What does a full house refurbishment actually include?
A full house refurbishment — as opposed to a cosmetic refresh or a room-by-room renovation — means comprehensively upgrading the property from structure to finish. A genuine full refurb typically includes:
**Structural works**: Any load-bearing wall removals, steel beam installations, chimney breast removals, or structural repairs to floors, walls, or roof structure.
**Roof**: If not recently renewed, the roof should be addressed during a full refurbishment — new felt, battens, tiles or slates, ridge tiles, and guttering.
**Damp investigation and remediation**: Full investigation and treatment before any internal finishes are applied. This may include repointing, damp-proof courses, tanking, or external drainage improvements.
**Full electrical rewire**: New consumer unit, all circuits, sockets, switches, lighting points, and EV charger provision if required. Rewiring during a full refurb — when walls are open — is far cheaper than retrofitting later.
**Full plumbing replacement**: New boiler, new heating system (radiators or underfloor heating where floors are open), new hot and cold pipework, replacement of lead supply pipes.
**Insulation**: Loft insulation, cavity wall insulation where applicable, internal wall insulation to solid walls, floor insulation where floors are lifted.
**Windows and external doors**: Repair or replacement depending on condition.
**Full plaster**: Skim coat to all walls and ceilings after services are in (or repair and retention of original lime plaster where appropriate).
**Kitchen**: New kitchen unit installation (kitchen supplied separately or by contractor depending on specification).
**Bathrooms**: New bathroom suites, tiling, and plumbing.
**Joinery**: Internal doors, door frames, skirting, architraves, and any bespoke joinery.
**Flooring**: Throughout the property.
**Decoration**: Full paint or wallpaper throughout, including ceilings.
Not every refurb includes every item on this list — the scope depends on the property's condition and the owner's brief.
The right order of works — why sequence matters
The order in which work happens on a refurbishment is not optional. Getting the sequence wrong is the most common cause of rework, cost overruns, and disputes.
**The correct sequence:**
1. **Strip-out first**: Removal of all fixtures, fittings, non-structural partitions, floor coverings, ceilings, and old services. This exposes the structure and makes everything else easier.
2. **Structural works**: Any load-bearing wall removals, steel beams, or structural repairs happen on the exposed structure — before anything else is built.
3. **Roof and external envelope**: The building must be weathertight before internal finishes begin. Roof works, window replacements, and any external damp repairs are done early.
4. **Damp investigation and treatment**: After strip-out and structural works expose the walls, damp investigations are conducted and treatment applied. Plastering over unresolved damp will fail.
5. **First-fix electrical**: All conduit routes, back boxes, and wiring are run before walls are boarded. This includes all circuits, TV/data cables, and EV charger cables.
6. **First-fix plumbing**: All new pipework — hot and cold, heating, and drainage — is installed before walls are closed.
7. **Underfloor heating**: Where specified, pipes are laid before screed is poured (wet UFH) or boards are installed (electric UFH).
8. **Insulation and boarding**: Wall insulation, floor insulation, and plasterboarding.
9. **Plastering**: Skim coat to walls and ceilings once boarding is complete. There is typically a drying-out period of 2–3 weeks before decoration can begin.
10. **Second-fix electrical**: Sockets, switches, light fittings, consumer unit commissioning.
11. **Second-fix plumbing**: Radiators or UFH manifolds, bathroom suites, boiler commissioning.
12. **Kitchen and bathroom installation**: Kitchen units, worktops, tiling. Bathroom tiling, suite installation, shower enclosures.
13. **Joinery**: Internal doors, skirting, architraves, and any bespoke joinery.
14. **Flooring**: Engineered timber, LVT, tile, or carpet installed last (after all other trades).
15. **Decoration**: Final paint throughout. This is always last.
How much does a full house refurbishment cost in London?
Costs for a full house refurbishment in London (2025) depend heavily on the size of the property, its condition at the start, and the scope and specification:
- **1-bedroom flat (50–60m²)**
- •Standard specification: £25,000–£45,000
- •High specification: £45,000–£70,000
- **2-bedroom flat or small terraced house (70–90m²)**
- •Standard specification: £40,000–£75,000
- •High specification: £75,000–£110,000
- **3-bedroom Victorian terraced house (90–120m²)**
- •Standard specification: £70,000–£120,000
- •High specification: £120,000–£180,000
- **4+ bedroom house or large Victorian semi (120–180m²)**
- •Standard specification: £110,000–£180,000
- •High specification: £180,000–£280,000+
- **Structural works and extensions** add to these figures:
- •Each load-bearing wall removal + RSJ: £4,000–£8,000
- •Rear extension: £45,000–£90,000
- •Loft conversion: £35,000–£100,000
**What 'standard' vs 'high' specification means:** Standard: mid-market kitchen and bathrooms (£8,000–£15,000 kitchen, £6,000–£10,000 per bathroom), engineered oak or LVT flooring, new windows (UPVC or aluminium), full rewire and plumbing, fresh plaster and decoration throughout. High specification: bespoke or premium kitchen (£20,000+), premium bathrooms (£12,000–£20,000 each), solid hardwood or large-format porcelain flooring, bespoke joinery, underfloor heating throughout, smart home systems, external works.
How long does a full house refurbishment take?
A full house refurbishment of a London terraced house typically takes 12–20 weeks on site, depending on the scope.
**1-bedroom flat**: 6–10 weeks **2-bedroom flat**: 8–14 weeks **3-bedroom terraced house (no extension)**: 12–18 weeks **3-bedroom terraced house (with rear extension or loft)**: 18–26 weeks **4+ bedroom house or complex structural works**: 18–28 weeks
- The factors that extend the programme:
- •Structural works (each opening adds 1–2 weeks)
- •Extent of damp remediation required
- •Plaster drying time (2–3 weeks before decoration, cannot be compressed)
- •Kitchen and bathroom specification and lead times
- •Whether the property is occupied during the works
For occupied refurbishments (phased room by room while the client lives in the house), the programme is typically 30–50% longer. An empty property allows work to proceed across all rooms simultaneously.
The decisions that make or break a refurbishment
The quality of a full house refurbishment is determined less by the specification of finishes and more by decisions made in the first month. The following are the decisions that matter most:
**1. How comprehensive is the scope?** Many clients start with a cosmetic brief and discover mid-project that the rewire, damp, or structural issue cannot be avoided. Trying to do a partial refurbishment in an older property often costs more in the medium term than doing the full scope at the outset. Get a structural and damp investigation done before fixing the scope.
**2. Is the design resolved before work starts?** The most expensive changes on a refurbishment are changes made after work has started. Every structural opening, kitchen layout, bathroom position, and partition location should be decided before first-fix begins.
**3. Bathroom and kitchen supply — client-supplied or contractor-supplied?** RCB's standard position is that second-fix materials and kitchen/bathroom units are client-supplied. This allows clients to select their own specification. It also means the contractor's programme depends on client supply arriving on time.
**4. Who is coordinating the trades?** A full refurbishment involves 8–12 different trades operating in a specific sequence. Without a principal contractor coordinating the sequence, gaps, overlaps, and conflicts between trades are the most common cause of delays and disputes. This is one of the core reasons to use a principal contractor rather than managing individual trades directly.
Common mistakes in full house refurbishments
The following are the mistakes that most frequently cause refurbishment projects to go over budget, over programme, or under-deliver on quality:
**Starting before the design is resolved**: Structural changes and service routes must be fixed before first-fix. Making layout decisions after walls are plastered means opening walls again.
**Underestimating the scope upfront**: Older properties regularly reveal damp, structural issues, or substandard previous works once the strip-out happens. Build a contingency of 10–15% of the total project cost for unforeseen items.
**Not waterproofing before plastering**: The single most common cause of plastering failure. If there is any damp in the walls — rising damp, penetrating damp, or condensation — it must be fully investigated and treated before the final plaster coat.
**Selecting finishes too late**: Long-lead items — bespoke kitchen units, bathroom tiles from specific suppliers, specialist flooring — can take 6–14 weeks from order to delivery. If these are not ordered before first-fix starts, they can hold up the finish stages.
**Managing individual trades directly**: Coordinating 10+ trades, each with their own schedule, is a full-time job. Most homeowners who try this experience the same failure: the sequence falls apart, trades wait on each other, and the project stalls. Using a principal contractor with a programme removes this risk.
What RCB does differently on full refurbishments
RCB approaches full house refurbishments as a principal contractor — meaning one party takes accountability for the entire project from strip-out to sign-off.
**Pre-construction stage**: Before work starts, we review the design, agree the scope, produce a programme, identify long-lead items, and flag any structural or damp risks that need investigation.
**Coordination**: We manage all trades — structural, electrical, plumbing, plastering, carpentry, tiling, flooring, and decoration — to a single programme. The client has one point of contact.
**Documentation**: Every refurbishment begins with a written scope of works. Changes are documented and priced before they are instructed.
**Quality control**: We manage Building Control inspections for works that require sign-off — electrical, structural, drainage, and energy performance.
**Client communication**: We provide regular updates throughout the project. Clients know the programme, where the project stands against it, and when they need to make decisions.
The result is a refurbishment that runs to programme, to budget, and to the agreed scope — without the coordination overhead falling on the client.
Frequently Asked Questions
How much does a full house refurbishment cost in London?▼
What is the correct order of works in a house refurbishment?▼
How long does a full house refurbishment take?▼
Should I live in the house during a full refurbishment?▼