Contents
What Building Regulations cover and when they apply
**What the Building Regulations 2010 cover**:
The Building Regulations 2010 (as amended) set out the minimum standards that new buildings and alterations to existing buildings must meet. They are organised into 'Approved Documents' (Parts A through S), each covering a different aspect of building performance:
- •*Part A — Structure*: Structural stability and robustness; load-bearing capacity; resistance to wind and ground movement
- •*Part B — Fire safety*: Fire spread; means of escape; access for firefighting; structural fire resistance; cavity barriers
- •*Part C — Site preparation and resistance to moisture*: Subsoil drainage; ground moisture resistance; weather resistance of walls and roofs
- •*Part E — Resistance to sound*: Airborne and impact sound insulation between rooms and between dwellings
- •*Part F — Ventilation*: Minimum ventilation rates; extract fans in kitchens and bathrooms; whole-house ventilation
- •*Part L — Conservation of fuel and power*: Thermal insulation of new elements; U-value requirements for extensions and loft conversions; energy efficiency of new windows and doors; boiler efficiency standards
- •*Part M — Access to and use of buildings*: Accessibility requirements for new dwellings and significant extensions
- •*Part P — Electrical safety in dwellings*: Competent person self-certification for electrical installation work; notification to Building Control
- •*Part Q — Security*: Minimum security standards for doors and windows in new dwellings and extensions
**When Building Regulations apply**:
Most significant building works require Building Regulations approval. Key triggers for domestic projects:
☐ Any extension (regardless of size, if it adds floor area to the dwelling) ☐ Loft conversions creating habitable rooms ☐ Garage conversions to habitable use ☐ Structural alterations (removing or altering load-bearing walls, installing structural steels) ☐ Basement conversions ☐ Installing or replacing a boiler, heating system, or hot water cylinder (Part J and Part L) ☐ New electrical circuits or rewiring (Part P — self-certification by registered electrician, or third-party Building Control notification) ☐ Installing a new window or door (Part Q — self-certification by FENSA or CERTASS registered installer, or third-party Building Control notification) ☐ Cavity wall insulation, external wall insulation, or loft insulation above certain thresholds (Part L)
**When Building Regulations do NOT typically apply**:
- •Like-for-like repairs and maintenance (replacing tiles, painting, replacing plasterboard, repairing a roof with the same materials)
- •Small outbuildings (under 30m² floor area, used for non-habitable purposes, no sleeping accommodation, not within 1m of a boundary — see Part 1, Class E of the GPDO 2015 PD rights, but note these are two separate regimes)
- •Internal alterations that do not affect structure, fire safety, energy efficiency, or drainage (removing non-load-bearing partition walls — but check Part B implications for means of escape)
*When uncertain*: Contact the Building Control body (Local Authority BC or an Approved Inspector) for a pre-application discussion — most offer this free of charge.
The two main approval routes — Full Plans vs. Building Notice
**Route 1 — Full Plans Application**:
- Under the Full Plans route, you submit detailed drawings (typically prepared by an architect or technician) and supporting calculations (typically from a structural engineer where structural work is involved) to the Building Control body BEFORE work starts. The Building Control surveyor reviews the submission and either:
- •Approves the plans (issues a Full Plans Approval notice) — work can proceed
- •Issues a conditional approval with specific requirements (e.g., additional structural calculations required)
- •Rejects the plans with reasons — plans must be amended and resubmitted
- *Advantages of Full Plans*:
- •Design issues are identified and resolved before work starts — not mid-construction
- •Approved plans provide certainty for the contractor, avoiding on-site rework
- •Provides a clear technical specification for tendering purposes
- •If the approved plans change during construction, a 'Regularisation' or 'Amendment to Full Plans' can be submitted
- •Gives buyers' solicitors and mortgage lenders the clearest evidence of Building Regulations compliance
*Timescales*: Plan checking: 5 weeks (local authority BC) or typically 3–4 weeks (Approved Inspector). Work can start on site immediately after submitting a Full Plans application (before approval is given) at the applicant's own risk — most contractors prefer to wait for approval on structural matters.
*Fee*: Calculated by the Building Control body; typically £400–£1,500 for a domestic extension; includes all site inspections to practical completion and the issue of a completion certificate.
*Best for*: Extensions, loft conversions, structural alterations, basement conversions, garage conversions — any project where design is fixed before starting.
**Route 2 — Building Notice**:
Under the Building Notice route, you notify the Building Control body that you intend to start works (at least 2 days before starting), but no detailed plans are submitted for checking. Instead, the Building Control surveyor inspects the works at key stages as they progress and advises on compliance.
- *Advantages of Building Notice*:
- •No delay waiting for plan approval — work can start in 2 days
- •Simpler administration — no need to prepare full working drawings before starting
- *Disadvantages of Building Notice*:
- •No pre-construction design review — compliance issues are identified on site
- •If the BC surveyor requires changes on site (different structural solution, additional fire protection), rework costs fall on the contractor and ultimately the homeowner
- •No approved plans document — buyers' solicitors may request further evidence; some mortgage lenders prefer Full Plans approval
- •NOT suitable for work subject to Section 1 of the Regulatory Reform (Fire Safety) Order 2005, work in HMOs, or work to flats
*Fee*: Similar to Full Plans, but typically slightly lower.
*Best for*: Minor or straightforward works where a professional contractor is experienced in the Building Regulations requirements and the design is simple. NOT recommended for structural work, loft conversions, or HMO works.
**Approved Inspectors vs. Local Authority Building Control**:
- Building Control services can be provided by either:
- •*Local Authority Building Control (LABC)*: The Building Control team of the local council. Always available; fees are set by the local authority; well-known to local planning and structural engineers.
- •*Approved Inspectors (private sector)*: Independent Building Control bodies (e.g., NHBC Building Control, Bureau Veritas, Quadrant, etc.). Often faster plan review; competitive fees; same statutory powers as LABC. Must notify the LABC of their appointment (Initial Notice — the LABC has a right to reject the appointment in certain circumstances).
For most domestic projects, either route works well. Approved Inspectors can offer faster turnaround and sometimes more flexible scheduling of inspections.
Inspections, completion certificates, and what happens without them
**Key Building Control inspection stages**:
Regardless of the approval route, the Building Control surveyor must be notified to carry out inspections at key stages. Typical inspection stages for an extension or loft conversion:
1. *Commencement*: Notification that works have started (for Building Notice route, this is the initial 2-day notice; for Full Plans, a separate commencement notice) 2. *Excavation*: Before the concrete is poured — foundations must be inspected at this stage; if concrete is poured before inspection, the BC surveyor may require it to be broken out 3. *Concrete/oversite*: After the concrete foundation and oversite are laid; before the ground floor is constructed above 4. *DPC*: Damp-proof course inspection at the base of the external wall 5. *Frame*: Structural frame inspection (floor joists, roof structure, steel beam installation) before it is covered 6. *Insulation*: Confirmation that thermal insulation meets Part L requirements (U-values, continuity, no cold bridges) 7. *Drains*: Foul drain connections, fall, access provision, and test before backfilling 8. *Fire protection*: FD30S doors, protected staircase, fire-stopping to penetrations, intumescent seals — particularly critical for loft conversions 9. *Completion*: Final inspection of the completed works
Missed inspections are a serious problem — particularly the foundation inspection. If the BC surveyor cannot inspect a stage because it has been covered up, they have the right to require opening up (at the contractor's cost, ultimately at the homeowner's cost).
**The completion certificate**:
After the final inspection, the Building Control body issues a Completion Certificate confirming that the inspected works comply with the Building Regulations. This is one of the most important documents in a domestic project:
- •*Required on sale*: Buyers' solicitors routinely require a copy of the Building Regulations completion certificate (and for energy-related works, a copy of the Part L compliance calculation) for any significant works carried out since the property was built
- •*Required for mortgage applications*: Lenders may require a completion certificate as a condition of releasing funds on a purchase
- •*Required for HMO licensing*: Many councils require copies of Building Control completion certificates for notifiable works as part of the HMO licence application
- •*Evidence for insurance claims*: In the event of a fire, flood, or structural failure, compliance certificates demonstrate that the works met statutory standards at time of construction
**What happens if works are carried out without Building Control**:
Unauthorised works (works that required Building Control approval but did not have it) are a serious problem:
- •*Regularisation*: The homeowner can apply for retrospective approval — a 'Regularisation Certificate' — but the BC surveyor may require opening up of completed works to verify compliance. This can be costly and disruptive.
- •*Enforcement*: The local authority has 12 months from the date of infringement to issue an enforcement notice (for most Building Regulations contraventions). After 12 months, enforcement by the LA is time-barred, but the works remain without a certificate.
- •*Indemnity insurance*: For historic unauthorised works (typically more than 12 months old with no enforcement action), buyers' solicitors often accept an indemnity insurance policy in lieu of a completion certificate. However, this is not available where the works are recent or where there is an existing enforcement notice.
Frequently Asked Questions
Do I need Building Regulations approval for a small extension?▼
Can my contractor submit the Building Control application, or must I do it myself?▼
What is the difference between planning permission and Building Regulations approval?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.