What a Full Refurbishment Typically Involves
A full house refurbishment in London varies significantly in scope — from a comprehensive upgrade of all rooms to a complete strip-back-to-brick and rebuild. The following is a typical scope for a Victorian terrace undergoing a full refurbishment:
- **Structure and fabric:**
- •Removal of internal partitions (where layout changes are planned)
- •Structural alterations (new openings, steel beams)
- •Party wall and structural repairs where found
- •Asbestos survey and removal (if required)
- **Mechanical and electrical:**
- •Full electrical rewire (Victorian properties frequently have ageing wiring that should be replaced)
- •New consumer unit (fuse box upgrade)
- •Replacement central heating system (if the existing boiler or radiators are old or undersized)
- •First-fix plumbing (relocating/adding bathrooms, kitchen)
- •New heating zones, smart controls
- **External fabric (often included in a full refurbishment):**
- •Roof inspection and repairs or replacement where required
- •Window replacement (if original sash windows are beyond repair — though sash restoration is often preferred)
- •External doors
- •External wall inspection and repointing or rerendering where required
- **Insulation and plastering:**
- •Internal wall insulation where practical (particularly in houses with no cavity walls)
- •Floor insulation (if floors are being replaced)
- •Full replastering throughout (skim coat on existing or full replaster where condition warrants)
- **Kitchens and bathrooms:**
- •New kitchen (client-supplied units at rcbGroup)
- •New bathrooms (typically 1–3 depending on house size)
- •Ensuites (in loft conversion if combined with loft project)
- **Finishes:**
- •Flooring (restoration of original boards, engineered hardwood, LVT, or carpets as required)
- •Full decoration
- •Joinery (skirting, architraves, internal doors, fitted storage)
The Typical Programme for a London Full Refurbishment
A full house refurbishment of a 3-bedroom London Victorian terrace (approximately 90–120m² gross internal area) typically takes 20–30 weeks on site from start to practical completion. The following is a typical programme outline:
- **Weeks 1–2: Enablement and demolition**
- •Soft strip of all rooms (carpets, fixtures, fittings)
- •Selective demolition (non-load-bearing walls, old kitchen and bathroom fittings)
- •Scaffold erection if roof or external works are included
- •Asbestos removal if found
- **Weeks 3–5: Structural works**
- •Structural openings (temporary propping, steel installation, padstones)
- •Any structural repairs to party walls or existing structure
- •Building Control structural inspection
- **Weeks 4–8 (overlapping with structural): Groundworks and external**
- •Roof repairs or replacement if included
- •External repointing or rerendering if included
- •New windows and external doors (typically supply has an 8–12 week lead time — order at week 1)
- **Weeks 7–12: First-fix M&E**
- •Full electrical rewire (cable runs, back boxes, consumer unit roughed in)
- •Heating: new boiler, radiator positions, zone controls
- •First-fix plumbing: supply and waste pipework to all bathrooms and kitchen
- •MVHR or ventilation ducting if specified
- **Weeks 10–14: Wet trades**
- •Insulation (where applicable)
- •Screeds (bathroom and kitchen floors if screed zones required)
- •Plasterboarding and skim plastering throughout
- •Drying time for screed: 4–6 weeks (this is a critical path item — cannot be skipped)
- •Drying time for plaster: 2–4 weeks
- **Weeks 14–20: Second-fix and finishes**
- •Second-fix joinery (door linings, skirtings, architraves, staircase)
- •Second-fix electrical (face plates, light fittings, consumer unit final connections)
- •Second-fix plumbing (sanitaryware, kitchen appliances)
- •Kitchen installation (client-supplied units)
- •Tiling (bathrooms and kitchen)
- •Decoration (undercoat and finish coat)
- •Floor finishes (hardwood, LVT, or carpets)
- **Weeks 20–25 (overlapping with second-fix): External and landscaping**
- •External works (garden, paths, driveway)
- •Building Control final inspection
- **Weeks 25–28: Snagging and completion**
- •Snagging inspection and rectification
- •Building Control completion certificate
- •Handover and documentation
**Note on programme duration:** The critical path constraint in most London refurbishments is the drying time for screeds and plaster — typically 6–8 weeks of drying time between the wet trades stage and the commencement of second-fix. This waiting period cannot be shortened without affecting the quality of finishes. Projects that appear slower than expected during this phase are often running to programme.
Managing the Process as a Client
- **Before work starts:**
- •Agree the scope in writing and in sufficient detail — what is and is not included, what materials are client-supplied, what the exclusions are
- •Agree the programme and get a written version from the contractor
- •Confirm all client-supplied items and their lead times — windows, kitchen units, bathroom sanitaryware, floor finishes, tiles. Many of these items have 6–12 week lead times. If they are not ordered before the project starts, they will delay the project.
- •Notify your buildings insurer that the property is undergoing a full refurbishment — the risk profile changes significantly during a comprehensive strip-out and rebuild
- **During the project:**
- •Visit the site regularly (weekly where possible) and take photographs at each visit
- •Attend the progress meeting (if the contractor runs one) or request fortnightly progress updates
- •Make decisions promptly when asked — remember that delayed decisions cascade into programme delays
- •Keep a log of all agreed variations (changes to the scope) in writing
- •If living off-site during the refurbishment, agree a re-entry date with the contractor and build in a realistic buffer before you plan to move back in
**Living in during a refurbishment:** Some clients attempt to live in a property during a full refurbishment — this is generally not recommended for a comprehensive strip-back refurbishment, as the work is inherently disruptive, dusty, noisy, and may periodically disconnect essential services. For a phased refurbishment (one room or floor at a time), it may be possible to remain in part of the property. Discuss the phasing implications with your contractor before committing to this approach.
Frequently Asked Questions
How long does a full house refurbishment take in London?▼
Should I move out during a full house refurbishment in London?▼
What is the most important thing to do before a full house refurbishment starts in London?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. To talk through your own project, book a project review.