Kitchen Renovation — What's Involved and How to Plan It Right

A kitchen renovation is one of the most impactful projects you can carry out in your home — both in terms of daily quality of life and property value. It is also one of the most disruptive: your kitchen is out of action for weeks, every trade is involved, and the number of decisions is enormous. This guide explains what a kitchen renovation involves, what it costs, the correct sequence of works, and how to plan it to avoid the most common and expensive mistakes.

Key Takeaways

  • Four levels: replacement only (£8k–£18k), full renovation (£15k–£28k), with structural opening (£25k–£45k), combined with extension (£50k–£150k+)
  • Sequence is critical — first-fix plumbing and electrics must be in the right positions before plastering; units before worktops; worktops before second-fix
  • Order units early — 4–12 week lead times are common; worktops are templated after units and take 5–10 additional days
  • Layout decisions must be fixed before any trades start — changing the plan after first-fix is very expensive
  • Kitchen units are client-supplied at RCB — you control specification and cost; we manage the installation

Levels of kitchen renovation

Not all kitchen renovations are equal. The scope can range from a simple unit replacement to a full structural reconfiguration:

**Level 1 — Replacement kitchen (units and worktops only)**: The existing layout stays. Old units are removed and new units installed in the same positions. Worktops replaced. Appliances swapped. Tiles behind the old units may need replacing. Typical cost: £8,000–£18,000 (units client-supplied or included; labour + plumbing + electrics + tiling) Disruption: 2–3 weeks

**Level 2 — Full renovation (layout change, new electrics and plumbing)**: Layout changed, new units and worktops, electrics and lighting fully updated, plumbing for sink and dishwasher relocated, extraction upgraded, new flooring. Typical cost: £15,000–£28,000 (excluding units) Disruption: 4–6 weeks

**Level 3 — Full renovation with structural opening**: All of Level 2, plus: a structural opening into an adjacent room (load-bearing wall removal and RSJ), or a connection through the rear wall into an extension. Structural engineer required. Building Regulations required. Typical cost: £25,000–£45,000 (excluding units and extension, if any) Disruption: 6–10 weeks

**Level 4 — Kitchen extension (combined with rear or side extension)**: See: kitchen extension guide. Total cost £50,000–£150,000+ including the extension structure.

The correct sequence of a kitchen renovation

Getting the sequence of trades right is the most important factor in a smooth kitchen renovation. The correct sequence:

1. **Strip-out and demolition**: removal of all old units, worktops, appliances, and old flooring; any wall openings cut; damp treatment if required 2. **Structural works**: RSJ installation for any structural opening; temporary propping; making good after steel installation 3. **First-fix plumbing**: new soil and water pipework in the correct positions for the new layout; hidden behind walls and floors before plastering 4. **First-fix electrics**: new circuits for cooker (typically 6mm² dedicated circuit), fridge-freezer (13A), dishwasher (13A), washing machine (13A), extraction (5A or dedicated), floor heating (if UFH); new lighting circuit; all wiring hidden before plastering 5. **Plastering**: plaster skim to all walls, patch plaster where old units were, new plaster where structural works were done; allow 7–14 days to dry 6. **Floor screed or substrate**: if new floor is to be laid (particularly if UFH is involved), floor screed or boards installed before units; allow 7–14 days to cure for screed 7. **Unit installation**: all base and wall units installed by the kitchen fitter; appliances may be placed in position 8. **Worktops**: templated and installed by the worktop fabricator (allow 5–10 days from templating to delivery for stone worktops) 9. **Second-fix plumbing**: sink, tap, dishwasher, and washing machine connected 10. **Second-fix electrics**: sockets, switches, under-cabinet lighting, and appliance connections; NICEIC Part P certificate issued 11. **Tiling**: splashback and any wall tiling; grout 12. **Flooring**: final flooring laid (if not before units) 13. **Final appliance installation**: integrated appliances (oven, hob, microwave, fridge-freezer) fitted 14. **Decoration**: painting and finishing; kitchen doors/handles adjusted and aligned 15. **Snagging**: walkthrough of all items; adjustment of hinges and drawers; first-use check of appliances and plumbing

What drives the cost of a kitchen renovation?

The cost of a kitchen renovation is driven by:

**Labour (60–70% of total cost for a trade-only scope)**: Plumber, electrician, structural carpenter (if opening involved), plasterer, tiler, kitchen fitter. In London, skilled trade day rates are £250–£400 per day. A complex kitchen renovation involves 6–8 different trades over 4–8 weeks.

  • **Kitchen units and worktops (separate cost — client-supplied or included)**:
  • IKEA-level: £1,500–£4,000 for units; £500–£1,500 for laminate worktops
  • Mid-range (Howdens, Wren, Symphony): £4,000–£12,000 for units; £1,500–£4,000 for quartz or engineered stone
  • High-end (bespoke cabinetry, real stone): £15,000–£60,000+

**Layout complexity**: An island layout requires more careful planning of service positions (socket and data points in the island, plumbing if a sink is included). Islands also require worktops in two or three pieces with joints — more expensive than a simple run.

**Structural works**: If the kitchen renovation involves removing a load-bearing wall to connect to an adjacent room, add £3,500–£6,500 for the structural work (structural engineer, propping, steel installation, making good).

**Extraction**: A standard extraction through an external wall is straightforward. Extraction through a central island (requiring ductwork through the ceiling and out through an external wall or roof) is significantly more complex and expensive.

Planning decisions that matter before work starts

The most expensive kitchen renovation mistakes happen at the planning stage, not the build stage:

**Decide the layout before any trades are booked**: the position of the sink, hob, fridge, and dishwasher determines the plumbing and electrical first-fix positions. Changing the layout after the first fix is under the floor and walls is extremely expensive.

**Order units and worktops early**: kitchen delivery lead times are 4–12 weeks depending on the manufacturer. Worktop stone is templated after units are installed — allow an additional 5–10 days. If delivery is late, the kitchen fitter waits and every subsequent trade is delayed.

**Confirm appliance cutout sizes before ordering units**: different appliance brands have different cutout requirements. The kitchen fitter must know the exact appliance models before building the cabinets — or the cutouts will be wrong.

**Decide on the flooring position in the sequence**: if hardwood or engineered boards are used, they should typically be installed before units to run continuously under the kick boards (it looks better and protects more of the floor). If large-format tiles are used, they can go before or after units. If the floor is screed with UFH, it goes before units.

**Confirm the extraction route**: the most overlooked decision. An island hob with overhead extraction requires ductwork through the ceiling — this must be coordinated with the plasterer, electrician, and any ceiling works.

Frequently Asked Questions

How much does a kitchen renovation cost in London?
A replacement kitchen (same layout, new units and worktops) costs £8,000–£18,000 in trade costs. A full renovation with layout change, new electrics and plumbing costs £15,000–£28,000. A renovation with a structural opening into an adjacent room costs £25,000–£45,000. All figures are for labour and materials — kitchen units and worktops are additional (£3,000–£60,000+ depending on specification).
How long does a kitchen renovation take?
A replacement kitchen takes 2–3 weeks. A full renovation with layout change takes 4–6 weeks. A renovation with structural works takes 6–10 weeks. Add 4–12 weeks for kitchen unit delivery and planning before works start.
Should I supply my own kitchen units or have the contractor supply them?
RCB Design & Build works with client-supplied kitchens — you choose and purchase the units direct from IKEA, Howdens, or a specialist kitchen company; we handle the fitting, plumbing, electrics, and all associated trades. This gives you full control over specification and cost. We can advise on planning and ordering, and we manage the installation sequence so delivery timing fits the programme.

Important Note

This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.