Contents
Cost Comparison: New Build vs Renovation
**New build costs in London (2026, exc. land and professional fees):**
New build construction costs in London depend on specification, site conditions, and structure type:
- •**Basic specification** (brick/block, standard fixtures): £2,000–£2,800/m² (Gross Internal Area)
- •**Mid-specification** (quality finishes, good glazing specification): £2,500–£3,500/m²
- •**High specification** (bespoke architecture, premium materials, complex structure): £3,500–£5,500/m²
For a typical 160m² detached house: build cost £320,000–£560,000, excluding land, planning, professional fees, and landscaping/external works.
**Renovation costs in London (2026):**
Full renovation of a Victorian or Edwardian terrace involves retaining the existing structure and upgrading it to a modern standard:
- •**Cosmetic renovation** (redecoration, new kitchen, new bathrooms, minor repairs): £400–£900/m²
- •**Medium renovation** (structural openings, full M&E upgrade, plastering, kitchen/bathrooms): £900–£1,500/m²
- •**Full structural renovation** (major remodelling, new M&E, extensions, loft conversion): £1,500–£2,500/m² (of total floor area including new elements)
For a typical 120m² Victorian terrace with a 30m² extension: full renovation + extension, all-in: £150,000–£250,000, excluding land purchase costs and professional fees.
**The key cost comparison:** For equivalent floor area, renovation of an existing property is typically cheaper than a new build by 20–40%. The existing shell (walls, roof, windows, drainage) has already been paid for once — you are improving rather than constructing from scratch. However, old buildings can conceal expensive surprises (asbestos, structural issues, drainage problems) that new builds do not.
Planning Risk: New Build vs Renovation
**Planning risk for new builds:**
Building a new house on a plot in London (demolishing an existing building or building on vacant land) typically requires full planning permission. This is a higher-risk planning route than householder extensions because:
- •New build proposals are assessed against the Local Development Plan, design codes, and character of the area
- •Height, massing, materials, and visual impact are all assessed
- •Conservation Area proposals are especially scrutinised — new buildings must be 'of equivalent quality' to the context and are often contentious
- •The council may require a Design and Access Statement, a Heritage Statement (if there is a listed structure nearby), and sometimes a planning viability assessment
- •Objections from neighbours are common and can delay decisions
- •Some boroughs are resistant to demolishing existing housing stock even to build new housing in its place
**Planning risk for renovation:**
- Renovating an existing building generally has a lower planning risk profile:
- •Extensions within PD limits do not require planning permission
- •Extensions requiring planning are householder applications — a simpler and more predictable process
- •The existing building's footprint and mass is established — you are not introducing a new massing into the street
- •Listed buildings present high planning risk for renovation (listed building consent required for most alterations), but non-listed Victorian and Edwardian stock is generally more straightforward
- **When new build planning can be easier:**
- •If the existing building is in poor structural condition and a certificate of lawful use confirms it is a redundant building
- •In some outer London locations where there is a clear need for housing supply and the site is allocated for development
- •Where the council has designated a site for residential development through a Site Allocation in the Local Plan
Timeline Comparison
**New build timeline:**
- •Site acquisition: 2–6 months (conveyancing)
- •Pre-application planning advice: 4–8 weeks
- •Design and planning preparation: 4–12 months (complex schemes)
- •Planning application (full): 13 weeks statutory; often 6–12 months in practice
- •Technical design and Building Regulations: 4–8 weeks
- •Contractor procurement: 4–8 weeks
- •Construction: 12–24 months (depending on size)
- •Landscaping, commissioning, snagging: 2–4 months
**Total new build timeline (land found to completion): 3–5 years for most London new builds**
**Renovation timeline:**
- •Property acquisition: 2–4 months
- •Design (architect): 2–4 months
- •Planning (householder, if required): 2–4 months
- •Technical design and Building Regulations: 1–2 months
- •Contractor procurement: 1–2 months
- •Construction: 3–9 months (depending on scope)
- •Snagging: 2–4 weeks
**Total renovation timeline (property found to completion): 12–24 months for most significant renovation projects**
Renovation is typically 1–3 years faster than a comparable new build, primarily because planning risk is lower and construction is faster (you are not starting from foundations).
Financial Return: Which Is More Profitable?
**For investment purposes (building to sell):**
The profitability of new build vs renovation depends primarily on the land/property acquisition cost relative to the end value (GDV — Gross Development Value).
A common development finance rule of thumb (the '70% rule') suggests that the total of land cost + build cost + professional fees + finance costs should not exceed 70% of GDV, leaving 30% for profit and contingency.
- In London, where land is very expensive:
- •A plot with planning permission for a 3-bed house in Zone 2–3 might cost £300,000–£600,000
- •Build cost for the house: £320,000–£480,000
- •Professional fees and finance: £60,000–£100,000
- •Total cost: £680,000–£1,180,000
- •GDV (selling price of the completed house): £700,000–£1,100,000 depending on location
- •Profit margin: often thin or negative in current London market conditions
- For renovation:
- •Buy a Victorian terrace requiring full renovation: £450,000–£700,000 (depending on borough)
- •Full renovation cost: £120,000–£200,000 (including extension)
- •Total: £570,000–£900,000
- •GDV: £700,000–£1,100,000 (depending on final specification and postcode)
- •Profit margin: typically 10–25% — better than many new build schemes in London
**For homeowners (building to live in):**
For a homeowner who plans to live in the property long-term, the new build vs renovation question is more about personal preference and aspiration than pure financial return:
- •A renovated Victorian terrace offers character, established neighbourhood, potentially lower initial purchase cost
- •A new build offers energy efficiency from the outset, modern layout, less maintenance in early years
- •For most London families, renovation of an existing Victorian property plus an extension is the most common and often most sensible path — it captures the character and location they want while creating the space they need
Frequently Asked Questions
Is it cheaper to renovate or build new in London?▼
Is it easier to get planning permission for a renovation or a new build in London?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. To talk through your own project, book a project review.
Was this guide helpful? Share it:
Have a question about your project?
Message us on WhatsApp or call — we reply during working hours (Mon–Fri 8am–6pm, Sat 9am–2pm).