How Long Does a Loft Conversion Take? A Week-by-Week Guide

The Typical Loft Conversion Journey

A standard loft conversion in London — typically a dormer or hip-to-gable — takes between 8 and 16 weeks on site once work begins. The full project, from first site visit to completion, usually spans 4 to 7 months when design and approvals are included.

This guide breaks down the key stages.

Stage 1: Design and Pre-Construction (4–12 Weeks)

Before any site work begins, the following needs to happen:

Weeks 1–2: Initial assessment and feasibility

  • Site visit to assess head height, roof structure, and access options
  • Architectural brief agreed
  • Concept drawings produced

Weeks 3–5: Design development

  • Planning drawings prepared
  • Structural engineer engaged for initial input
  • Building Regulations pre-application discussions if needed

Weeks 5–8: Approvals

  • Planning application submitted if required (8-week statutory determination period)
  • Building Regulations application submitted (full plans route preferred)
  • Party Wall Notices served if applicable (minimum 2 months' notice)

For permitted development loft conversions, the planning stage may be skipped, reducing pre-construction time significantly.

Stage 2: Procurement and Pre-Start (2–4 Weeks)

Once approvals are in place:

  • Detailed specification agreed
  • Materials and specialist components ordered (steel beams, roof windows, structural timber)
  • Scaffold erected and site set up
  • Pre-start meeting with client

Stage 3: Structural and Roof Works (Weeks 1–4 on Site)

  • Floor structure installed (new structural floor joists or engineered floor system)
  • Dormer or hip-to-gable structure built
  • Roof windows and dormer cheeks installed
  • Roof made weathertight
  • Steel beams installed if structural openings required below

This phase is weather-dependent. Wet or icy conditions slow exterior works.

Stage 4: First-Fix Works (Weeks 4–7)

  • Insulation installed to roof and walls
  • First-fix electrics run (lighting, sockets, smoke detectors)
  • First-fix plumbing run if bathroom is included
  • Staircase structure installed
  • Internal stud partitions built

Stage 5: Boarding and Plastering (Weeks 7–9)

  • Plasterboard fixed to walls and ceiling
  • Wet plaster or skim applied
  • Plaster allowed to dry (minimum 2 weeks before decoration)

Stage 6: Second-Fix and Finishing (Weeks 9–13)

  • Second-fix electrics (sockets, switches, lighting pendants)
  • Second-fix plumbing (bathroom suite, radiators, towel rails)
  • Joinery (skirting, architrave, doors, door frames, window boards)
  • Staircase completed with handrail and balustrade
  • Decoration (client-supplied or contractor)
  • Flooring (client-supplied and installed)
  • Bathroom tiling and finishing

Stage 7: Completion and Sign-Off

  • Building Control inspection and completion certificate
  • Snagging list raised and resolved
  • Handover to client

Total Timeline Summary

Route Pre-Construction On Site Total
Permitted Development 6–8 weeks 8–12 weeks 3–5 months
With Planning Permission 14–20 weeks 8–12 weeks 5–8 months
Complex conversion 16–24 weeks 12–16 weeks 7–10 months

Common Causes of Delay

  • Late approval of structural engineer drawings
  • Party wall disputes or delayed neighbour agreements
  • Changes to design after work has started
  • Materials delays (especially specialist roof windows)
  • Weather during roof opening phase

RCB Design & Build

RCB produces a clear programme at the pre-construction stage so clients know exactly what to expect at each phase. We coordinate planning, Building Control, structural input, and procurement before the first day on site — reducing the risk of delays and keeping the project on track.