Internal Refurbishment in London: Scope, Costs and Programme 2025

An internal refurbishment is the improvement, updating, or reconfiguration of the internal spaces of a property without significant changes to the external envelope or structural form of the building. For many London property buyers — particularly those buying a Victorian or Edwardian terrace or a period flat that has not been updated in a decade or more — an internal refurbishment is the first and most immediate priority after purchase. Getting the scope, sequencing, specification, and cost right from the start avoids the expensive second-round works (relaying floors after plumbing changes, redecoration after electrical work, and so on) that add unnecessary cost to a London refurbishment.

Key Takeaways

  • Internal refurbishment scope (London, full specification): strip-out and enabling works; first fix electrical (full rewire, consumer unit upgrade); first fix plumbing (replumb supply, waste, drainage); boiler replacement or heat pump; underfloor heating (if required); plastering (full skim after first fix); second fix electrical (sockets, switches, downlights, consumer unit commissioning, EICR); second fix plumbing (sanitaryware, kitchen connections, boiler commissioning); kitchen and bathroom installation; internal doors, skirting, architraves; flooring throughout; full redecoration. No planning permission required for internal works.
  • All-in cost ranges (London, 2025, labour + standard materials, kitchen and bathroom supply excluded): 1-bed flat (40-55 sq m): £30,000-£55,000. 2-bed flat (60-80 sq m): £45,000-£80,000. 2-bed terrace (85-110 sq m): £55,000-£95,000. 3-bed terrace (100-130 sq m): £70,000-£120,000. 4-bed semi/detached (130-200 sq m): £90,000-£180,000. Full rewire (3-bed terrace): £5,000-£9,000. Full replumb: £6,000-£12,000. Full plaster skim (3-bed): £7,000-£14,000. Bathroom labour and tiles (excl. suite): £3,500-£7,000.
  • Programme (London, 2025): full internal refurbishment of a 2-3 bed flat or terrace takes 8-14 weeks. Sequence: strip-out (weeks 1-2) → first fix structural and services (weeks 2-4) → plastering and screeds (weeks 4-6) → second fix and finishes (weeks 6-8) → flooring and decoration (weeks 8-10) → snagging and handover. Delays most commonly caused by: late delivery of client-supplied items (order kitchen, sanitaryware, tiles, and flooring before or at the start of the refurbishment); hidden defects uncovered at strip-out; and structural issues requiring Building Regulations approval.
  • Building Regulations required for: Part P electrical work (self-certified by NICEIC/NAPIT electrician or BCO application); new boiler or heat pump (Part J and Part L); structural alterations to load-bearing walls (Part A — structural engineer and BCO approval required); drainage connections near a public sewer (Thames Water build-over or connection approval). Building Regulations NOT required for: internal decoration; non-structural partition removal or addition; new flooring; internal door replacement; new kitchen or bathroom in existing positions without structural changes.

What does an internal London refurbishment typically include?

The scope of an internal refurbishment varies significantly based on the starting condition of the property, the owner's ambitions for the finished result, and the budget. For a typical London Victorian terrace or Edwardian flat that has not been significantly updated in 10-20 years, a thorough internal refurbishment typically covers: First fix works (structural and services): structural works — removing or widening internal doorways (non-structural stud walls or existing masonry partitions where no structural element is involved), or reconfiguring room layouts where feasible within the existing building structure. New wiring (full or partial electrical rewire): replaces ageing wiring, brings the installation up to current Part P (Building Regulations) and BS 7671 (IET Wiring Regulations 18th Edition) standards, and accommodates the modern socket, lighting, and data requirements of a contemporary home. EICR (Electrical Installation Condition Report) required on completion and must be provided to any incoming tenant. New plumbing (full or partial): replaces ageing lead supply pipes (lead pipes should be replaced on public health grounds — all London pre-war properties may still have lead supply pipes from the street connection to the main internal stop cock), copper or plastic (JG Speedfit/Hep2O) supply pipes throughout, and waste/drainage connections for new sanitaryware and kitchen. Boiler replacement or upgrade: a pre-condensing boiler (typically pre-2005 in London housing stock) should be replaced with a high-efficiency condensing combi or system boiler. Consider heat pump where EPC improvement is required (EPC C target for rental properties by 2028). Underfloor heating: wet or electric UFH, most commonly for the ground floor (kitchen, bathroom/WC) in a London refurbishment. Second fix works (internal finishes): plastering (full re-skim or patch repair of walls and ceilings after first fix services; new plasterboard partitions on new steel stud or timber frame where room reconfiguration is required). Flooring: solid or engineered hardwood or LVT (luxury vinyl tile) on ground and upper floors. Porcelain tile on kitchen floor and bathroom/WC floors. Joinery: new internal doors (solid core flush or panelled, with chrome or brushed stainless ironmongery), new skirting and architrave throughout, staircase refurbishment (repair, paint, or replace staircase treads and handrail). Kitchen: new kitchen installation (see separate kitchen guide). Bathroom/WC/en-suite: full strip-out and replacement of existing sanitaryware, tiles, shower, and vanity unit. Decoration: full decoration throughout (walls, ceilings, skirting, doors) in neutral specification. Typically two coats of emulsion on walls and ceilings, two coats of satinwood on joinery.

Internal refurbishment costs for London flats and houses (2025)

Typical all-in cost ranges for internal refurbishment in London (2025), inclusive of labour and all standard materials (but excluding kitchen and bathroom supply, which are treated as client-procured items in most standard RCB refurbishment packages): 1-bedroom London flat (40-55 sq m): light cosmetic refurbishment (decoration, new flooring, minor plumbing, new sanitaryware supply and fit, new light fittings): £15,000-£28,000. Full internal refurbishment (full rewire, full replumb, new boiler, full decoration, new kitchen and bathroom: labour-only plus cost of kitchens and bathrooms): £30,000-£55,000 all-in. 2-bedroom London flat (60-80 sq m): full internal refurbishment: £45,000-£80,000 all-in. 2-bedroom London Victorian terrace (85-110 sq m GIA): full internal refurbishment (full rewire, full replumb, new boiler, replastering in key areas, new kitchen, 2 bathrooms, full decoration, new internal doors and joinery, new flooring throughout): £55,000-£95,000 all-in. 3-bedroom London Victorian terrace (100-130 sq m GIA): full internal refurbishment as above: £70,000-£120,000 all-in. 4-bedroom London Victorian semi-detached or detached (130-200 sq m GIA): comprehensive internal refurbishment: £90,000-£180,000 all-in. Cost variables that most affect the London internal refurbishment price: Electrical: a full rewire of a 2-bedroom London flat: £3,500-£6,500. A full rewire of a 3-bedroom London terrace: £5,000-£9,000. Partial rewire or consumer unit upgrade only: £1,500-£4,000. Plumbing: full replumb of a 2-bed London flat: £4,000-£9,000. 3-bed terrace: £6,000-£12,000. Plastering: full skim plaster of walls and ceilings of a 2-bed flat: £5,000-£9,000. 3-bed terrace: £7,000-£14,000. Bathroom: supply and fit of a standard bathroom (new bath, WC, basin, shower, fully tiled walls and floor, heated towel rail): labour and tiles £3,500-£7,000 + client-supplied sanitaryware suite. En-suite: smaller room but similar complexity — labour and tiles £2,500-£5,500 + suite. Kitchen: installation of a client-supplied kitchen (labour, plumbing connections, electrical connections, worktop cutting and fitting): £1,500-£4,000. Flooring: supply and fit of engineered oak (14-3mm click system) for ground and upper floors of a 3-bed terrace (60 sq m): £4,000-£9,000. Porcelain tile supply and fit (bathroom and kitchen): £60-£140/sq m installed.

Sequencing and programme for a London internal refurbishment

Getting the sequencing right in a London internal refurbishment is critical — out-of-sequence work increases cost (e.g., replastering a wall and then cutting it for a cable or pipe), extends the programme, and creates unnecessary disruption. Standard RCB Design & Build sequence for a London internal refurbishment: Week 1-2 — Strip-out and enabling works: full or partial strip-out of the existing kitchen (cabinets, appliances, worktops), bathroom/s (tiles, sanitaryware), and any internal stud partition walls being removed or reconfigured. Removal of existing flooring (if being replaced). Skip hire and waste disposal. Week 2-4 — First fix structural and services: structural works where applicable (openings, lintels, padstones, where structural alterations form part of the refurbishment scope). First fix electrical (new wiring runs, back-boxes, consumer unit location confirmed). First fix plumbing (new supply pipework runs, waste and soil pipe connections for new sanitaryware positions, boiler relocation if required). First fix underfloor heating (if wet UFH: screed over pipework or slim-mat system beneath tiles). Week 4-6 — Plastering, boarding, and screeds: new plasterboard to any reconfigured stud partitions. Full skim plaster to walls and ceilings throughout (in sequence with first fix — plaster after first fix work is complete in each room). Sand and cement or self-levelling screed over wet UFH or to level existing floors. Week 6-8 — Second fix and finishes: second fix electrical (sockets, switches, downlights, extractor fans, consumer unit commissioning, EICR test). Second fix plumbing (sanitaryware installation, tiling of bathrooms and WC, kitchen sink, dishwasher and washing machine connections, boiler commissioning). Kitchen installation (carcasses, worktops, splashback tiles, appliances). Internal doors, skirting boards, and architraves. Week 8-10 — Flooring and decoration: floor finishes throughout (engineered oak, LVT, or porcelain tile). Full redecoration (mist coat on new plaster, two coats emulsion, satinwood on joinery). Snagging and handover. Typical total programme: 8-14 weeks for a 2-3 bedroom London flat or terrace full internal refurbishment, depending on scope, site access, and material lead times. Note that some material lead times (bespoke kitchens, specialist tiles, imported sanitaryware) can extend the programme if not ordered early. Order all client-procured items (kitchen, sanitaryware, tiles) as early as possible — ideally before the refurbishment starts.

Frequently Asked Questions

How long does an internal refurbishment take in London?
A typical full internal refurbishment of a 2-3 bedroom London flat or Victorian terrace takes 8-14 weeks from strip-out to handover, depending on scope. The critical path is typically: first fix services (electrical and plumbing) → plastering → second fix and finishes → flooring and decoration. Delays most commonly occur from: late delivery of client-procured items (kitchen, sanitaryware, tiles, flooring); hidden defects uncovered during strip-out (concealed damp, defective plumbing, insufficient electrical capacity); and planning complications (if structural works requiring Building Regulations approval are involved). Order all client-procured items before or at the start of the refurbishment.
How much does a full internal refurbishment cost in London?
All-in costs (London, 2025, inclusive of labour and standard materials, excluding kitchen and bathroom supply): 1-bed flat: £30,000-£55,000; 2-bed flat: £45,000-£80,000; 2-bed terrace: £55,000-£95,000; 3-bed terrace: £70,000-£120,000; 4-bed semi-detached or detached: £90,000-£180,000. These ranges reflect a full scope (rewire, replumb, boiler, plaster, floors, decoration, new doors and joinery). Light or cosmetic refurbishments (decoration, minor plumbing, new sanitaryware only) cost significantly less.
Do I need planning permission for an internal refurbishment in London?
No — internal refurbishment works (decorating, new kitchen, new bathrooms, rewiring, replumbing, new flooring, internal non-structural partition reconfiguration) do not require planning permission. Building Regulations approval is required for: full or partial rewires (Part P electrical work — typically self-certified by an NICEIC or NAPIT registered electrician, or submitted as a Building Regulations application to the local authority building control); new boiler or heat pump installation (Part J and Part L compliance); structural alterations (any removal or modification of load-bearing walls or structures — Part A Building Regulations, requires structural engineer input and building control approval); bathroom and kitchen additions that involve building over or near a public sewer (Thames Water approval).

Important Note

This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.