⭐ 9.96/10 Checkatrade · 114+ Reviews
📞 07359 872594
Services & Projects2 min read

Concrete Screed Floors for London Extensions and Renovations: Types, Costs, and What to Expect

A concrete screed floor is the standard finished substrate for the majority of London extension and ground-floor renovation projects — it provides the level, smooth surface over which tiles, engineered wood, LVT (luxury vinyl tile), or polished concrete are laid. Understanding the different types of screed, how they interact with underfloor heating, how long they take to dry and cure, and what they cost helps you plan a building project realistically and avoid the common delays that occur when screed is not specified and managed correctly.

Key Takeaways

  • Three main screed types for London extensions: (1) sand-cement screed 65–75mm: cheapest (£15–£25/m²), slowest to dry (1mm/day — 65mm takes ~65 days), suitable for all finishes; (2) anhydrite (liquid/calcium sulphate) screed 30–40mm over UFH: faster installation (pump-applied), thinner section, better UFH thermal contact, faster drying — preferred for UFH systems; 30–50% more expensive than sand-cement; not for wet rooms; must prime before cement adhesive; (3) self-levelling compound 10–20mm: for levelling existing slabs or spot correction, not a structural screed
  • UFH integration: wet UFH pipe (PE-X or MLCP, 16mm OD) installed in loops on insulation and clipped; pressure-tested at 6 bar before screed is poured (pipe stays at pressure during pour); anhydrite screed envelops pipe with no voids for best thermal contact; commissioning cycle required before floor finish: 28 days natural drying, then heat from 25°C rising to max flow temp (45–55°C) over 2–3 weeks, then moisture test to ≤75% RH (timber/LVT) or ≤80% RH (tile)
  • Drying times to floor finish: sand-cement with UFH: 50–65 days total; anhydrite with UFH: 35–50 days total; common mistakes causing delays: no pressure test before screed (damaged pipe found only after pour), excessive direct heat causing surface cracking, floor finish laid before moisture content reaches target (adhesive debonding, timber warping)
  • Screed costs for London (2025): sand-cement 65mm with UFH £18–£30/m²; anhydrite 35mm with UFH £22–£40/m²; UFH pipe and manifold additionally £18–£35/m² of heated floor area; insulation 75–100mm PIR additionally £8–£20/m²; laitance removal for anhydrite £5–£10/m²; full ground floor spec (insulation + DPM + UFH + anhydrite screed) typically £50–£90/m² all-in
  • Upper floor screed considerations: sand-cement at 65mm weighs ~115 kg/m² — original Victorian timber joists typically cannot carry this without structural upgrade; anhydrite at 30–35mm weighs ~60 kg/m² — may be within joist capacity after assessment by structural engineer; lightweight dry-screed systems (gypsum fibreboard over UFH plates, ~30 kg/m²) are the most practical UFH floor solution for upper floors in period properties without structural upgrade

Types of screed and which to use for different situations

**Sand-cement (traditional) screed**:

Sand-cement screed is the traditional screed — a 1:3 to 1:4.5 mix of cement and sharp sand, mixed on site with water. It is laid over a damp-proof membrane and insulation (for ground floor slabs) or directly onto the structural concrete (for upper floors).

*Typical thickness*: 65–75mm for an unbonded screed (laid over insulation without bonding to the structural slab); 40–50mm for a bonded screed (chemically bonded to the structural slab with SBR primer); 25–40mm for a float-and-set screed on the structural slab (without insulation — typically for upper floors).

*Drying and curing time*: Sand-cement screed dries at approximately 1mm per day in normal UK conditions (16–20°C, adequate ventilation). A 65mm sand-cement screed takes approximately 65 days to be 'move-in dry' (i.e., dry enough to lay the floor finish). For underfloor heating systems, the heating cycle must be run before the floor finish is laid (the heating cycle drives off remaining moisture — a process known as 'commissioning the screed') — this typically begins 28 days after laying and runs for approximately 7–14 days.

  • *When to use sand-cement screed*:
  • When the project budget is the primary driver (sand-cement is the cheapest type)
  • When standard floor finishes are specified (tile, LVT, engineered wood)
  • When the floor is not incorporating underfloor heating (the slower drying time of sand-cement is less problematic without UFH)
  • When the overall build programme has sufficient float to accommodate the drying time

**Anhydrite (calcium sulphate / gypsum) screed**:

Anhydrite screed (trade names: Gypsol, Primio, Isocrete K-Screed) is a liquid screed made from calcium sulphate, fine aggregate, and water, supplied as a ready-mixed liquid and pumped into the floor area. It flows into all corners and around UFH pipes without tamping, self-levels to a smooth surface, and can be laid at a minimum 30mm thickness over UFH pipes (compared with 65mm for sand-cement screed).

  • *Key advantages over sand-cement*:
  • *Faster installation*: A screed team can lay 1,000–2,000m² of anhydrite screed per day (vs. 100–150m² for sand-cement)
  • *Thinner section*: 30–40mm over UFH pipes vs. 65–75mm for sand-cement — important for floor-to-ceiling height in extensions
  • *Better thermal contact with UFH pipes*: The liquid screed envelops the pipes completely with no voids — better thermal conductivity to the floor surface
  • *Better surface flatness*: Anhydrite screed self-levels to a flatter surface than hand-trowelled sand-cement screed
  • *Faster drying*: Anhydrite screed dries faster than sand-cement in equivalent thicknesses — typically 1.5–2mm per day in good drying conditions
  • *Key considerations*:
  • *Cost*: Anhydrite screed is approximately 30–50% more expensive per m² than sand-cement screed (pump hire, faster setting, ready-mixed supply)
  • *Incompatibility with cement adhesives*: Anhydrite screed is calcium sulphate-based; contact with water-containing cement products can cause expansion — floor tiles must be laid with sulphate-resistant adhesives; the screed surface must be sealed with a diluted PVA primer before laying any cement-based adhesive
  • *Not suitable for wet rooms*: Anhydrite screed is not suitable for use in shower enclosures or wet rooms — the calcium sulphate dissolves on prolonged contact with water; a cement-based product should be used in these areas
  • *Surface skin*: Anhydrite screed forms a hard crystalline skin when dried; this skin must be sanded off with a floor sander before laying the floor finish (laitance removal)
  • *When to use anhydrite screed*:
  • When UFH is installed (anhydrite is the preferred screed type for UFH systems)
  • When programme is tight (faster installation and faster drying than sand-cement)
  • When the floor is large (over 50m²) — the speed advantage of pump-applied liquid screed becomes more significant
  • When flat floor tolerances are critical (for tile or polished concrete finishes with very low tolerance on flatness)

**Self-levelling compounds (self-levelling screed)**:

  • Self-levelling compounds (SLCs — brands: Ardex, Mapei, Laticrete) are cement-based or calcium-sulphate-based products mixed with water to a pourable consistency and used for:
  • Topping an existing concrete slab to correct level differences and surface irregularities (without laying a full screed)
  • Levelling over existing solid floors before laying floor finishes (e.g., levelling over a slightly uneven original Victorian concrete floor in a refurbishment)
  • Thin-section levelling over screeded areas that are not perfectly flat

*Typical use in London renovations*: In a full house refurbishment where the existing ground floor concrete slab is sound but uneven, a 10–20mm SLC topping can level the slab for the floor finish without laying a full screed — saving programme time and cost. Where an existing screed has localised low areas, SLC can be used to 'spot level' rather than laying a full replacement screed.

Underfloor heating integration and the commissioning process

**How wet UFH integrates with screed**:

Wet underfloor heating (water-filled pipe UFH) is the standard system for heated concrete screed floors in London extensions. The UFH pipe (typically Hep2O barrier pipe, MLCP composite pipe, or similar cross-linked polyethylene PE-X pipe, 16mm or 20mm OD) is installed in pre-designed loops on the insulation surface and clipped or stapled to hold the pipe in the correct position; then the screed is laid over the pipe.

  • *Design considerations*:
  • *Pipe spacing*: Standard room zones use 200mm pipe spacing; higher-output areas (poorly insulated walls or unusually cold rooms) use 150mm spacing; bathrooms with tiled floors use 150mm spacing for faster warm-up
  • *Maximum loop length*: Individual loops should not exceed approximately 100m for 16mm pipe or 120m for 20mm pipe (to maintain adequate flow velocity and pressure drop) — larger rooms require multiple loops each connected to the manifold
  • *Manifold location*: The UFH manifold (the flow-and-return header from which each zone is controlled) must be accessible and in a suitable location — typically a utility room or purpose-built UFH manifold cupboard; all pipes connect from the zones to the manifold
  • *Pressure testing before screed*: The UFH pipe must be pressure-tested at 6 bar or 1.5× the system working pressure before the screed is laid — with the pipe at pressure throughout the screed pour to prevent collapse; the test certificate is a required milestone before the screed contractor will proceed

**The screed commissioning process (for UFH screeds)**:

Before laying any floor finish over a UFH screed, the screed must be commissioned:

1. *Initial drying period*: After laying, the screed is left to dry naturally for a minimum of 28 days (sand-cement) or 14 days (anhydrite) — windows should be kept closed for the first 48 hours to prevent surface cracking from rapid drying, then ventilation provided 2. *Commissioning heating cycle*: The heating system is set to 25°C flow temperature for 3–5 days, then increased by 5°C per day up to the maximum design flow temperature (typically 45°C for ASHP or 55°C for gas boiler) and held for 4 days, then reduced back to ambient 3. *Moisture content test*: A calibrated hygrometer or CM (calcium carbide) moisture test is carried out to confirm the screed has reached an acceptable moisture content for the intended floor finish (typically ≤75% RH for timber or LVT finishes; tile on cement adhesive can typically be laid at ≤80% RH) 4. *Surface preparation for anhydrite*: The crystalline surface skin (laitance) is sanded off with a floor sander; any cracked or hollow areas are assessed and repaired; the surface is primed before laying the floor finish

**Common mistakes that cause programme delays**:

  • *Laying screed without pressure-testing the UFH pipe*: If the pipe is damaged during screed laying and the test was not done beforehand, the screed must be broken out and replaced
  • *Trying to accelerate drying with excessive direct heat*: Pointing propane heaters directly at fresh screed causes surface cracking; the correct method is gentle air circulation at a controlled temperature
  • *Not allowing the commissioning cycle before laying floor finishes*: Laying tiles or timber flooring on an incompletely dried screed causes debonding of adhesive and warping of timber — expensive remedial works
  • *Allowing foot traffic too soon*: Sand-cement screed is not structurally mature enough for heavy foot traffic for 7 days; workers walking on it before this causes surface damage that then requires grinding or topping

Costs, programme, and what to look for in a screed contractor

**Typical screed costs for London (2025)**:

| Screed type and situation | Typical cost per m² (supply and install, exc. insulation) | |---|---| | Sand-cement screed 65mm, no UFH | £15–£25/m² | | Sand-cement screed 65mm, over UFH pipe (pipe supplied by others) | £18–£30/m² | | Anhydrite (liquid) screed 35mm, over UFH pipe (pipe supplied by others) | £22–£40/m² | | Anhydrite (liquid) screed 35mm, no UFH | £18–£32/m² | | Self-levelling compound, 10mm topping | £12–£22/m² |

  • *Additional costs*:
  • UFH pipe and manifold supply: typically £18–£35/m² of heated floor area (supplied and installed by UFH subcontractor before the screed is laid)
  • Insulation below screed (typically 75–100mm PIR or 100mm EPS): £8–£20/m² (supply and install)
  • Damp-proof membrane: typically £2–£5/m²
  • Screed commissioning cycle (running heating system): no additional cost if the heating system is operational; contractor monitoring not usually charged separately
  • Laitance removal (anhydrite only): £5–£10/m²

**Programme: how long does screed take?**

For a 30m² extension (a typical kitchen-diner rear extension):

| Activity | Duration | |---|---| | Insulation and DPM preparation | 1 day | | UFH pipe installation | 1 day | | UFH pressure test | 1 day (test period) | | Sand-cement screed laying | 1 day | | Sand-cement drying to 75% RH | 55–70 days (depends on conditions) | | Sand-cement commissioning cycle | 14–21 days (typically overlapping last 2 weeks of drying) | | *Total to floor finish* | 65–80 days | | | | | Anhydrite screed laying | 0.5 day | | Anhydrite drying to 75% RH | 35–50 days (depends on conditions) | | Anhydrite commissioning cycle | 14–21 days | | Laitance removal | 1 day | | *Total to floor finish* | 45–60 days |

**What to look for in a screed contractor**:

  • *Experience with the specific screed type*: Anhydrite screed laying in particular requires specialist equipment (pump and hose) and experience with the material's specific characteristics (flow rate, self-levelling behaviour, drying requirements); not all screed contractors work with both types
  • *BS 8204 compliance*: The British Standard for screeds, bases, and in-situ floorings; a professional screed contractor should work to this standard and be able to demonstrate it
  • *Written mix specification*: For sand-cement screeds, the mix ratio, water/cement ratio, and additive specification should be documented; 'we've always done it this way' without a written specification is a warning sign
  • *Evidence of moisture testing*: A professional screed contractor or finishing contractor will carry out a calibrated moisture content test before releasing the floor for finish laying; if no moisture testing is proposed, push back and insist on it
  • *Suitable ambient conditions*: Screed should not be laid in temperatures below 5°C or above 30°C; in winter, the extension must be adequately enclosed and warmed before the screed is laid

Frequently Asked Questions

How long does it take before I can lay floor tiles on a screed?
For sand-cement screed without UFH: approximately 65 days (at 1mm per day in normal UK drying conditions, for a 65mm screed) before the moisture content is low enough to bond ceramic or porcelain tiles with a cement adhesive (target moisture content ≤80% RH). For sand-cement screed with UFH: a minimum of 28 days' natural drying, then the commissioning heating cycle (2–3 weeks), then moisture test — typically 50–65 days in total. For anhydrite screed with UFH: a minimum of 14 days' natural drying, then the commissioning cycle (2–3 weeks), then laitance removal and moisture test — typically 35–50 days in total. For timber or LVT finishes, which are more moisture-sensitive than tile, the target moisture content is lower (≤75% RH) and may require additional drying time or the use of a moisture-tolerant adhesive system.
Can I lay a screed floor on an upper floor of my house?
Yes — screed floors are commonly used on upper floors in London renovation projects, particularly where UFH is wanted throughout the house. The structural consideration is: screeds are heavy (sand-cement at 65mm weighs approximately 115 kg/m²; anhydrite at 35mm weighs approximately 60 kg/m²) and the existing floor structure must be designed to carry this load. In most Victorian terraced houses, the original timber floor joists were not designed for a concrete screed load. For a renovation project specifying UFH on upper floors: the structural engineer must calculate whether the existing joists are adequate (they often are not, especially for deeper sand-cement screeds); anhydrite screed at 30–35mm may be within the capacity of upgraded joists; alternatively, lightweight screed systems (such as dry-screed systems using gypsum fibreboard panels over UFH plates) can achieve similar thermal performance at a fraction of the weight (approximately 30 kg/m²).
What happens if cracks appear in my screed floor?
Some cracking in sand-cement screed is normal — particularly early plastic shrinkage cracks (which occur in the first 24–48 hours if the screed dries too quickly on the surface before it has sufficient strength), and later drying shrinkage cracks. Whether cracks are a problem depends on their nature: (a) hairline surface cracks (under 0.5mm width) typically do not affect the structural integrity or the floor finish adhesion if the screed is otherwise sound; they can be filled with compatible filler; (b) structural cracks (wider than 1mm, particularly cracks that go through the full depth and are accompanied by movement) indicate a problem with the mix, the drying conditions, or the subbase — these need investigation and possibly localised breaking out and replacement; (c) hollow areas (screed that sounds hollow when tapped with a steel rod) indicate debonding from the substrate — these areas have no structural integrity and must be broken out and relaid. Always investigate any cracking or hollow areas before laying the floor finish — it is far cheaper to address screed defects before tiling than after.

Important Note

This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.

Ready to Discuss Your Project?

Free site survey. No obligation. Covering all Greater London & M25.

📞 Call now💬 WhatsAppFree Quote