Contents
- 1. How beam and block floors work — components, installation sequence, and structural behaviour
- 2. When to specify a beam and block floor instead of a ground-bearing slab — London-specific considerations
- 3. Insulation, Part L compliance, and costs for beam and block floors in London extensions
- 4. Frequently Asked Questions
How beam and block floors work — components, installation sequence, and structural behaviour
**The key components of a beam and block floor**:
- *Precast concrete beams*:
- The structural element — typically a prestressed concrete inverted-T or U-beam (the beam web hangs down; the flanges form the top bearing surface). Standard beam dimensions for residential beam and block:
- •155mm beam depth (the most common for residential spans up to approximately 5.5m)
- •200mm beam depth (for longer spans or heavier loading)
- •Beam centres: typically 305mm apart (dictated by the width of the standard 100mm hollow or aerated concrete infill block, which is 440mm long × 215mm wide × 100mm deep — fitting between beam webs with a 5mm joint each side)
Beams are manufactured by specialist concrete product companies (Forterra; Litecast; Bison) and delivered to site in preset lengths, cut to order. Beams are lifted from the delivery vehicle by hand for shorter lengths (under 3m; manageable for 2 persons) or by crane/HIAB for longer spans.
*Infill blocks*: Concrete infill blocks (typically aerated concrete — Thermalite or Celcon — for lightweight thermal performance; or dense concrete for heavier loading) fill the spaces between the beam webs. Standard infill block: 440mm × 215mm × 100mm. Lightweight aerated infill blocks (Thermalite Hi-Strength or similar) weigh approximately 8–9 kg each and can be handled quickly by one person.
- *Edge beam or dwarf walls*:
- The beam and block floor must be supported at its perimeter on either:
- •The extension's external walls (built to DPC level, then the beams bear onto the wall plate or directly onto the masonry)
- •Dwarf walls (low internal masonry walls built to carry the mid-span bearing points of the beams for longer spans or where the beam must be supported mid-span)
- •Edge beams (concrete or masonry upstand at the foundation perimeter that carries the beam ends)
*Structural screed or topping*: Once the beams and blocks are laid, a structural topping (typically 65mm C25 structural concrete screed with A142 mesh) is poured over the entire floor to bond the beams and blocks into a composite structural element, provide the finished floor level, and create a solid surface for subsequent floor finishes. An alternative is a 'dry lean mix' (no-fines concrete poured between the beams only; the blocks remain separate) — but the structural screed topping is more common for residential construction as it provides a composite structural diaphragm.
**The installation sequence for a beam and block floor in a London extension**:
1. External walls of extension built to DPC level (beam bearing level) 2. Dwarf walls (if required for long spans or beam intermediate support) built to height 3. Ground surface below the floor: remove any organic material; compact; leave ground clear for ventilation void 4. Beams positioned: laid at the specified centres, cut to length where required (beams can be cut with an angle grinder or disc cutter on site; prestressed strands are cut through) 5. Infill blocks placed between beams (working from one end to the other; dry-placed; no mortar between infill blocks and beam flanges) 6. Polythene sheet (DPM) laid over the beam and block floor to prevent screed loss through the gaps and provide a DPC layer 7. Insulation laid: rigid insulation board (PIR or EPS — see insulation options below) placed on top of the DPM 8. A142 mesh (welded steel mesh reinforcement) laid on chairs above the insulation to reinforce the structural screed topping 9. Structural screed: C25 concrete, typically 65mm, poured and levelled (or a liquid self-levelling screed — more expensive but produces a flatter surface) 10. Allow screed to cure: minimum 7 days before foot traffic; 28 days before full structural loading
**Structural behaviour — why beam and block works as a structural floor**:
The T-beams are prestressed during manufacture — high-tensile steel strands are tensioned before the concrete is cast around them; when the concrete cures and the tension is released, the beams are placed into a permanent state of 'pre-compression' (the concrete is pre-squeezed). This pre-compression means the beams can carry bending loads without the concrete going into tension (concrete is weak in tension — prestressing keeps it in compression throughout). A prestressed concrete beam can span significantly further than a plain reinforced concrete beam of the same depth.
Once the structural screed topping is cast, the beams, blocks, and screed act as a composite T-section — much stiffer and stronger than the beams alone. The result is a structural floor capable of carrying the residential imposed loading (1.5 kN/m²) across spans that would require a deep conventional concrete slab if ground-bearing.
When to specify a beam and block floor instead of a ground-bearing slab — London-specific considerations
**Ground-bearing slab vs. beam and block — the decision matrix**:
A ground-bearing slab sits directly on the compacted ground (no void below). It works structurally by bearing the load onto the ground and relying on the ground to provide a stable, evenly distributing support. A beam and block floor spans from support to support (the extension walls or dwarf walls) — the ground below does not contribute to the structural support of the floor.
- This fundamental difference means:
- •A ground-bearing slab REQUIRES stable, well-compacted, non-compressible ground that will not settle or heave beneath the slab
- •A beam and block floor can be used wherever the perimeter walls provide a stable bearing — regardless of what the ground below does
**Situations in which beam and block is preferred for London residential extensions**:
*1. Made ground or fill within the extension footprint*: If the extension footprint contains made ground (backfilled soil; demolition rubble; organic material) that cannot be economically excavated and replaced with compacted hardcore, a ground-bearing slab on this unstable material will settle and crack. A beam and block floor spanning over the made ground (supported from the perimeter walls, which are founded below the made ground on solid bearing) avoids the settlement risk entirely.
*2. Building over existing drains (particularly where a Build Over Agreement is required)*: For extensions that span over a public sewer or private drain that cannot be moved, a beam and block floor can span the drain zone — the void beneath the floor is accessible (from outside the building via inspection chambers) and the drain is not affected by the floor above. A ground-bearing slab would create a permanent cover over the drain, preventing maintenance access.
*3. Tree root zones (London Clay shrinkage/heave risk)*: On London Clay sites near large trees, the soil below the extension floor level may be subject to shrinkage (when tree roots desiccate the clay in summer) and heave (when trees are removed and the clay rewets). A ground-bearing slab subject to heave can crack dramatically. A beam and block floor — supported from the external walls (which are founded deep enough to avoid the heave zone) — is immune to sub-floor heave because there is a clear void between the floor and the ground; the floor cannot be pushed up by the heaving clay.
*4. High groundwater table (low-lying areas near Thames tributaries)*: In parts of South, East, and West London near the Thames flood plain (Hammersmith, Wandsworth, Lambeth, Tower Hamlets), the groundwater table may be close to or above the standard slab formation level. A ground-bearing slab in these conditions requires extensive drainage works and waterproofing. A beam and block floor with a ventilated void (maintained at or above the groundwater level by the perimeter wall height) is a simpler structural solution in many such cases.
*5. Short-span floors for single-storey extensions at differing levels*: Where a single-storey extension requires a floor at a level different from the existing house floor (e.g., a lower-level garden room extension, or a kitchen extension at a level raised above external ground), a beam and block floor can create the correct finished floor level without significant excavation and filling.
**When a ground-bearing slab is preferred over beam and block in London extensions**:
- •Stable, firm London Clay ground without tree proximity, drainage conflicts, or made ground — a ground-bearing slab is simpler, faster, and less expensive on good ground
- •Short extension widths (under 3.0m) where the beam span is minimal — beam and block offers little advantage over a simple ground-bearing slab on narrow extensions
- •Fast programme required — a ground-bearing slab (one day to pour) is faster than a beam and block floor (beams delivery lead time; block laying; screed cure)
- •Budget-driven projects on stable ground — ground-bearing slab is typically £15–£30/m² cheaper than beam and block on stable ground
**Ventilation of the void below a beam and block floor**:
- Building Regulations Approved Document C requires adequate cross-ventilation of the void beneath a suspended timber or concrete floor to prevent moisture accumulation and subsequent decay or degradation. For beam and block floors:
- •Ventilation openings ('air bricks' or proprietary ventilation products) required in at least two opposing external walls
- •Total free ventilation area: minimum 1,500 mm² per metre run of external wall (the old deemed-to-satisfy standard) — or airflow calculations under CIBSE guidance
- •The void depth (from top of soil to underside of beam and block) must be at least 150mm to allow adequate air circulation
- •The ground within the void should be cleared of organic material and covered with a weed-suppression membrane to prevent plant growth in the void
Insulation, Part L compliance, and costs for beam and block floors in London extensions
**Insulation specification for beam and block floors under Building Regulations Part L**:
Part L requires that the ground floor of a new extension achieves a U-value of 0.25 W/m²K or better. For a beam and block floor, the thermal resistance must come from insulation laid on top of the beam and block — either under or within the screed — because the ventilated void below the floor means there is no insulation benefit from the ground (unlike a ground-bearing slab where the ground itself adds some thermal resistance at the perimeter).
*Insulation options for beam and block floors*:
- *Option 1 — Rigid insulation board above beam and block (below screed)*:
- This is the most common approach:
- •100mm PIR (polyisocyanurate) insulation board (e.g., Celotex GA4000; Kingspan Kooltherm K8): lambda ≈ 0.022 W/mK; thermal resistance ≈ 4.55 m²K/W; U-value achieved ≈ 0.18–0.20 W/m²K (well within Part L requirement of 0.25)
- •75mm PIR board: U-value ≈ 0.22–0.25 W/m²K (borderline — check thermal calculation)
- •150mm EPS (expanded polystyrene) board (e.g., Jablite EP70): lambda ≈ 0.036 W/mK; thermal resistance ≈ 4.17 m²K/W; U-value ≈ 0.20 W/m²K
- •100mm EPS (EPS70): U-value ≈ 0.28 W/m²K (marginal — may not achieve 0.25 W/m²K without perimeter edge insulation)
The insulation board is laid in two staggered layers (to eliminate thermal bridging at board joints), typically with a DPM on top to protect from liquid screed penetration.
*Option 2 — Insulated screed (liquid insulating screed)*: Specialist liquid screed systems incorporating insulation (e.g., Cemfloor Thermal) are available that combine the screed and insulation function — the screed itself has a higher thermal resistance than standard concrete. However, for most London residential extension budgets, the rigid board + conventional screed approach is more cost-effective.
*Perimeter (edge) insulation*: At the perimeter of the beam and block floor, where the beam bears onto the external wall, there is a thermal bridge — the concrete beam contacts the masonry wall which is outside the insulation zone. This 'cold bridge' at the floor perimeter must be addressed by continuous insulated block or perimeter insulation upstand. Failure to address the floor perimeter cold bridge results in condensation risk at the skirting level and reduces the effective thermal performance of the floor. Specification: 50mm EPS or PIR insulation strip at the perimeter, between the beam end and the external wall masonry.
**Beam and block floor costs for London extensions (2025, supply and install)**:
*Cost comparison: beam and block vs. ground-bearing slab (both including insulation and screed to Part L standard)*:
| Element | Ground-bearing slab | Beam and block | |---|---|---| | Excavation/preparation | £10–£20/m² | £5–£10/m² | | Hardcore fill (150mm compacted) | £8–£15/m² | Not required | | DPM | £3–£5/m² | £3–£5/m² | | Insulation (100mm PIR) | £18–£28/m² | £18–£28/m² | | Beams + blocks (supply + lay) | Not applicable | £35–£55/m² | | Concrete slab (150mm C25) | £20–£35/m² | Not applicable | | Structural screed topping (65mm) | Not required | £15–£25/m² | | **Total installed (typical range)** | **£55–£95/m²** | **£75–£115/m²** |
- For a 25m² extension floor area:
- •Ground-bearing slab: £1,375–£2,375
- •Beam and block: £1,875–£2,875
The premium for beam and block over a ground-bearing slab is typically £20–£35/m² (approximately £500–£875 for a 25m² extension) — reflecting the additional cost of beams, blocks, and structural screed over simple hardcore and slab.
**Delivery lead time for beam and block**:
- Precast concrete beams are manufactured to order by UK concrete product companies (Forterra, Litecast, Bison). Lead times:
- •Standard residential spans from stock: 5–10 working days
- •Long spans or non-standard widths: 2–4 weeks
As with structural steelwork, beam and block materials should be ordered as soon as the structural engineer confirms the specification — not at the time of installation. A delayed beam delivery holds up the entire floor construction sequence.
Frequently Asked Questions
Do I need a beam and block floor or a ground-bearing slab for my London extension?▼
How much insulation do I need under a beam and block floor to meet Building Regulations?▼
How long does a beam and block floor take to install in a London extension?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.