Contents
Understanding the chimney structure and what happens when you remove part of it
A Victorian or Edwardian chimney is typically a continuous masonry stack that runs from the foundations through all floors of the house and exits through the roof. In a typical two-storey London terrace:
- •**Ground floor chimney breast**: the lowest visible section in the ground floor reception room, containing one or two fireplace openings
- •**First floor chimney breast**: the section directly above on the first floor, often in a bedroom
- •**Stack above roof level**: the section that exits through the roof and terminates in chimney pots
The critical structural point: if only the ground floor chimney breast is removed and the first floor breast and stack above remain, the weight of the first floor breast and stack must be transferred to a new support. The remaining breast above cannot just 'hang in the air' — it requires an RSJ (steel beam) inserted at first floor level to carry the load of the masonry above.
**Three common removal scenarios**:
- *Ground floor removal only*:
- •Most common scenario — removes the chimney breast from the ground floor room while retaining the first floor and above
- •Requires an RSJ installed at first floor level to carry the load of the first floor breast and stack
- •The RSJ sits in the party wall (or gable wall) at each end — requiring padstones and potentially party wall notice
- •The first floor floorboards and structure must be temporarily propped during steel installation
- *Ground floor and first floor removal*:
- •Both chimney breasts removed, leaving only the stack above the first floor ceiling
- •Requires an RSJ at second floor level (or at the base of the roof structure) to carry the stack above
- •More complex, more expensive, more intrusive — but frees maximum space on both floors
- *Full removal (including stack)*:
- •All chimney breast and stack removed from the property — including the section above roof level
- •The roof where the stack exits must be carefully made good — the stack exit is usually via a purpose-formed penetration in the roof, which must be properly flashed and waterproofed after removal
- •No structural steel required if no chimney breast remains (no weight to transfer), but the opening left in the roof requires specific attention
- •Most invasive and most expensive — typically only justified on major refurbishments
Structural requirements, Building Regulations, and the party wall
**Structural engineer requirement**: Chimney breast removal requires a structural engineer to design the new load path — specifically the RSJ required to carry the remaining structure above. Building Control will not approve the work without an engineer's design and calculation.
- The engineer will specify:
- •The RSJ section (depth, weight per metre) adequate for the load
- •Padstone size and specification at each end of the beam
- •Temporary propping arrangement during installation
- •Any implications for the party wall at the beam bearings
- **Building Regulations (Part A — Structure)**:
- Chimney breast removal is notifiable under Building Regulations — a structural alteration affecting a load-bearing element. Approval is required:
- •Either through Full Plans Approval (FPA) before work starts — which gives a formal approval notice from Building Control
- •Or through a Building Notice — which allows work to start sooner but requires regular on-site inspections by the Building Control officer
- Building Control inspections for chimney breast removal typically include:
- •Inspection before the propping is put in place (to confirm the temporary works arrangement)
- •Inspection before the RSJ is positioned and masonry made good (to confirm steel size and padstones match the specification)
- •Final inspection after making good
**Party Wall implications**: In a mid-terrace Victorian property, the chimney breast is typically on the party wall — shared with the adjacent property. The RSJ required to carry the remaining stack above will bear on the party wall at each end.
- This constitutes 'work on the party wall' under the Party Wall etc. Act 1996 — specifically Section 2 (works to a party wall). A Party Wall Notice must be served on the adjoining owner before the works start. The neighbour has 14 days to:
- •Consent in writing (the work can proceed)
- •Dissent (triggering the party wall award process — appointment of surveyors, production of a schedule of condition and award)
- •Not respond (deemed dissent after 14 days — surveyor appointment follows)
For chimney breast removal in mid-terrace properties, assume a Party Wall Notice will be required — budget for it (surveyor fees £1,000–£2,500 per surveyor) and allow the 14-day notice period in your programme.
Costs, programme, and value considerations
**Typical costs (London 2025)**:
- *Ground floor chimney breast removal only (RSJ at first floor level)*:
- •Structural engineer (calculation + specification): £500–£1,200
- •Building Control (Building Notice or Full Plans): £400–£800
- •Contractor works (demolition of breast, temporary propping, RSJ installation, padstones, making good): £2,500–£5,500
- •Party wall surveyors (if required): £1,000–£2,500
- •Decoration making good: £500–£1,500
- **Total: £5,000–£11,500 approximately (all in)**
- *Ground floor and first floor chimney breast removal*:
- •More extensive — typically £3,000–£7,000 for the contractor works element; total £7,000–£15,000 all-in
- *Full chimney breast and stack removal*:
- •Roof making good significant — typically £8,000–£20,000 all-in depending on property size and specification
- **Programme**:
- •A straightforward ground floor breast removal with an efficient contractor: 3–6 working days for the structural works, plus decoration making good
- •Allows for Party Wall Notice period (minimum 1 month before work starts after the notice is served and agreed) in the overall programme
**Does it add value?** In a typical London Victorian terrace, removing the chimney breast from the ground floor reception room creates a materially more spacious and usable open-plan living area. This generally adds value — a well-executed removal on a narrow-fronted Victorian terrace (14–16ft wide typical) can transform the feel of the ground floor and increase sale value.
- However:
- •Retain the fireplace opening if you can — original fireplaces with period surrounds are valued by buyers and can be retained even after chimney breast removal by creating a false breast or recessing behind the RSJ line
- •The quality of making good matters — a poorly patched ceiling or wall around the removed breast is an obvious tell and reduces the perceived quality
- •An unsupported stack (where a breast has been removed without proper RSJ support) is a serious defect that will be caught by a building survey and can prevent a mortgage and sale — always use a structural engineer
Frequently Asked Questions
Can I remove a chimney breast without Building Regulations approval?▼
My builder says he's done loads of chimney breast removals and doesn't need a structural engineer. Is this correct?▼
What happens to the chimney breast on the floor above if I only remove the ground floor one?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.