as truly independent — an independent appointment is better for both parties.
Common questions and what happens if you ignore the Act
**The most commonly asked questions**:
*Does the Party Wall Act apply to loft conversions?*
A loft conversion will typically trigger the Party Wall Act if: (a) a steel beam is being inserted into the party wall (carried by the party wall) — common in hip-to-gable conversions and dormer loft conversions where the structural steel bears on the party wall; (b) the party wall is being raised (to achieve adequate head height at the eaves); (c) the loft floor is a party structure (in a flat conversion). A straightforward Velux conversion where no work is carried out on the party wall does not trigger the Act.
*Does the Party Wall Act apply to a rear extension?*
A rear extension will typically trigger Section 6 (excavation) if the foundations are within 3m of the party wall and go deeper than the neighbour's foundations — which, in most London terraces, means almost all rear extension foundation work triggers Section 6. It will also trigger Section 2 if any steels are being carried on the party wall, or if the extension wall is being built up to or into the party wall. Rear extensions that are entirely freestanding and whose foundations are more than 3m from any adjoining structure do not trigger the Act.
*Do I need to serve a notice for a garden wall or fence?*
A boundary garden wall or fence does not trigger the Act unless works are being carried out on the party wall itself (the wall that is shared at the boundary between properties). A free-standing garden wall on one side of the boundary is not a party wall. If the wall is shared (both properties use it as their boundary wall), then works to it may trigger Section 2.
*What if the neighbour refuses to engage?*
If the adjoining owner refuses to appoint a surveyor, the Act provides that the building owner's surveyor can appoint a surveyor on the adjoining owner's behalf. The adjoining owner cannot block the party wall process by simply refusing to engage — the Act has a mechanism to proceed in their absence.
**What happens if you ignore the Act and start work without serving notices?**
Starting work that requires party wall notices without serving them is a civil wrong. The adjoining owner has the right to:
- •Apply to the County Court for an injunction to stop the works immediately
- •If the court grants the injunction, the works must stop until the party wall process is completed (which takes at minimum 1–3 months)
- •Claim compensation for any damage caused to their property
- •Require the building owner to demolish and rebuild structures that were built without the required Award if they encroach on or damage the party wall
In practice, the most damaging consequence of ignoring the Act is the injunction — stopping a live construction project for 3 months while the party wall process is retrospectively completed can add £5,000–£20,000 in delay costs (contractor downtime, prelim extension, rescheduling). Starting without notices also means there is no Schedule of Condition in place — if any damage occurs during the works, the building owner has no baseline to defend themselves against claims.
**The party wall process in a well-managed London project**:
1. *At design stage*: architect and structural engineer identify which elements of the project trigger the Act (Section 2, 6, or both) 2. *At planning application stage or before*: party wall notices prepared and served (allow for 2-month period before works can start) 3. *During the notice period*: adjoining owners respond; if consenting, proceed after notice period; if disputing, appoint surveyors 4. *Before works start*: Schedule of Condition prepared; Award produced and served (if required) 5. *During works*: work on party wall elements proceeds in accordance with the Award conditions 6. *Post-works*: any damage notified promptly; made good by the building owner
A well-managed party wall process is a cost of good neighbourly relations — not an obstacle to building.
Frequently Asked Questions
Can my neighbour stop my building work using the Party Wall Act?▼
Does the Party Wall Act apply to flats?▼
How long does the party wall process take?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.