Pre-Construction Stages: Where Most of the Time Goes
The pre-construction phase — everything that happens before a builder sets foot on site — is the part of the project that homeowners most frequently underestimate.
Feasibility and brief (1–4 weeks): The first stage is establishing what you want to achieve, what the site constraints are, and what the project is likely to cost. This involves: initial discussions with an architect or design-and-build contractor; a site visit and initial feasibility assessment; a rough cost plan; and (for planning-sensitive projects) a preliminary discussion with the LPA's pre-application advice team.
Pre-application advice from the LPA (0–8 weeks): For projects where the planning outcome is uncertain (anything in a Conservation Area, anything involving a listed building, or any project that pushes at the limits of local policy), pre-application advice from the LPA's duty planner or pre-application service is strongly recommended. Some London boroughs provide pre-application advice within 2–4 weeks; others take 6–8 weeks. The cost is typically £150–£600 for a formal written response.
Design development (4–12 weeks): The architect or designer develops the concept into planning drawings — location and block plans, floor plans, elevations. This typically takes 4–8 weeks for a straightforward householder project; longer for more complex schemes or where significant client consultation and design iterations are required.
In parallel, the structural engineer provides initial structural input (the outline structural strategy — location of steel beams, foundation approach) so that the design can reflect the structure realistically.
Planning application (8–16+ weeks from submission): The planning application is submitted. The validation period takes 1–4 weeks (if the application is complete — see the planning application checklist). From validation, the statutory determination period is 8 weeks. However, in busy London boroughs, many applications take 10–14 weeks to be determined. Applications in Conservation Areas, requiring Ecology Reports, or generating significant neighbour representations may take 16+ weeks.
Total time from initial design brief to planning decision: typically 16–28 weeks for a project requiring planning permission. Some straightforward applications in pro-development boroughs can be determined in 12–16 weeks from brief to decision.
Projects that are permitted development (no planning permission required) — such as a loft conversion within permitted development size limits, or a rear extension within the permitted development parameters (single-storey, max 3m deep for a terrace, or using prior approval under the GPDO) — bypass the planning stage. However, they still require Building Regulations approval.
Building Regulations, Structural Engineer, and Party Wall Timeline
Building Regulations approval:
Building Regulations approval can be obtained via two routes: Local Authority Building Control (LABC) or an Approved Inspector (now renamed Registered Building Inspector from April 2024). Either route typically takes 4–8 weeks for full plans approval.
Many contractors and clients choose to submit for Building Regulations approval in parallel with the planning application — since the structural design can develop in parallel with the planning drawings. This saves significant time. Where the planning application is approved with conditions that affect the design, the Building Regulations drawings may need minor revisions.
Structural engineer timeline: Structural calculations and details for a typical rear extension or loft conversion take 3–6 weeks from the engineer's initial site visit to the issue of the completed calculation pack. Structural engineers in London are busy — book early. Structural engineering fees for a typical householder project: £800–£2,000 for a loft conversion; £1,200–£3,000 for a rear extension with RSJ openings; more for complex structural schemes.
Party wall timeline: The party wall process has statutory timetables that cannot be accelerated:
Serving notice: the party wall surveyor (or the building owner) serves the relevant notice on the adjoining owner. The type of notice and the notice period vary: Party Structure Notice (works directly on or to the party wall): the notice must be served at least 2 months before the start of the notifiable works. Three Metre / Six Metre Notice (excavations near party structures): the notice must be served at least 1 month before the works. Line of Junction Notice (new structures on the boundary): the notice must be served at least 1 month before the works.
Consent or dissent: the adjoining owner has 14 days to respond. If they consent in writing, no Award is needed. If they dissent (or fail to respond), the Award process begins.
Award process: typically 4–10 weeks from the appointment of surveyors to the issue of the Award (see the party wall award guide for details).
The party wall process should be started in parallel with the planning application and Building Regulations stages — not after planning permission is received. If the party wall process is started when the planning permission arrives, it adds 8–14 weeks to the pre-construction programme before site can start. Starting the party wall notices during the planning determination period ensures the Award is ready when permission is received.
Typical Construction Programme: Stage by Stage
Loft conversion (standard, within permitted development limits): Pre-construction: 3–8 months (no planning required, but allow time for Building Regulations, structural engineer, and party wall where applicable). On site: 10–14 weeks. Key stages: scaffold erection (week 1); structural alterations to ceiling joists and ridge beam (weeks 1–2); dormer construction if applicable (weeks 2–4); roofing and weathertightness (weeks 3–5); staircase installation (weeks 5–6); first fix electrics and plumbing (week 6); insulation and plasterboard (weeks 7–9); second fix and joinery (weeks 10–11); bathroom fit-out (weeks 11–12); decoration and snagging (weeks 13–14); scaffold strike.
Single-storey rear extension: Pre-construction: 4–12 months (planning permission usually required for extensions beyond permitted development size). On site: 12–18 weeks. Key stages: groundworks and foundations (weeks 1–3); drainage diversion if required (weeks 1–2); structural frame and steelwork (weeks 3–5); roof structure and waterproofing (weeks 5–7); external glazing installation (weeks 7–8); first fix M&E (weeks 8–9); insulation and boarding (weeks 9–10); plastering and drying (weeks 10–12, allowing for drying time); second fix M&E (weeks 12–13); flooring and tiling (weeks 13–15); kitchen fit-out (weeks 15–16); decoration and snagging (weeks 16–18).
Double-storey extension: Pre-construction: 5–14 months. On site: 16–24 weeks. Additional complexity vs single-storey: structural connections at first floor level; bathroom or en-suite fit-out on new first floor; scaffolding required at second floor height; more complex party wall implications.
Full house refurbishment (occupied Victorian terrace, all rooms): Pre-construction: 4–8 months (typically permitted development or prior approval, but may require planning for some elements). On site: 20–36 weeks. Best approach is a staged programme: strip out and structural works (all floors) → first fix M&E (all floors) → insulation and boarding → plastering → kitchens and bathrooms → flooring → joinery → decoration → snagging.
Kitchen renovation only (existing kitchen space, no structural alteration): Pre-construction: 2–4 weeks (no planning or Building Regulations beyond Part P electrical notification). On site: 4–6 weeks.
Procurement Lead Times That Affect the Programme
One of the most common causes of construction programme delays is the late ordering of long-lead items — components whose manufacture, delivery, or fabrication takes more time than the construction programme allows.
Key long-lead items for London home projects:
Structural steel: standard rolled steel sections (RSJs, UBs) are typically available ex-stock from steel stockholders in 5–10 working days. However, if the sections need to be fabricated (welded, drilled, primed, painted, cut to length with bespoke connections), fabrication typically takes 3–6 weeks from the structural engineer's completed drawing issue.
Bifold and sliding doors: aluminium bifold or sliding door systems with standard specifications (powder-coated, double-glazed) typically have a lead time of 6–10 weeks from order confirmation to delivery. Bespoke specifications (non-standard RAL colours, triple glazing, integrated blinds, unusual dimensions) can take 12–16 weeks. Order before the structural frame is complete.
Roof lanterns: aluminium or steel roof lanterns have similar lead times to bifold doors — 6–10 weeks for standard, 12–16 weeks for bespoke.
Bespoke kitchens: standard flat-pack kitchens (IKEA, B&Q) are available with 2–4 weeks' lead time. Mid-range Shaker-style or handleless kitchens from retailers (Howdens, Wren) are typically 3–6 weeks from order to delivery. Bespoke hand-painted or in-frame kitchens from specialist makers: 8–16 weeks from final order.
Custom joinery: bespoke staircases, fitted wardrobes, joinery for alcoves, and similar items are typically manufactured to order in 4–8 weeks.
Sanitary ware: standard sanitary ware (basin, bath, WC, shower tray) from high-street retailers is typically available within 1–2 weeks. Premium or continental brands (Duravit, Villeroy & Boch, Bette, Laufen) may require 3–8 weeks.
Procurement rule: order all long-lead items immediately after the structural engineer's calculations are confirmed and the layout is frozen. Do not wait until the shell is complete — by then, the structural steel should already be on site and the glazing should be two weeks from delivery.
Managing Delays and Keeping the Programme on Track
Even with excellent pre-construction planning, construction projects in London frequently encounter delays. Understanding the most common causes allows homeowners and contractors to mitigate them:
1. Unforeseen groundwork issues: Encountering an uncharted drainage run, an old cesspit, a buried structure, or deeper-than-expected building over the neighbouring foundation can stop groundworks for 1–3 weeks while the issue is investigated and resolved. Mitigation: commission a CCTV drainage survey before construction starts (£300–£600) to locate all drains within the footprint; request the GPR (ground penetrating radar) scan of the foundation area if the structural engineer recommends it.
2. Structural surprises: Opening up the existing structure (cutting out for RSJs, removing floors to expose joists) can reveal unexpected conditions — undersized existing lintels, cracked joists, rot in the existing structure, or a party wall in worse condition than expected. Mitigation: ensure the contractor allows adequate investigation time before works begin, and ensure the contingency sum in the budget is adequate (10–15% of construction cost for older properties).
3. Wet weather: Groundworks, brickwork, external rendering, roofing, and external joinery installation are all weather-dependent. A wet summer adds days to the external programme. Mitigation: plan the programme so that the most weather-sensitive stages (groundworks, brickwork) are completed before the British winter.
4. Material supply delays: Supply chain disruptions (as experienced in 2021–2022) can affect the availability of structural timber, insulation, engineered wood products, and specialist fixtures. Mitigation: order critical items early; agree a material procurement schedule with the contractor before works begin.
5. Decision delays from the client: Many construction programme delays in residential projects arise because the client does not make decisions (tile selection, paint colours, tap specification, worktop material) in time for the contractor to proceed. Mitigation: agree a decision schedule with the contractor and architect at the start of the project; make all specification decisions before the construction programme reaches the stage where they are needed.
Communication principle: a good principal contractor runs a weekly programme review with the client and updates the programme weekly. If a delay occurs, both parties understand the cause and the recovery plan immediately — not weeks after the original completion date has passed.
Frequently Asked Questions
How long does a loft conversion take from start to finish?▼
Can I live in the house during a rear extension?▼
Why is my contractor quoting a shorter programme than your typical timescales?▼
Should I wait until planning permission is received before looking for a contractor?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. rcbGroup offers free initial consultations — book your free survey.