Finding a Plot and Understanding the Planning Position
The first and often most difficult challenge in a London self-build is finding a suitable plot. London's density means that genuinely available development plots are rare, and competition for them is fierce.
**Types of London self-build plots:**
- •**Garden plots:** Subdividing a large garden to create a new plot. This is the most common source of self-build opportunity in London. The planning position varies significantly — some boroughs actively resist garden subdivision ('garden grabbing'), while others permit well-designed infill development in appropriate contexts.
- •**Replacement dwellings:** Demolishing an existing structure (a garage, a bungalow, or a small house) and replacing it with a larger or better-quality new dwelling. The replacement dwelling typically must be no larger than a certain multiple of the existing structure under local planning policy, though permitted development rights (Class G and H of the GPDO) allow some replacement dwellings in certain circumstances.
- •**Gap sites and brownfield land:** Underdeveloped plots between existing buildings, former commercial sites, and other brownfield opportunities. These require careful feasibility assessment — ground conditions, access, services, and planning history all matter.
- •**Airspace developments:** Building above an existing structure (a garage, a single-storey building, or a lower-density structure) to create new residential accommodation above. Airspace development is technically complex and requires careful structural assessment.
**The planning position for new residential development in London:**
A new dwelling in London requires full planning permission — permitted development does not extend to new dwellings (with very limited exceptions). Key planning considerations include:
- •**Local plan policies on housing and density:** Each London borough has its own policies on where new housing is permitted, what density is acceptable, and what design standards apply.
- •**London Plan standards:** The Mayor of London's London Plan sets minimum space standards (the Nationally Described Space Standard), minimum daylight and sunlight standards, and amenity space requirements that all new dwellings must meet.
- •**Design standards:** New dwellings in London are assessed against the London Plan's design policies and the borough's local design policies — typically requiring good quality design that responds to local context.
- •**Conservation areas and listed building context:** Many London streets are in conservation areas — significant design constraints apply to new buildings in these areas.
**Pre-application advice:** For a new dwelling, pre-application engagement with the borough's planning team is strongly recommended before investing in full planning drawings. Pre-application advice is a paid service (typically £200–£800 depending on the borough and scheme size) but provides useful early feedback on whether a new dwelling is likely to be supported in principle.
The Stages of a London Self-Build
A London self-build project typically proceeds through the following stages:
- **Stage 1: Site purchase and feasibility**
- •Purchase or secure option on the plot
- •Commissioning a structural survey (if there is an existing structure), a topographical survey, and a ground investigation
- •Feasibility design: a sketch scheme to test what is achievable on the plot within likely planning parameters
- •Pre-application planning advice
- •Utility connections feasibility: water, gas, electricity, drainage connections to the site
- **Stage 2: Design and planning**
- •Appoint architect and specialist consultants (structural engineer, ecology, daylight/sunlight, heritage if relevant)
- •Develop design to planning stage
- •Submit planning application (typically 8–13 weeks to decision; may involve pre-application consultation)
- •Once planning is granted: develop technical design to construction stage (RIBA Stage 4)
- •Building Regulations application (via approved inspector or local authority building control)
- **Stage 3: Pre-construction**
- •Tender and appoint principal contractor (or design-and-build contractor)
- •Finalise specification and material selections
- •Utility connections arranged
- •Party wall agreements where required
- •CDM notifications (if the project is notifiable — which most new builds in London will be)
**Stage 4: Construction** A new build in London typically takes 14–24 months on site from groundworks start to practical completion, depending on size and complexity:
- •**Months 1–3:** Groundworks, foundations (piling in many London sites due to made-up ground or proximity to underground infrastructure), slab
- •**Months 3–8:** Superstructure (walls, floors, roof frame)
- •**Months 6–10:** Weatherproofing (roof, windows, external doors)
- •**Months 8–14:** First-fix M&E (electrical, plumbing, heating, MVHR)
- •**Months 10–16:** Internal finishes (insulation, plastering, screed)
- •**Months 14–20:** Second-fix (joinery, electrical, plumbing, kitchen, bathrooms)
- •**Months 18–24:** Decoration, external works, snagging
- **Stage 5: Completion and occupation**
- •Building Control completion certificate
- •Structural warranty (typically 10-year warranty with NHBC Buildmark or similar)
- •Occupation and CML (Council of Mortgage Lenders) sign-off if mortgaged
- •Registration of new dwelling with Land Registry
Costs of a London Self-Build
A London self-build is expensive — London construction costs are among the highest in the country, and land costs are very high.
**Typical construction cost ranges:**
- •**Standard specification new build in London:** £2,500–£3,500/m² (gross internal area)
- •**Good specification:** £3,500–£4,500/m²
- •**High specification / architecturally complex:** £4,500–£7,000+/m²
- For a 150m² (gross internal area) four-bedroom house in London at a good specification:
- •Construction cost: approximately £525,000–£675,000
- •Professional fees (architect, structural engineer, specialist consultants): approximately £60,000–£90,000 (10–15% of construction cost)
- •Planning and Building Control fees: approximately £5,000–£15,000
- •VAT: New builds are zero-rated for VAT on construction — a significant saving compared with renovation work (where the 20% standard VAT rate applies to the contractor's labour). Note: this applies to the construction contract, not to professional fees or materials purchased directly by the client.
- **Additional costs often overlooked:**
- •Ground investigation and topographic survey: £3,000–£8,000
- •Utility connection costs: £5,000–£30,000+ depending on location and services available
- •Structural warranty: £1,500–£5,000
- •Stamp Duty Land Tax on the land purchase (if purchased separately from an existing house)
- •Demolition costs if an existing structure is to be removed: £10,000–£40,000
**Financing a London self-build:** Self-build mortgages are available for new builds in London — they release funds in stages as the build progresses (rather than as a single sum on completion). The government's Self-Build Register and Help to Build scheme provide some support, though availability and eligibility criteria vary. A specialist self-build mortgage broker is advisable for this type of project.
Frequently Asked Questions
Do I need planning permission to build a new home in London?▼
How much does it cost to build a new home in London?▼
How long does it take to build a new home in London?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. To talk through your own project, book a project review.