Full refurbishment sequence stages 1-5: demolition and strip-out, structural works, drainage and groundworks, M&E first fix, and boarding for London homes in 2025
The full refurbishment trade sequence for a London home refurbishment — Stages 1 to 5: demolition and strip-out, structural works, drainage and groundworks, M&E first fix (mechanical and electrical services first fix), and boarding — in detail for 2025: STAGE 1 — SITE SET-UP AND DEMOLITION / STRIP-OUT: SITE SET-UP: before any trades start, the site must be set up correctly: PROTECTION OF RETAINED SURFACES AND FINISHES (hardboard or correx protection to stairs, floors, and any retained fixtures); DUST PROTECTION (polythene screens, hoarding, dust extraction at sanding and cutting operations); WELFARE (toilet, wash basin, storage, first aid — CDM 2015 requirements for any site with more than one trade working simultaneously or for more than 30 working days); ASBESTOS: if the property is pre-2000, an ASBESTOS REFURBISHMENT AND DEMOLITION (R&D) SURVEY must be commissioned from an accredited analyst (UKAS-accredited) BEFORE strip-out begins; the R&D survey identifies asbestos containing materials (ACMs) in the areas to be disturbed — ceiling tiles (Artex), floor tiles and adhesive, pipe lagging, boiler cement, window putty, partition walls, roof tiles; if ACMs are found: a LICENSED CONTRACTOR (if notifiable asbestos — typically friable or sprayed materials) or NON-LICENSED LICENSED REMOVAL (for non-friable ACMs like floor tiles or textured coatings) must remove the ACMs before general strip-out proceeds; STRIP-OUT SEQUENCE: internal: remove all fixtures, sanitaryware, kitchen units, ceiling tiles, carpets, floor coverings; remove non-structural stud partitions and door linings in the areas to be reconfigured; remove existing M&E where appropriate (existing boiler, radiators, hot water cylinder, wiring to areas being rewired, existing plumbing in areas being replumbed); external: any external works (scaffolding for roof or chimney, demolition of an existing outbuilding or old extension to be replaced) are also done at this stage; REASON FOR FIRST: strip-out must be complete before structural works begin — the structural engineer's calculations and drawings assumed the as-built condition; if unexpected elements are found during strip-out (e.g., an undisclosed chimney breast that the drawings showed as removed, or a different floor construction than expected), the engineer should be notified before proceeding; STAGE 2 — STRUCTURAL WORKS: SEQUENCE: structural works follow strip-out; WHAT STRUCTURAL WORKS INCLUDE: wall removals (with temporary propping and steel beam installation — see the structural alterations guide); chimney breast removal or retention work; new openings in external walls (for extension openings, new doors or windows); underpinning if required; new pad foundations or strip footings for columns or extensions; BUILDING CONTROL INVOLVEMENT: the structural engineer's drawings are submitted and approved (Full Plans application recommended); Building Control inspector attends to check the temporary propping, the steel beam installation, and the padstone details before any making-good takes place; WHY BEFORE M&E: structural works must be complete before M&E first fix because: the M&E first fix routes (pipe runs, cable routes) must be designed around the final structural configuration; new structural openings may affect where M&E services can and cannot go; STAGE 3 — DRAINAGE AND GROUNDWORKS: SEQUENCE: drainage and groundworks at ground floor level (including any basement waterproofing, drainage runs in the floor slab, and any required UFC — underfloor slab-level works) follow structural works; WHAT IS INCLUDED: breaking out the existing concrete ground floor slab (if being replaced or if new drainage is being installed below it); new underground drainage runs from the extension back to the existing manhole or public sewer connection; new slab pour (concrete slab — typically 100-150mm C25 concrete on 300mm well-compacted hardcore, with 100mm PIR insulation below the slab for a ground floor Part L-compliant floor, and DPM polyethylene sheet above the insulation); wet UFH pipework installation in the new slab at this stage (if ground floor UFH is specified); BUILDING CONTROL: new concrete slab poured only after Building Control inspector has approved the formation level, hardcore compaction, and DPM/insulation details; STAGE 4 — M&E FIRST FIX (THE MOST COMPLEX STAGE IN A REFURBISHMENT): the M&E FIRST FIX is the installation of all MECHANICAL (heating and plumbing) and ELECTRICAL (wiring and conduit) services within the floor, wall, and ceiling structure BEFORE the surfaces are boarded or plastered; WHY FIRST FIX IS CRITICAL: after boarding and plastering, access to the structure is lost; any M&E first fix that is missed, incorrectly positioned, or incorrectly specified must be CHASED (cut) into finished plaster — a disruptive and costly operation; ELECTRICAL FIRST FIX: installation of ALL new wiring within the STRUCTURAL FABRIC before boarding; WHAT IS COVERED: consumer unit position (new consumer unit location confirmed with the homeowner before wiring starts — the cable runs and circuit arrangement radiate from the consumer unit position); all lighting circuits (3-core cable from each light switch and light fitting position to the junction box location in the ceiling void; in a full rewire, this means a cable at every switch position, every ceiling rose position, every downlight position, and every pendant position on the drawing); all power ring circuits (13A ring mains — typically a ring per floor or per zone); dedicated circuits: electric oven and hob (radial circuit, 6mm2 cable); electric shower (10mm2); EV charger conduit (20-25mm conduit run + 6mm2 cable); UFH thermostat cables; bathroom extract fan circuit (fused spur at 5A, with overrun timer built in at the fan); IMPORTANT COORDINATION WITH BATHROOMS: the bathroom extract fan cable, the electric UFH thermostat cable, and the shower circuit must all be installed during electrical first fix — these are all Part P notifiable and need to be inspected before boarding; PLUMBING FIRST FIX: installation of ALL new pipework within the structural fabric before boarding; WHAT IS COVERED: new main cold water supply from the stopcock to the new cylinder or combi boiler position; new central heating pipework (flow and return) from the boiler or heat pump to all radiator positions and to the UFH manifold; RADIATOR CONNECTIONS: stub pipes project from the floor or wall at each radiator position (these must be at the correct position for the specified radiator — confirm radiator sizes and positions with the client and architect before plumbing first fix); BATHROOM PLUMBING: all hot and cold water supply pipes to each bathroom fitting (WC, bath, shower, basin) are run in first fix (concealed within the floor and wall structure); the bath/shower waste pipe and soil vent connection are also done at first fix; kitchen plumbing first fix: supply pipes and drain positions for the kitchen sink, dishwasher, washing machine, and boiling water tap (if included) are installed; COORDINATION BETWEEN ELECTRICIAN AND PLUMBER: first fix is a joint operation — the electrician and plumber must work in the same zones simultaneously or in close sequence; a common problem is ONE TRADE BOARDING (boxing) OVER ACCESS FOR THE OTHER TRADE'S WORK; the principal contractor must manage this so that no area is boarded until BOTH electrician and plumber have signed off their first fix in that zone; HEATING ENGINEER FIRST FIX: new boiler/heat pump position; radiator pipe stubs (flow and return); primary circuit to hot water cylinder if system boiler; STAGE 5 — BOARDING: SEQUENCE: boarding follows the completion of M&E first fix in each zone; WHAT IS INCLUDED: installing METAL STUD PARTITIONS or TIMBER STUD PARTITIONS to create new room layouts (new partition walls in the area of the refurbishment — e.g., new bathroom partition, new en suite partition, new bedroom partition); lining the underside of the roof structure (in a loft conversion — installing the insulation and lining to the rafters); PLASTERBOARD: 12.5mm standard for walls and ceilings (square edge for skim, tapered edge for jointing compound only — not typically used in UK domestic); 15mm for areas requiring better impact resistance; MOISTURE-RESISTANT PLASTERBOARD (MR, coloured blue — e.g., LAFARGE AQUABOARD, BRITISH GYPSUM MOISTURE BOARD): used in bathrooms, kitchens, and any areas subject to intermittent moisture; TIP: MOISTURE RESISTANT PLASTERBOARD IS NOT THE SAME AS WATERPROOF — see the bathroom guide for correct tanking and waterproofing specification; FIRE RATED BOARD: 12.5mm BRITISH GYPSUM FIRELINE in areas requiring fire resistance (party wall junctions, below stairs, garage walls) — typically specified by the structural engineer or Building Control; TAPE AND JOINT: taped over all plasterboard joints and screw positions with PINK GRIP TAPE and joint compound before skimming.
Stages 6-10: plastering, second fix M&E, decorating and floor finishes, snagging, and principal contractor programme management for London home refurbishments in 2025
Refurbishment trade sequence stages 6 to 10 — plastering, M&E second fix, decorating and floor finishes, snagging and handover, and the principal contractor's programme management role — for London home refurbishments in 2025: STAGE 6 — PLASTERING (A CRITICAL-PATH ACTIVITY): PLASTERING CANNOT START until: M&E first fix is complete (signed off by electrician and plumber); boarding is complete; structural works have been approved by Building Control; any required tanking (in bathrooms) has been applied and cured; WHY PLASTERING IS CRITICAL PATH: plastering introduces a large quantity of water into the building (bonding plaster and finishing plaster contain water, and the newly plastered surface takes 3-7 days per room to dry sufficiently before painting and second fix begin); the drying time is WEATHER AND TEMPERATURE DEPENDENT: in winter in London (unheated building, low external temperatures), plastering dries slowly; drying can be accelerated by TEMPORARY DEHUMIDIFIERS and HEATERS (temporary electric or gas heaters — ensure CO monitoring and ventilation); but the fundamental drying requirement cannot be rushed without risk of paint bubbling, blow-off, and adhesion failure later; PLASTER TYPES USED IN LONDON RESIDENTIAL REFURBISHMENTS: BONDING COAT (browning plaster — British Gypsum Thistle Bonding): applied to brick, blockwork, and heavyweight substrates requiring build-up; typically 8-10mm single coat; MULTIFINISH (British Gypsum Thistle Multifinish): skim coat applied over plasterboard or bonding coat; 2mm finish coat, trowelled to a smooth flat finish; HARDWALL: a stronger undercoat for areas subject to impact or in unheated buildings (garages, utility rooms); DRY LINING (PLASTERBOARD DIRECT OVER METAL STUD, JOINTS TAPED AND TOP-COATED): increasingly common in London refurbishments as it is faster than traditional plastering — but it requires correct boarding and jointing skills to achieve a smooth finish; a poorly boarded and taped surface shows joint lines and fastener shadows after painting (especially in raking light); some clients and contractors prefer traditional skim-over-board for better finish; EXTERNAL RENDER (IF APPLICABLE): for extensions with blockwork or brick needing a rendered finish: two-coat sand:cement or one-coat monocouche render is applied after structural works and before painting; STAGE 7 — M&E SECOND FIX: SEQUENCE: M&E second fix begins once the plaster has dried sufficiently (typically 5-7 days after finishing plaster on wall areas; may be longer for bathrooms where tanking cure time adds to the wait); ELECTRICAL SECOND FIX: installation of all the visible electrical components: sockets (faceplates and socket connections at all first-fix wiring positions); switches (1G, 2G, or 3G plates at all switch positions — confirm switch plate style with client before second fix: brushed brass/chrome/white plastic/matt black — the client may have a strong preference); ceiling roses and pendants; downlight fittings in the ceiling (recessed LED downlights — confirm insulation fire-rated (IC-F rated) where the downlight is in a ceiling beneath a loft or roof void — standard downlights in a ceiling below an insulated loft lose significant heat, and are a fire risk if covered by insulation — always use IC-F rated downlights in these positions); consumer unit final connections and labelling; TESTING AND CERTIFICATION: the electrician tests the complete installation (insulation resistance, earth loop impedance, RCD function tests) and issues an ELECTRICAL INSTALLATION CERTIFICATE (EIC — NICEIC or NAPIT registered electrician) and Part P Building Control compliance certification; PLUMBING SECOND FIX: connection of all plumbing appliances to the first-fix pipework: radiators (connecting the radiator tails to the flow and return stubs; fitting the TRV valve and lockshield valve); hot water cylinder (final connection if a system boiler); bathroom sanitaryware (WC cistern and pan connection; bath waste and overflow; basin waste; shower tray or wet room drain); kitchen sink; dishwasher and washing machine supply and waste connections; TESTING: pressure test of the central heating system (typically at 6 bar for 30 minutes before filling); fill and vent the system; dose with inhibitor (Fernox F1 or Sentinel X100); commission the boiler or heat pump (gas-safe registered engineer for gas; MCS certified for heat pump); boiler commissioning certificate issued; GAS SAFE CERTIFICATE for gas boiler installation (required by law); STAGE 8 — DECORATING: SEQUENCE: decorating begins after plaster is fully dry and M&E second fix is complete; WHY AFTER SECOND FIX: all socket boxes, ceiling roses, and switch plates need to be installed before painting so that their revealing edges are painted (if painting is done first, second-fix components fitted over unpainted recesses leave visible unpainted margins); minor making-good of any chased or patched areas is done at the start of decorating (filler, sand, prime before painting); DECORATING SEQUENCE: PRIME COAT: over all new plaster (a mist coat of diluted emulsion or a proprietary sealer/primer — necessary because new plaster is very absorbent; a primer prevents the top coat from being absorbed unevenly); CAULKING: fill all gaps between painted surfaces (skirting to wall, architrave to wall, coving to wall) with flexible decorator's caulk (not filler — caulk accommodates movement without cracking); TOP COATS: typically 2 coats of emulsion (walls and ceilings); WOODWORK PAINTING: gloss or eggshell on doors, door frames, skirting boards, architraves, window boards (either oil-based alkyd — the traditional London decorator's preference for a hard durable finish — or water-based acrylic gloss — faster drying, lower odour); STAGE 9 — FLOOR FINISHES: SEQUENCE: floor finishes are installed AFTER decoration (to avoid paint splashing on finished floors) and AFTER M&E second fix is complete (to avoid damaging floor finishes by subsequent trades); FLOOR FINISH INSTALLATION SEQUENCE: ENGINEERED TIMBER (floating): laying boards and fitting skirting boards over the floor; PORCELAIN OR NATURAL STONE TILES (glued): tile adhesive and grout; skirting fitted after tiling; CARPET: carpet fitter last (after all other trades have finished — carpet is the most vulnerable to damage); SKIRTING: in most London refurbishments, SKIRTING BOARDS ARE FITTED AFTER FLOOR FINISHES (the skirting drops to just above the floor level — if skirting is fitted before tiling, the tiler must cut around the skirting which is far harder; if skirting is fitted before carpet, the carpet is laid to the skirting face — either approach can work but must be consistent and agreed in advance); STAGE 10 — SNAGGING AND HANDOVER: SNAGGING: the final stage of the refurbishment programme before handover to the client is a COMPREHENSIVE SNAGGING INSPECTION — a systematic review of every room and every element of the works to identify items that are incomplete, defective, or not in accordance with the specification; WHO DOES THE SNAGGING: the PRINCIPAL CONTRACTOR (PC) conducts their own internal snagging and rectification BEFORE the client's snagging; then the CLIENT (or a professional SNAGGING INSPECTOR) conducts a joint snagging inspection with the PC; common snagging items in a London house refurbishment: PAINTING (missed areas, runs, thin coverage, unfilled nail holes in skirting, unsanded plaster repairs visible as shadows); JOINERY (doors not hanging level, locks stiff, gaps between architrave and door lining, unfinished caulking); TILING (grout not pointed out to edges, lippage between tiles, grouting lines not consistent, unsealed natural stone edges); PLUMBING (leaking radiator valve, dripping tap, running cistern not adjusted); ELECTRICAL (switch plate not level, socket face not flush, downlights not centred in ceiling tiles); BUILDING CONTROL COMPLETION CERTIFICATE: once snagging is complete and all required inspections have been passed, the Building Control completion certificate is issued; this is a CRITICAL document — keep it with the property deeds for the future sale; PROGRAMME MANAGEMENT — THE PRINCIPAL CONTRACTOR ROLE: the PC is responsible for: preparing and maintaining the CONSTRUCTION PROGRAMME (a Gantt chart or equivalent showing all trades, their durations, dependencies, and start/finish dates); MANAGING TRADE INTERFACES (ensuring the plumber leaves the correct stub-out positions for the kitchen before the kitchen fitter arrives; ensuring the tiler has the correct drain position from the plumber before tiling the wet room floor); MANAGING SUPPLY CHAIN (sanitaryware, kitchen, tiles, flooring, windows, and other long-lead-time items must be ordered BEFORE CONSTRUCTION STARTS to ensure they are available when their installation stage arrives — a common cause of delay in London refurbishments is long-lead-time kitchen delivery or window delivery when the structure is ready but the item has not yet arrived); CLIENT COMMUNICATION: weekly progress updates; early flagging of issues that may affect programme or budget.
Frequently Asked Questions
How long does a full house refurbishment take in London in 2025?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.