Construction Programme Explained: How Long Your Project Will Take

One of the most common causes of homeowner frustration in construction is not cost overrun — it is programme overrun. Projects take longer than expected partly because construction is inherently complex, but mostly because homeowners and contractors alike underestimate the pre-construction activities that happen before work starts: planning applications, Building Control approval, party wall process, structural engineer appointments, material lead times, and contractor mobilisation. This guide sets out realistic timescales for common London residential projects — both on-site and from the moment you decide to proceed.

Key Takeaways

  • Every project has two programme components: the on-site programme (actual construction duration, typically 8–28 weeks depending on project type) and the pre-construction programme (planning, Building Control, party wall, structural engineering, tender, and contractor mobilisation — typically adding 4–14 months before site start); homeowners who expect to be building in 4–6 weeks from decision are almost always disappointed
  • The total programme from 'I've decided to proceed' to practical completion is typically 8–18 months for a London extension or loft conversion — 4–6 months pre-construction + 14–18 weeks on-site for a typical single-storey rear extension with planning permission required
  • Serve party wall notices on Day 1 of the design process (not after planning permission) — the Section 3 notice period is 2 months minimum, and this is on the critical path; ordering structural steel, bespoke windows, and kitchen units as soon as specifications are fixed (not when they are needed on site) avoids the most common causes of on-site programme slippage
  • Build 10–15% programme contingency into the on-site programme, and accept that unforeseen site conditions (asbestos, buried drainage, structural surprises), late homeowner decisions on materials, and inspection wait times are normal features of domestic construction in London — they should be expected, not treated as exceptional events
  • A written programme that is a contract document (showing all pre-construction activities, site milestones, material procurement dates, and inspection stages) is the most effective management tool for both contractor and homeowner accountability — produced before contract signing and updated monthly during construction

The two components of the total project programme

**Why 'how long will it take?' needs two answers**:

Every project has two distinct programme elements:

1. *The on-site programme*: The duration of actual construction works from site start to practical completion 2. *The pre-construction programme*: The activities that must happen before the contractor sets foot on site — design, planning, Building Control, party wall, and structural engineering

Homeowners who ask 'how long will my extension take?' are usually thinking of the on-site programme. Contractors who quote a 12-week programme are usually answering that question. But the full journey from 'I've decided to do this' to 'the extension is complete' is typically 6–14 months longer than the on-site programme alone.

**The pre-construction programme — London typical activities and durations**:

| Activity | Who does it | Typical duration | |---|---|---| | Appoint architect / architectural technician | Client | 1–2 weeks | | Concept design and drawings | Architect | 2–4 weeks | | Planning application preparation | Architect | 1–2 weeks | | Planning application determination | LPA | 8–14 weeks (statutory 8 weeks; in practice up to 14 for London LPAs) | | Structural engineer appointment | Client / Architect | 1 week | | Structural engineer calculations | SE | 2–4 weeks (after drawing set agreed) | | Building Regulations Full Plans application | Architect / SE / contractor | 1 week to submit | | Building Regulations plan checking | BC body | 5 weeks statutory; 3–4 weeks for Approved Inspector | | Party wall notices served | Client / party wall surveyor | Day 1 — serve as early as possible | | Party wall response period (Section 3) | Adjoining owner | 2 months minimum | | Party wall Award (if dissent) | Surveyors | +2–6 weeks after dissent | | Tender — prepare scope and send to 3 contractors | Client / Architect | 1–2 weeks | | Tender — contractors price and return | Contractors | 2–4 weeks | | Tender assessment and appointment | Client | 1 week | | Contractor mobilisation (notice period, SSIP, insurance, sub-contractor bookings) | Contractor | 4–8 weeks |

  • *Practical reality*: Many of these activities can run in parallel — structural engineering during planning determination; Building Control application during tender period; party wall notices served on day 1 of design. A well-coordinated pre-construction programme can compress these activities to approximately:
  • Minimum: 4–5 months (where no planning is needed, neighbours consent immediately on party wall, and a contractor is available without a long mobilisation lead)
  • Typical: 6–9 months (planning application with standard 8–10 week determination + Building Control + party wall + contractor mobilisation)
  • Extended: 9–14 months+ (planning refusal and appeal, complex party wall dispute, multiple rounds of Building Control comments, or contractor with a long mobilisation queue)

**Serving party wall notices as early as possible**:

The party wall process is entirely separate from planning and Building Control — it runs in parallel. The Section 3 notice period is 2 months minimum. If both neighbours dissent and each appoints their own surveyor, the Award takes a further 2–6 weeks. Serving party wall notices on day 1 of the design process — rather than after planning permission is obtained — can save 2–4 months on the total programme.

On-site programme durations by project type

**Realistic on-site programme durations for London residential projects (2025)**:

All durations assume: contractor has an experienced site team; materials are ordered with adequate lead times; no significant unforeseen conditions (buried services, poor ground, unexpected structural issues); and Building Control inspections are available without excessive wait times.

  • **Single-storey rear extension (30–40m², open plan kitchen/dining)**:
  • Strip-out and demolition: 2–3 days
  • Excavation and foundation concrete: 1 week
  • Superstructure (blockwork or timber frame): 2–3 weeks
  • Flat or pitched roof structure and weatherproofing: 1–2 weeks
  • First-fix M&E (electrical, plumbing): 1.5 weeks
  • Windows and external doors: 1 week (after frame is set)
  • Insulation, first-fix carpentry: 1 week
  • Plastering and skim: 1.5 weeks (+ 1 week drying)
  • Second-fix M&E, carpentry, decorating: 2 weeks
  • Kitchen installation and finishing: 1–2 weeks
  • *Total on-site: 14–18 weeks*

**Single-storey extension + ground floor refurbishment**: *Total on-site: 18–24 weeks*

**Single-storey rear + side return extension (wrap-around)**: *Total on-site: 18–24 weeks*

  • **Double-storey rear extension**:
  • Significantly more complex due to structural requirements at first floor, scaffolding requirements, and coordination with upper floor rooms during construction
  • *Total on-site: 20–28 weeks*

**Loft conversion — Velux**: *Total on-site: 8–12 weeks*

**Loft conversion — box dormer**: *Total on-site: 10–14 weeks*

**Loft conversion — L-shaped dormer**: *Total on-site: 14–18 weeks*

**Loft conversion — mansard**: *Total on-site: 16–22 weeks*

**Full flat refurbishment (2-bed flat, occupied during works)**: *Total on-site: 10–14 weeks*

**Full flat refurbishment (vacant, full strip-out and refit)**: *Total on-site: 14–18 weeks*

**Full Victorian terrace refurbishment (3-bed, strip-out to shell and refit)**: *Total on-site: 20–30 weeks*

**HMO conversion (3-bed to 5-bed, fire compliance, en-suites)**: *Total on-site: 12–18 weeks*

**Garage conversion (single, to habitable use)**: *Total on-site: 6–10 weeks*

**Basement conversion (shell condition to completion)**: *Total on-site: 16–28 weeks (depending on excavation and waterproofing complexity)*

**Critical path items that extend the on-site programme**:

  • *Structural steel fabrication and delivery*: Typically 4–8 weeks from order to delivery. If not ordered early enough, the structural opening cannot be formed and the programme stalls.
  • *Bespoke windows and doors*: 6–12 weeks lead time for aluminium or timber sliding or bifold doors. Order when the frame is measured — not when you want them.
  • *Kitchen lead time*: Bespoke fitted kitchens from trade suppliers: 6–12 weeks. IKEA: typically 2–4 weeks from order to delivery. Never assume kitchens are available off-the-shelf for delivery in less than 4 weeks.
  • *Building Control inspection availability*: During busy periods, BC inspectors may have 1–2 week wait times for inspection bookings. Build buffer into the programme at inspection-dependent stages.

Managing the programme — what homeowners and contractors can do

**Setting a realistic programme at the outset**:

  • The most effective way to manage construction programme expectations is to produce a written programme at the start of the project that shows:
  • All pre-construction activities (design, planning, BC, party wall, structural engineering, tender)
  • The planned site start date
  • On-site milestone dates (substructure, superstructure, weathered-in, first-fix complete, plastering, second-fix, practical completion)
  • Key material procurement milestones (steel order date, window order date, kitchen order date)
  • Building Control inspection stages

This programme should be prepared by the architect or contractor before the contract is signed and should form a contract document (the JCT Minor Works contract has a provision for a programme to be attached). A written programme creates accountability — both for the contractor (to hit milestones) and for the homeowner (to make decisions, supply materials, and respond to contractor queries promptly).

**The most common causes of programme slippage in London residential projects**:

1. *Late decision-making by the homeowner*: Tiles, kitchen units, sanitaryware, flooring, and ironmongery must be specified and ordered before the contractor needs them — often 6–10 weeks ahead. Late material decisions are the most common cause of practical delay in domestic refurbishments.

2. *Unforeseen site conditions*: Buried drainage routes, unexpected structural issues (deteriorated floor joists, incorrect load assumptions), asbestos discovery (common in pre-2000 London houses — artex ceilings, floor adhesives, pipe insulation), and underground obstructions (old Victorian wells, coal holes, collapsed drains) all require programme allowance.

3. *Structural steel delays*: Ordering structural steel too late is a very common programme delay. The contractor should order steel as soon as the structural engineer's scheme design is agreed — not when the structural calculations are complete.

4. *Party wall delays*: Uncooperative adjoining owners who appoint surveyors who then prolong the Award process can delay the start of notifiable works significantly. There is no contractual shortcut — the statutory process must complete.

5. *Planning delays*: LPA determination of a householder application taking 14+ weeks (common in under-resourced London LPAs) when the contractor's programme assumed 8 weeks.

**The 10% contingency rule for programme as well as cost**:

Just as 10–15% cost contingency should always be built into a project budget, 10–15% programme contingency should be built into the on-site programme. A 14-week extension programme should be planned to practical completion 15–16 weeks, not 14 weeks. This buffer absorbs the minor delays (inspection wait times, material delivery slippage, a wet week when external work is critical-path) that are inevitable on any real project.

Frequently Asked Questions

How long after getting planning permission can we start building?
Planning permission itself does not set a start date — it simply authorises the works to be carried out. However, before starting on site, you still need: Building Regulations Full Plans approval (or Building Notice submitted at least 2 days before starting); party wall Award in place (if triggered — 2–4 months from notice); structural engineer calculations approved; contractor appointed and mobilised (4–8 weeks); and key materials ordered (steel: 4–8 weeks lead; windows: 6–12 weeks). Realistically, even with a smooth pre-construction programme, allow 3–5 months from planning permission grant to actual site start.
Can my contractor give me a guaranteed completion date?
A competent contractor can give you a contractual completion date (a date by which they undertake to achieve practical completion under the contract) with a mechanism for adjusting that date if risk events occur (exceptionally adverse weather, design changes, ground conditions). Most standard form domestic contracts (JCT Minor Works, FMB Contract) include an extension of time mechanism for both employer-risk events (design changes, client-caused delay) and neutral events. However, a 'guaranteed' date in the sense of an absolute commitment regardless of what happens on site is not commercially realistic — the contractor cannot guarantee that asbestos will not be found, that the neighbours will not delay the party wall process, or that a heatwave will not make concrete pouring impossible for two weeks.
Is it possible to live in the house during the construction works?
Possible but challenging, depending on the project type. For loft conversions, life is disrupted but usually manageable — the works are physically separate from the main living areas for most of the programme. For ground floor extensions and kitchen renovations, losing the kitchen for 8–16 weeks requires temporary kitchen arrangements. For whole-house refurbishments or basement conversions with extensive works throughout the house, living in the property during works is generally inadvisable — the dust, noise, restricted access, and complexity of working around residents significantly slows the programme and reduces the quality of life. Renting alternative accommodation for the duration of a major refurbishment is typically the better outcome, particularly where young children or vulnerable family members are involved.

Important Note

This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.