Sewer Build-Over Agreements in London: What They Are, When You Need One, and How to Get Approved

One of the most frequently overlooked constraints affecting rear extension and basement projects in London is the presence of public sewers running beneath or close to domestic gardens. In London, the responsibility for public sewers rests with Thames Water — and before any building works can begin within a specified exclusion zone of a public sewer, homeowners must obtain a Build Over Agreement from Thames Water. Failing to obtain a Build Over Agreement when required can result in enforcement action by Thames Water, the requirement to demolish or modify the completed structure, significant delays to a building project, and complications when selling the property. This guide explains what public sewers are in the context of London residential properties, how to identify whether a sewer runs through or near your garden, what a Build Over Agreement involves, and what the practical design and cost implications are for a London extension or basement project.

Key Takeaways

  • Public sewers and lateral drains: the Water Industry Act 1991 and the Water Industry (Schemes for Adoption of Private Sewers) Regulations 2011 (the "October 2011 transfer") define public sewers as those adopted and maintained by the sewerage undertaker (Thames Water in London). Before October 2011, only sewers serving more than one property were adopted — private drains serving a single property (connecting the property's internal drainage to the public sewer in the street) were the owner's responsibility. After October 2011, the private sewers and lateral drains between a property boundary and the public sewer main were transferred to Thames Water (the sewerage undertaker) and are now public sewers, maintained by Thames Water. The practical consequence is that the network of public sewers in London is now much larger than it was before 2011 — many pipes running through domestic gardens that were previously private drains are now classified as public sewers and are subject to Build Over Agreement requirements. An important implication for rear extension projects: the lateral drain running from the house's internal drainage system to the public sewer in the street typically runs through the rear garden (or under the house) — and this lateral drain is now a public sewer. If the proposed extension is to be built over or within the exclusion zone of this lateral drain, a Build Over Agreement is required from Thames Water. The distinction between a "drain" (serving a single property, privately owned) and a "sewer" (serving more than one property, adopted by Thames Water) remains relevant for drainage that has not been transferred — for example, the underground drainage serving a single property entirely within that property's boundaries, running from the soil stack to the boundary, may still be privately owned and therefore not subject to a Build Over Agreement — but the determination of adoption status must be confirmed by a Thames Water records search before this assumption is relied upon
  • Thames Water's Build Over Agreement requirements: Thames Water's Build Over Policy (published on their website and updated periodically) sets out the conditions under which they will permit construction over or near public sewers. The key requirements as of 2025 are: a pre-application CCTV survey of the public sewer must be carried out by a contractor accredited by the Water Research Centre (WRcN) or similar accredited body, to establish the existing condition of the sewer before construction begins. Thames Water requires the CCTV survey results to confirm that the sewer is in a reasonable state of repair before the build-over agreement is granted — if the sewer is in poor condition, Thames Water may require the sewer to be repaired before construction proceeds; the new structure must not: be within 1 metre of the pipe centreline for pipes up to 160mm diameter and within 3 metres for pipes of 225mm diameter and above (this is a simplified summary of Thames Water's exclusion zone requirements — the actual minimum distances depend on the pipe diameter, depth, material, and construction method, and are set out in the Thames Water Build Over Agreement guidance); significantly increase the loading on the sewer (construction materials and structural loads that exceed the existing ground loading above the sewer will require structural support to be designed to bridge over the sewer, transferring the structural loads to foundations on either side of the sewer exclusion zone); allow access to the sewer for maintenance and inspection (Thames Water requires that inspection access to manholes in the path of the development is either maintained or relocated — a new inspection chamber may need to be constructed at a location that allows access despite the new structure above); the proposed structure must be designed and built so that the sewer can be accessed for emergency repairs without demolishing significant parts of the building above. Post-construction CCTV survey: Thames Water typically requires a post-construction CCTV survey of the sewer after the works are complete (usually 3 months after completion, when any settlement has occurred) to confirm that the construction has not caused damage to the sewer. The results of the post-construction CCTV survey are compared with the pre-application survey to identify any changes to the sewer's condition
  • How to identify whether a public sewer runs through your London garden: the starting point is a Thames Water records search — an online sewer records search, available for free through the Thames Water website, showing the location of recorded public sewers (within approximately 1:1250 scale accuracy). The Thames Water sewer records show: the location and diameter of recorded public sewers (including both the adopted main network sewers and the October 2011 transferred lateral drains); the location of manholes and inspection chambers; the direction of flow in the sewer (useful for understanding the drainage catchment). Important caveats on Thames Water sewer records: the records show the recorded position of sewers, which may not always correspond exactly with the actual position of the pipe in the ground — particularly for older Victorian sewers in London, where records may be inaccurate by up to 500mm or more in position and depth; some sewers in London, particularly older combined sewers and smaller lateral drains, may be unrecorded in Thames Water's database — a drainage engineer who encounters a previously unrecorded sewer during ground investigation must notify Thames Water so the sewer can be added to the records; the sewer records show the horizontal position of the pipe but do not typically show the depth, which is important for structural design. A drainage CCTV survey (carried out before design begins) provides more reliable information about the position, depth, condition, and construction material of any sewer within the proposed development area than the Thames Water records alone. For any rear extension or basement project in London, a pre-design drainage survey (including Thames Water records check, visual inspection of any accessible manholes or inspection chambers, and CCTV survey of any sewers within or close to the proposed works area) is strongly recommended as part of the early project feasibility stage
  • What happens if you build over a public sewer without a Build Over Agreement: Thames Water has a legal right under the Water Industry Act 1991 to access public sewers for maintenance, repair, and improvement. If a building is constructed over a public sewer without a Build Over Agreement, Thames Water can: require the building owner to demolish or alter the structure at the building owner's cost to allow access to the sewer; carry out works to the sewer in an emergency and charge the costs (including any resulting structural damage to the building above) to the building owner; refuse to issue retrospective Build Over Agreement approval, requiring the building to be modified or relocated. Additionally, building over a public sewer without a Build Over Agreement may: prevent you from obtaining Building Regulations completion certificate (Local Authority Building Control and private approved inspectors are required to check drainage and sewer compliance as part of the Part H inspection); create complications when selling the property (the CON29DW drainage search carried out by the buyer's conveyancer will reveal whether a Build Over Agreement was obtained, and an absence of a Build Over Agreement for a building over or near a sewer will be flagged as a risk item requiring investigation and potential remediation before the transaction can proceed). The cost of a retrospective Build Over Agreement application (where one was required but not obtained) is typically higher than a pre-application agreement — Thames Water may require additional information, reinstatement of access chambers, or structural works to the building — and the outcome is not certain (Thames Water may require structural modifications as a condition of retrospective approval)

Designing Around a Sewer: Bridging, Diversion, and Exclusion Zone Strategies

When a public sewer runs through a proposed rear extension area, there are three main design strategies:

Strategy 1 — Design the extension structure to bridge over the sewer: The extension foundations are designed to bridge over the sewer, with strip or pad foundations on either side of the sewer exclusion zone that span across the sewer. The structural floor and the walls above are supported by the bridging foundations and do not bear on the ground directly above the sewer. This is the most common approach for rear extensions where the sewer is relatively shallow (within 1.5m of the surface) and where the exclusion zone is not so wide that it makes the extension footprint unviable. The structural engineer designs the foundations to span the sewer exclusion zone, which may require: deeper foundations to maintain adequate bearing capacity at the correct distance from the sewer; reinforced concrete foundations or ring beams to carry the spanning loads; a structural slab (ground-bearing or suspended) to carry floor loads across the sewer exclusion zone. Thames Water's Build Over Agreement guidance provides specific technical requirements for the minimum dimensions of the bridging foundation (the size and location of the "raft" or "bridge" over the sewer depends on the sewer diameter, depth, and the structural loads being carried).

Strategy 2 — Application to divert the sewer: A sewer diversion involves physically relocating the public sewer away from the proposed development area — typically by laying a new sewer pipe on a new alignment that avoids the building footprint. A sewer diversion application is made to Thames Water under Section 185 of the Water Industry Act 1991, which gives the developer the right to divert a public sewer (at the developer's cost) where the sewer will interfere with the development. A sewer diversion typically costs £10,000–£50,000+ for a domestic garden sewer, depending on: the diameter of the sewer; the depth of the sewer; the length of the diversion; any ground conditions or other utilities that affect the diversion route; and Thames Water's design, inspection, and adoption fees. A sewer diversion is appropriate where: the exclusion zone makes the proposed extension layout unviable; a Build Over Agreement cannot be obtained (for example, because the sewer is too large or the structure is too complex); or the developer prefers a long-term solution that eliminates the ongoing maintenance access obligation. A sewer diversion allows the extension to be built without the sewer exclusion zone constraint, but the diversion itself adds significant cost and programme time.

Strategy 3 — Modify the extension design to avoid the sewer: In some cases, the simplest solution is to modify the extension design to keep the new structure outside the sewer exclusion zone entirely — either by making the extension shorter, narrower, or differently shaped to avoid the sewer. This approach avoids the need for either a bridging design or a diversion, and eliminates the Build Over Agreement requirement. Whether this strategy is acceptable depends on whether the resulting modified extension achieves the homeowner's objectives for the project.

Build Over Agreement Application Process and Costs

The Thames Water Build Over Agreement application process involves several steps, each with associated costs:

Step 1 — Thames Water sewer records check (free): download or view the Thames Water sewer records for the property to identify any recorded sewers within or near the proposed works. Thames Water provides a free online sewer records map (via their website) showing recorded public sewers.

Step 2 — Pre-application CCTV drainage survey (£300–£800): a CCTV survey of the sewer within the proposed works area, carried out by a WRc-accredited drainage contractor. The CCTV footage is used to assess the condition of the sewer and to determine the exact position and depth of the pipe. The CCTV survey report forms part of the Build Over Agreement application.

Step 3 — Structural design (included in the engineer's fee): the structural engineer designs the bridging foundations or structural slab in accordance with Thames Water's Build Over Agreement technical requirements and the project structural requirements. The structural design drawings form part of the application.

Step 4 — Build Over Agreement application to Thames Water (fee: £328–£695 as of 2024–2025 — Thames Water's fee structure has multiple tiers based on the type and complexity of the build-over): the application is submitted to Thames Water with: the proposed design drawings (plans, sections, and structural details); the CCTV survey report; the drainage engineer's or structural engineer's assessment; and the application fee. Thames Water aims to determine Build Over Agreement applications within 28 days of receiving a complete application (though complex applications may take longer).

Step 5 — Construction and Thames Water inspections: Thames Water may require inspections during construction (particularly of the foundation works over or near the sewer) to verify that the works comply with the approved Build Over Agreement conditions.

Step 6 — Post-construction CCTV survey (£300–£800): once the construction is complete and the building is settled (typically 3 months post-completion), a second CCTV survey of the sewer is carried out to confirm that no damage has occurred to the sewer during construction.

Total typical cost of a Build Over Agreement (Thames Water fees, CCTV surveys, engineer's time): £1,500–£4,000 for a standard domestic rear extension build-over, excluding the additional structural cost of the bridging foundation design itself.

Adoption Status Check and CON29DW Drainage Search

A key step in any London extension or basement project is confirming the adoption status of all drains and sewers in the proposed development area.

CON29DW drainage search: The CON29DW drainage search (the standard drainage search carried out as part of the conveyancing process for any property purchase in England and Wales) provides information on: whether the property is connected to the public sewer network; the location of public sewers within the boundaries of the property; whether there is a public sewer within the property boundaries that would affect development. The CON29DW search is carried out on the basis of the Thames Water records and identifies the presence of public sewers (adopted sewers maintained by Thames Water) in the property's boundaries.

Pre-design drainage records search: For an extension or basement project, a more detailed pre-design investigation is advisable, including: a Thames Water records request (the formal records information, as opposed to the free online map, which provides more precise positional data); inspection of all accessible manholes and inspection chambers within the property to confirm the adopted public sewer network and the routes of any private drains; a CCTV survey of any sewers that cannot be adequately assessed from the records and manhole inspection alone.

Adoption status: Even where a drain or sewer is not shown on the Thames Water records as an adopted public sewer, it may have been adopted after the most recent records update (particularly where the October 2011 transfer is recent relative to the records). In cases of uncertainty, Thames Water can be contacted directly to confirm the adoption status of a specific pipe or to request an adoption investigation. Building over a pipe that is actually an adopted public sewer without a Build Over Agreement, on the grounds that it was believed to be a private drain, does not protect the building owner from Thames Water enforcement action — Thames Water's rights apply to the physical sewer, regardless of whether the records correctly identified it as adopted.

Frequently Asked Questions

How close to a public sewer can I build a London extension?
Thames Water's Build Over Agreement guidance specifies minimum clearance distances from public sewers for new construction. As a general guide (the actual requirements depend on the specific sewer diameter, depth, material, and the proposed construction method): for pipes up to 160mm diameter, the minimum clearance from the pipe centreline to the nearest foundation wall or structural element is typically 1m; for pipes of 225mm diameter or larger, the minimum clearance is typically 3m from the pipe centreline. These clearances define the sewer exclusion zone — any new building structure (foundation, ground-bearing slab, or wall base) within the exclusion zone requires a Build Over Agreement and must be designed to bridge over the sewer. The specific exclusion zone for your project must be confirmed with a qualified drainage engineer or structural engineer who can review the sewer records, the CCTV survey results, and the proposed design to determine the applicable Thames Water requirements for your specific sewer.
Do I need a Build Over Agreement if the sewer is outside my extension footprint but near the boundary?
Yes, in some cases. Thames Water's Build Over Agreement requirements apply not only to structures directly over the sewer but also to structures within the sewer exclusion zone — which may extend outside the physical extent of the extension if the sewer is near the boundary. For a sewer of 225mm or larger diameter, the exclusion zone extends 3m from the pipe centreline — so if the sewer runs along a boundary at 0.5m from the party wall, the exclusion zone extends 2.5m into the proposed extension area. Additionally, even where the extension footprint does not overlap with the exclusion zone, the excavation for the foundations may extend into the exclusion zone (the bottom of a foundation excavation may be within the exclusion zone even if the finished foundation wall face is not). A Build Over Agreement application should be considered for any project where a public sewer is within the site boundary or within 3m of the proposed works.
Can I get a Build Over Agreement retrospectively if I have already built over a sewer?
Thames Water will consider retrospective Build Over Agreement applications, but they are more complex, more expensive, and less certain in outcome than pre-application agreements. For a retrospective application, Thames Water will typically require: a post-construction CCTV survey of the sewer to assess whether any damage has occurred during construction; structural drawings showing the as-built construction over the sewer; and evidence that the construction provides adequate access for future sewer maintenance and emergency repairs. If the as-built construction does not meet Thames Water's technical requirements (for example, if the clearance to the sewer is insufficient or if access chambers have been covered without a rodding eye or new chamber being provided), Thames Water may require structural modifications to the building as a condition of retrospective approval. In the worst case, Thames Water may require removal of the structure. For any project where a Build Over Agreement is required but has not been obtained, seek professional advice from a drainage engineer and Thames Water before taking further action — the earlier the issue is identified, the lower the remediation cost is likely to be.

Important Note

This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. rcbGroup offers free initial consultations — book your free survey.

Was this guide helpful? Share it:

Have a question about your project?

Chat with us on WhatsApp — Faith usually replies within the hour.

Ready to Discuss Your Project?

Free site survey. No obligation. Covering all Greater London & M25.

📞 Call now💬 WhatsAppFree Quote