First Fix vs Second Fix — What Each Stage Means and What It Includes

Construction projects — extensions, loft conversions, and refurbishments — proceed through a logical sequence. First fix and second fix are terms that describe two distinct phases of trade work that bracket the plastering phase. Understanding what each stage includes helps homeowners communicate more clearly with their contractor, follow the programme with confidence, and understand why certain items appear on a payment schedule. This guide explains what first fix and second fix mean for electrical, plumbing, and carpentry trades.

Key Takeaways

  • First fix = all concealed infrastructure before plastering: cable runs, pipework, stud framing, plasterboard fixing
  • Second fix = all visible finished elements after plastering: switches, sockets, sanitaryware, radiators, skirting boards, doors, stair treads
  • Plastering divides first and second fix — plaster must fully dry (3–5 weeks) before second fix and decoration begin
  • Understanding the sequence helps homeowners track progress and understand payment milestones tied to construction stages
  • RCB's standard position: second-fix materials are client-supplied (the client sources their own kitchen, bathroom, flooring, and finishes)

First fix — before plastering

First fix is all the work carried out before plastering — the work that is hidden within the structure of the building (behind walls, within floor and ceiling voids, in roof spaces) and cannot be accessed once plasterboard is fixed and plaster is applied.

  • **First fix electrics**:
  • Installing the consumer unit (fuse board) position and main cable run
  • Running cables throughout the building to every socket, light, and appliance position
  • Positioning back boxes (the metal or plastic boxes that the switches and sockets will fix to)
  • Running cables for mains-wired smoke alarms at each level
  • Cables for heating controls, extractor fans, and any specialised circuits (electric shower, cooker, EV charger)
  • First fix does NOT include fitting switches, sockets, light fittings, or connecting the consumer unit — those are second fix
  • **First fix plumbing**:
  • Installing the new pipework runs for hot and cold water throughout the building
  • Installing soil and waste pipes for new bathrooms, WCs, and kitchen sinks
  • Positioning the boiler location pipework and connections (boiler is not fitted at first fix)
  • Installing central heating flow and return pipework to radiator positions throughout the building
  • Radiator valves and tails at each radiator position
  • First fix does NOT include fitting sanitaryware (bath, basin, WC), radiators, or the boiler
  • **First fix carpentry**:
  • Stud wall framing (where stud walls are part of the new layout)
  • Window and door lining installation
  • Floor joist installation (in new structures)
  • Stair string and newel post installation (the structural elements of the staircase)
  • Plasterboard fixing (boarding the stud walls and ceilings)
  • First fix does NOT include skirting boards, architraves, doors, fitted furniture, or stair treads — those are second fix

The plastering phase

Between first fix and second fix, the plastering phase takes place. This is when:

  • Plasterboard is skimmed with a thin coat of finish plaster (traditional wet plaster)
  • OR dry lining compound is applied over taped plasterboard joints (drylining/tape and joint system)
  • Render is applied to external walls
  • Floor screeds are poured (liquid screed or traditional sand/cement screed) over underfloor heating pipes or to level uneven floors
  • **Why plastering is the dividing line**:
  • The plastering phase is the dividing line between first and second fix because:
  • Once plaster is applied, the cables and pipes are fully concealed — any changes require cutting into the finish
  • The plaster must fully dry (minimum 3–4 weeks for traditional plaster, faster for drylining compound) before second fix decoration
  • The plaster provides the smooth surface onto which skirting boards, architraves, and other second-fix elements are fitted

**Plastering programme**: For a typical extension (4m x 5m footprint, with first-floor bathroom above), plastering typically takes 1–2 weeks for a small team of plasterers. Drying time before decoration adds a further 2–4 weeks.

Second fix — after plastering

Second fix is all the work carried out after plastering — the visible, finished elements that are installed to complete the space.

  • **Second fix electrics**:
  • Fitting all switches and socket faceplates
  • Fitting light fittings and pendants
  • Connecting and commissioning the consumer unit
  • Connecting and testing all circuits
  • Part P certification and Building Control notification
  • Installing and testing the mains-wired smoke alarms
  • **Second fix plumbing**:
  • Fitting the boiler and commissioning the heating system
  • Installing radiators and connecting to the flow and return tails
  • Fitting the bath, basin, WC, and shower in each bathroom
  • Fitting taps, valves, and waste connections
  • Connecting and testing all water supply and waste connections
  • Commissioning the boiler and full heating system pressure test
  • **Second fix carpentry**:
  • Installing skirting boards and architraves throughout
  • Hanging internal doors on their linings
  • Installing door furniture (handles, hinges, locks)
  • Stair treads, risers, and balustrading
  • Fitted wardrobe installation
  • Any other joinery elements (window boards, bespoke shelving)

**Decoration (separate from second fix carpentry)**: Decoration (painting and decorating) typically follows second fix carpentry. The sequence is: plaster dry → first coat of paint → skirting and architrave installation → final coat of paint (cutting in around the new joinery).

Frequently Asked Questions

When does second fix start in a building project?
Second fix starts after plastering is complete and the plaster is sufficiently dry — typically 3–5 weeks after plastering is finished (depending on whether traditional wet plaster or drylining compound is used). The plasterer must be satisfied the surface is ready for decoration before second fix commences.
What does 'first fix included' mean in a contractor's quote?
If a contractor's quote states 'first fix included', it means all the concealed infrastructure work (cable runs, pipework, stud framing) is included in the price. It does NOT include fitting switches, sockets, sanitaryware, radiators, or door hardware — those are second fix and may be priced separately or as a separate stage.
Why are materials often split between first fix and second fix?
Many contractors and clients distinguish between first-fix materials (cables, pipes, plasterboard — functional and hidden) and second-fix materials (switches, sockets, tiles, flooring, sanitaryware — visible and specified by the client). RCB Design & Build's standard position is that all second-fix materials are client-supplied, so the client chooses and sources their own kitchen, bathroom, flooring, and switches — giving full control over specification without markup.

Important Note

This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.