Contents
- 1. Stage 1: Decision to appoint and initial design (4-8 weeks)
- 2. Stage 2: Planning (2-14 weeks, depending on route)
- 3. Stage 3: Party wall and structural design (6-12 weeks)
- 4. Stage 4: Tender and contractor appointment (4-8 weeks)
- 5. Stage 5: Construction (12-24 weeks on site)
- 6. Frequently Asked Questions
Stage 1: Decision to appoint and initial design (4-8 weeks)
From the decision to proceed to receiving the initial design drawings from your architect or design-and-build contractor: Initial meeting and brief: 1-2 weeks from contact to first meeting. Scheme design (concept layout, initial elevations, outline specification): 2-4 weeks from initial meeting. Design review and client feedback: 1-2 weeks. Scheme design approval: total 4-8 weeks from first appointment to agreed scheme design. What affects this stage: the clarity of the brief — a clear, well-defined brief produces design proposals faster than a brief that evolves significantly through multiple rounds of revision. Time to review: if the homeowner is unavailable to review designs promptly, turnaround time extends. Complexity: a straightforward single-storey rear extension with no conservation area complications moves faster than a complex conservation area project where the design must carefully address heritage concerns.
Stage 2: Planning (2-14 weeks, depending on route)
From the agreed scheme design to planning decision or PD confirmation: Permitted development — no application required: if the extension is clearly within PD limits and no LDC is sought, no planning stage is needed — zero weeks. Lawful Development Certificate (LDC) application: 8-10 weeks for determination by the Local Planning Authority. Prior approval (Larger Home Extension scheme): 8-10 weeks from submission (42-day neighbour consultation period, then decision). Full planning permission application: 8-12 weeks statutory determination period (10-14 weeks in practice for most London Boroughs, due to workload). Conservation area full planning application: 10-16 weeks in practice — conservation officer consultations and the risk of committee referral add time. Planning refusal and appeal: 28-52 weeks from refusal to appeal decision — a major programme risk. What causes planning delays in London: incomplete application (missing plans, incorrect fee): the LPA will not validate an incomplete application — validation takes 1-2 weeks, and an incompletely submitted application restarts the clock. Committee referral: if the application is contentious (many objections, heritage significance), it may be referred to the planning committee rather than decided under delegated authority — adds 4-8 weeks. Officer caseload: some London Boroughs have significant planning officer caseloads — applications may not be allocated to an officer until 3-4 weeks after validation.
Stage 3: Party wall and structural design (6-12 weeks)
Running in parallel with planning (ideally): Party wall notice service: the notice can be served immediately the scheme design is agreed, without waiting for planning permission. 2-month notice period for most party wall matters (1 month for some). Party wall award: if the neighbour consents, no award is needed. If the neighbour does not respond or dissents: a party wall award takes 4-8 weeks to prepare and agree (if an agreed single surveyor) or 8-16 weeks (if each party appoints their own surveyor and an umpire is required). Structural engineer appointment and calculations: appointment: 1-2 weeks. Foundation design: 2-3 weeks from site investigation data. Steel beam design and calculations: 2-4 weeks. Building Regulations Full Plans application: submission and validation: 1 week. Assessment and approval (for a standard residential extension): 4-6 weeks. Note: if the Building Regulations application is submitted during the planning process (rather than after planning approval), the Building Regulations can be approved before planning — allowing construction to start sooner after planning approval. Running these parallel stages simultaneously saves 4-8 weeks on the overall programme.
Stage 4: Tender and contractor appointment (4-8 weeks)
From Building Regulations approval (or parallel with it) to contractor appointment: Tender document preparation (drawings, specification, schedule of works): 1-2 weeks. Tender invitation and tender period: 2-4 weeks for contractors to price the project. Tender return and analysis: 1-2 weeks. Contractor interviews and clarifications: 1-2 weeks. Contract negotiation and execution: 1-2 weeks. Total tender and appointment stage: 4-8 weeks. What affects this stage: number of tenderers — inviting 3 rather than 5 contractors simplifies the process; responding to tender queries promptly keeps the programme moving. Contractor availability — a quality contractor may have a 4-8 week lead time between appointment and start on site. Programme pressure — avoid setting an unrealistic start date that leads to appointing the wrong contractor; the tender process should identify the best contractor for the project, not merely the fastest to start.
Stage 5: Construction (12-24 weeks on site)
Construction duration for common London extension types: Single-storey rear extension (15-20m²): 10-14 weeks. Single-storey rear extension with full ground floor refurbishment: 14-22 weeks. Double-storey rear extension: 16-24 weeks. Loft conversion (rear dormer): 12-18 weeks. Hip-to-gable plus rear dormer loft: 14-20 weeks. What causes construction programme overruns in London: Late material deliveries: specialist items (bifold doors, rooflights, bespoke joinery) with long lead times that were not ordered early enough. This is the most common cause of London extension construction delays — order all specialist items at the start of the construction programme. Unforeseen conditions: unexpected ground conditions (buried structures, old drainage, difficult soil), unforeseen structural conditions (inadequate existing structure, asbestos discovery, unexpectedly shallow foundations). Weather: significant delays are uncommon in London for structural works (which can proceed in most weather), but extreme weather (prolonged frost, high winds during roof works) can cause delays. Subcontractor availability: if the main contractor is relying on specialist subcontractors (plumber, electrician, roofer) who are unavailable at the required time, the programme slips. Subcontractor management is a key principal contractor responsibility. Total programme summary (realistic): simple PD single-storey rear extension: 6-12 months from first appointment to practical completion. Conservation area single-storey rear extension (with planning application): 10-16 months. Double-storey extension with full planning permission: 14-22 months. Loft conversion: 8-14 months. Add 12-18 months for a planning appeal scenario.
Frequently Asked Questions
How long does a single-storey rear extension take in London from start to finish?▼
What causes the most delays in London extension projects?▼
Can I run planning and structural design in parallel for a London extension?▼
When should I order bifold or sliding doors for my London extension?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.