⭐ 9.96/10 Checkatrade · 114+ Reviews
📞 07359 872594
Structural Works3 min read

Concrete Slab Floors for London Victorian Terrace Extensions and Refurbishments

The concrete ground-bearing slab is the standard floor construction for single-storey rear extensions on London Victorian terraces and for the replacement of original suspended timber ground floors in full house refurbishments. It provides a stable, thermally efficient, damp-resistant floor base that supports a wide range of finishes — from polished concrete and large-format porcelain tiles to engineered timber and luxury vinyl tile — and integrates naturally with wet underfloor heating systems. This guide covers the correct specification for a concrete ground-bearing slab in a London residential extension or ground floor refurbishment, including preparation, DPM, insulation, structural mesh, concrete grade, and the screed finishing layer.

Key Takeaways

  • Ground preparation and excavation for London extension slabs: EXCAVATION DEPTH (working backwards from required FFL): deduct floor finish (10-20mm tile, 14-22mm engineered timber, 2-4mm LVT) + screed (65-75mm liquid screed or sand-cement) + PIR insulation (100mm Kingspan Kooltherm K3) + DPM (negligible) + concrete slab (100mm minimum) + compacted hardcore (150mm minimum — 200-250mm loose before compaction) — total build-up depth approximately 415-475mm below FFL (excl. floor finish); TOTAL TYPICAL EXCAVATION DEPTH FOR LONDON EXTENSION: approximately 425-500mm below intended FFL; LONDON-SPECIFIC RISKS: (1) LONDON CLAY — high volume change potential (heave/shrinkage with moisture — especially near trees) — trees within ~1.5x mature height of slab require structural engineer advice on anti-heave precautions (anti-heave boards, compressible layer, or void form below slab); (2) MADE GROUND AND HISTORIC FILL — very common in Victorian terrace back gardens (rubble, ash, cinders) — made ground is not suitable direct bearing stratum without consolidation — confirm founding conditions with Building Control; (3) CONTAMINATION — industrial history areas of London — report unusual materials or odours during excavation to Building Control
  • DPM, insulation, and structural mesh build-up: BLINDING LAYER (50mm sharp sand, compacted over hardcore): provides smooth level surface for DPM — prevents hardcore aggregate puncturing DPM; DPM (damp-proof membrane): Visqueen Super Flexible Plus 1200 gauge (300 micron) — Building Regs minimum 1000 gauge (250 micron) — standard specification 1200 gauge; minimum 150mm overlap at all joints, taped with Visqueen polythene tape or fully welded; lapped up internal face of all surrounding walls to DPC height and connected to wall DPC (continuous horizontal moisture barrier); where radon protection required (check UKHSA radon map for specific address) — all joints must be fully taped and sealed (DPM also acts as radon barrier); PIR INSULATION: Kingspan Kooltherm K3 Floorboard (~150 kPa compressive strength) or Celotex GA4000 (~100 kPa) — 100mm depth achieves approximately 0.18-0.22 W/m²K depending on floor geometry; Part L 2021 backstop 0.15 W/m²K maximum — 120-150mm PIR for compliance; STRUCTURAL MESH: A193 (7mm bar at 200mm centres each way, 193mm²/m) minimum — A252 (8mm bar at 200mm centres) for heavier loading — supported on plastic bar chair spacers at mid-slab depth (minimum 25mm cover from base — NOT resting on insulation board)
  • Concrete grade and casting: CONCRETE GRADE (BS 8500-1 / BS EN 206 designated): C25/P (GEN 3) — minimum Building Control standard for ground-bearing residential slab in most London boroughs; C30/P (GEN 4) — recommended current specification for London residential slabs — better durability, lower W/C ratio — preferred where sulphate exposure class DS-1 or DS-2 applies (London clay groundwater typically ACEC class AC-1 or AC-2 — confirm with BCO or structural engineer); WORKABILITY: Slump Class S3 (100-150mm) for ground-bearing slab — allows compaction and levelling around mesh reinforcement; ORDER ready-mix from Hanson ReadyMix, CEMEX, Aggregate Industries, or Breedon — DO NOT site-mix structural slab concrete; CASTING: place in sections — do not dump full load in one place (displaces mesh and insulation); compact with 38-50mm poker vibrator (overlapping insertions max 600mm apart — eliminates voids around mesh); screed level with straight edge, laser level, or datum pegs; float surface with bull float — do not over-trowel while wet; CURING: cover with polythene for minimum 3 days in cold weather — minimum 7 days before loading or screed application — full strength at 28 days
  • Screed types — liquid screed vs sand-cement screed: LIQUID SCREED (calcium sulphate anhydrite — Hanson Cemfloor, Lafarge Thermia Floor — pump-applied — PREFERRED FOR UFH SYSTEMS AND LARGE AREAS): self-levelling to flat surface (SR2 as poured, SR1 with grinding); 200-300m²/day installation rate; encapsulates UFH pipes without voids (critical for thermal contact); minimum 50mm above top of UFH pipe (total typically 65-70mm with 16mm OD pipe); walkable 24-48h; full cure 28-42 days; DRYING: ~1mm/day first 40mm then ~0.5mm/day — 70mm screed ~50-80 days to 75% RH (reduce with forced air from day 7, and UFH drying cycle: day 7 set to 25°C, +5°C/day to max 55°C, hold 7 days, -5°C/day); CRITICAL: surface laitance MUST be abraded/sanded before adhesive floor finishes; SAND AND CEMENT SCREED (1:3.5 OPC:sharp sand, semi-dry — TRADITIONAL): 30-50m²/day installation rate; minimum 65mm depth (floating/unbonded); over UFH minimum 65mm above pipe top; more prone to shrinkage cracking (max bay 40m² or 8m linear — Sika joint sealant at movement joints); curing 28 days minimum; does NOT require sanding before floor finish
  • Costs London 2025 (supply + fit, groundworks/flooring contractor, labour + materials): excavation to formation level: ~£15-35/m² (mechanical access); ~£30-60/m² (restricted hand excavation — inner-London terrace premium); Type 1 hardcore supply and compact (150mm min): ~£12-22/m²; DPM 1200 gauge supply and lay: ~£3-6/m²; 100mm PIR insulation (Kooltherm K3 or Celotex GA4000) supply and lay: ~£22-38/m²; 100mm C25/P or C30/P concrete slab (ready-mix, pump, place, compact, float): ~£20-38/m² (concrete pump add ~£400-700 per pour for restricted-access); liquid screed over UFH (Cemfloor/Thermia, min 65mm above pipe, pump-applied): ~£18-30/m²; TOTAL PACKAGE (all above combined, excl. UFH pipework and floor finish): ~£90-190/m² (mechanical excavation access); ~£120-240/m² (restricted hand excavation); EXAMPLE: 20m² extension slab (mechanical access): ~£1,800-3,800 total; EXCLUDES: floor finish, UFH pipework and manifold, plumbing connections, extension structure (walls, roof, foundations)

Ground Preparation and Excavation for London Extension Slabs

THE GROUND PREPARATION FOR A CONCRETE SLAB FLOOR IN A LONDON VICTORIAN TERRACE EXTENSION OR GROUND FLOOR REFURBISHMENT IS THE FOUNDATION ON WHICH THE ENTIRE FLOOR BUILD-UP DEPENDS — INADEQUATE PREPARATION LEADS TO FUTURE SLAB HEAVE, SUBSIDENCE, DAMP, OR DIFFERENTIAL SETTLEMENT BETWEEN THE SLAB AND THE SURROUNDING STRUCTURE.

EXCAVATION DEPTH: THE EXCAVATION DEPTH FOR A NEW GROUND-BEARING SLAB IN A REAR EXTENSION ON A LONDON VICTORIAN TERRACE IS DETERMINED BY THE REQUIRED SLAB FORMATION LEVEL — WORKING BACKWARDS FROM THE REQUIRED FINISHED FLOOR LEVEL (FFL) WHICH IS TYPICALLY MATCHED TO THE INTERNAL FLOOR LEVEL OF THE EXISTING PROPERTY: FROM THE REQUIRED FFL DEDUCT: THICKNESS OF FLOOR FINISH (TYPICALLY 10-20MM FOR CERAMIC/PORCELAIN TILE, 14-22MM FOR ENGINEERED TIMBER, 2-4MM FOR LVT); THICKNESS OF SCREED (TYPICALLY 65-75MM LIQUID SCREED SUCH AS HANSON CEMFLOOR OR LAFARGE THERMIA IF UFH, OR 65-75MM SAND AND CEMENT SCREED IF NO UFH); THICKNESS OF PIR INSULATION (TYPICALLY 100MM KINGSPAN KOOLTHERM K3 FLOORBOARD OR CELOTEX GA4000 PIR — SEE BELOW); THICKNESS OF DPM (1200 GAUGE VISQUEEN SUPER FLEXIBLE PLUS DPM — APPROXIMATELY 0.3MM — NEGLIGIBLE BUT INCLUDE IN FORMATION LEVEL CALCULATION); THICKNESS OF CONCRETE SLAB (TYPICALLY 100MM MINIMUM FOR A GROUND-BEARING SLAB IN A RESIDENTIAL EXTENSION — BUILDING CONTROL WILL TYPICALLY REQUIRE MINIMUM 100MM C25/P CONCRETE — SEE BELOW); THICKNESS OF COMPACTED HARDCORE BASE (TARMAC TOPBASE TYPE 1 LIMESTONE AGGREGATE OR EQUIVALENT CLEAN ANGULAR HARDCORE — MINIMUM 150MM COMPACTED DEPTH — 200-250MM LOOSE DEPTH BEFORE COMPACTION USING WACKER PLATE); LONDON-SPECIFIC CONSIDERATIONS: (1) LONDON CLAY — LONDON CLAY HAS HIGH VOLUME-CHANGE POTENTIAL (HEAVE AND SHRINKAGE WITH MOISTURE CONTENT CHANGES — PARTICULARLY RELEVANT WHERE TREES ARE PRESENT) — WHERE TREES ARE WITHIN APPROXIMATELY 1.5X MATURE TREE HEIGHT OF THE PROPOSED SLAB, A STRUCTURAL ENGINEER SHOULD BE CONSULTED ON WHETHER PRECAUTIONS ARE NEEDED (ANTI-HEAVE BOARDS, COMPRESSIBLE LAYER, OR VOID-FORM SYSTEM) TO PROTECT THE SLAB AGAINST CLAY HEAVE; (2) MADE GROUND AND FILL — LONDON HAS EXTENSIVE AREAS OF MADE GROUND AND HISTORIC FILL (RUBBLE, ASH, CINDERS) PARTICULARLY IN THE BACK GARDEN AREAS OF VICTORIAN TERRACES — MADE GROUND IS NOT A SUITABLE DIRECT BEARING STRATUM FOR A GROUND-BEARING SLAB WITHOUT CONSOLIDATION — BUILDING CONTROL WILL TYPICALLY REQUIRE CONFIRMATION OF FOUNDING CONDITIONS; (3) CONTAMINATION — IN SOME PARTS OF LONDON (PARTICULARLY AREAS WITH INDUSTRIAL HISTORY) GROUND CONTAMINATION MAY AFFECT THE FILL MATERIAL — REPORT TO BUILDING CONTROL IF UNUSUAL MATERIALS OR ODOURS ARE ENCOUNTERED DURING EXCAVATION.

DPM, Insulation, and Structural Mesh Specification

THE SLAB BUILD-UP ABOVE THE COMPACTED HARDCORE (FROM BOTTOM UP) IS: BLINDING LAYER + DPM + PIR INSULATION + STRUCTURAL MESH + CONCRETE.

BLINDING LAYER (SHARP SAND BLINDING — TYPICALLY 50MM COMPACTED DEPTH): A THIN LAYER OF SHARP SAND IS LAID AND COMPACTED OVER THE COMPACTED HARDCORE TO PROVIDE A SMOOTH, LEVEL SURFACE FOR THE DPM — PREVENTS THE HARDCORE AGGREGATE FROM PUNCTURING THE DPM; DPM (DAMP-PROOF MEMBRANE — PROTECTS THE SLAB AND FLOOR CONSTRUCTION FROM GROUND MOISTURE AND SOIL GAS): SPECIFICATION: VISQUEEN SUPER FLEXIBLE PLUS 1200 GAUGE POLYTHENE SHEET DPM (1200 GAUGE = 300 MICRON THICKNESS — THE BUILDING REGULATIONS MINIMUM FOR A GROUND FLOOR DPM IS 1000 GAUGE — 1200 GAUGE IS THE STANDARD SPECIFICATION FOR NEW-BUILD AND EXTENSION SLABS IN LONDON); LAP AND TAPE: MINIMUM 150MM OVERLAP AT ALL JOINTS — TAPED WITH VISQUEEN POLYTHENE TAPE OR FULLY WELDED — CRITICAL THAT LAPS ARE PROPERLY SEALED TO PREVENT MOISTURE OR RADON INGRESS AT JOINTS; DPM MUST BE LAPPED UP THE INTERNAL FACE OF ALL SURROUNDING WALLS TO AT LEAST DPC HEIGHT — CONNECTED TO THE WALL DPC — TO COMPLETE THE CONTINUOUS HORIZONTAL MOISTURE BARRIER BENEATH THE SLAB; WHERE RADON PROTECTION IS REQUIRED (PART C AND THE RADON MAP — LONDON IS GENERALLY IN THE LOWER-RISK ZONES FOR RADON BUT SOME AREAS REQUIRE RADON PROTECTION — THE BUILDING CONTROL OFFICER WILL ADVISE): THE DPM ALSO ACTS AS A RADON BARRIER — ALL JOINTS MUST BE FULLY SEALED; PIR INSULATION (RIGID CLOSED-CELL PIR (POLYISOCYANURATE) INSULATION BOARD — INSTALLED ABOVE THE DPM AND BELOW THE CONCRETE SLAB OR (ALTERNATIVELY IN SOME SPECIFICATIONS) ABOVE THE SLAB AND BELOW THE SCREED): SPECIFICATION: KINGSPAN KOOLTHERM K3 FLOORBOARD (RATED COMPRESSIVE STRENGTH APPROXIMATELY 150 KPA — SUITABLE FOR RESIDENTIAL FLOOR LOADING) OR CELOTEX GA4000 (100 KPA — ALSO SUITABLE FOR RESIDENTIAL) — AT 100MM DEPTH: U-VALUE OF COMBINED SLAB/INSULATION ASSEMBLY APPROXIMATELY 0.18-0.22 W/M²K DEPENDING ON FLOOR PLAN GEOMETRY (EDGE EFFECTS INCREASE U-VALUE — LARGER FLOOR AREA = BETTER EFFECTIVE U-VALUE); PART L 2021 TARGET: 0.15 W/M²K FOR NEW GROUND FLOORS (MAXIMUM — LOWER IS BETTER) — 100MM KINGSPAN KOOLTHERM K3 TYPICALLY ACHIEVES 0.15-0.20 W/M²K DEPENDING ON AREA AND PLAN GEOMETRY — FOR BETTER PERFORMANCE, INCREASE INSULATION DEPTH TO 120MM OR 150MM; STRUCTURAL MESH (REINFORCING MESH FABRIC — BINDS THE CONCRETE SLAB AND PROVIDES CRACK CONTROL): SPECIFICATION: A193 MESH (AREA OF STEEL 193 MM²/M — 7MM BAR AT 200MM CENTRES EACH WAY) — THE MINIMUM STANDARD MESH FOR A GROUND-BEARING RESIDENTIAL SLAB; A252 MESH (8MM BAR AT 200MM CENTRES — SLIGHTLY HEAVIER — USED WHERE HEAVIER LOCALISED LOADS ARE EXPECTED OR WHERE THE ENGINEER SPECIFIES); SUPPORT: MESH MUST BE SUPPORTED AT MID-DEPTH OF THE CONCRETE SLAB USING PLASTIC SPACER CHAIRS (BAR CHAIRS — MINIMUM 25MM COVER TO ALL STEEL FROM THE BASE) — NOT RESTING ON THE INSULATION BOARD.

Concrete Grade and Slab Casting

THE CONCRETE GRADE AND CASTING METHOD FOR A RESIDENTIAL EXTENSION GROUND-BEARING SLAB IN LONDON ARE CRITICAL TO THE LONG-TERM PERFORMANCE OF THE FLOOR — WEAK OR POORLY CAST CONCRETE LEADS TO SURFACE DUSTING, CRACKING, INSUFFICIENT STRENGTH, AND POTENTIAL BUILDING CONTROL NON-COMPLIANCE.

CONCRETE GRADE (BS 8500-1 / BS EN 206 — DESIGNATED CONCRETE — DESIGNED MIX): C25/P (GEN 3 — THE MINIMUM BUILDING CONTROL STANDARD FOR A GROUND-BEARING RESIDENTIAL SLAB IN MANY LONDON BOROUGHS — THE DESIGNATION C25/P: C25 = MINIMUM 28-DAY CHARACTERISTIC COMPRESSIVE CUBE STRENGTH 25 N/MM², P = PRESCRIBED MIX WITH DEFINED WORKABILITY — SLUMP OR FLOW CLASS) — SPECIFY AS GEN 3 FROM THE CONCRETE SUPPLIER (HANSON READYMIX, CEMEX, AGGREGATE INDUSTRIES READYMIX, BREEDON CONCRETE — ALL HAVE READY-MIX PLANTS ACROSS LONDON); RC30 OR C30/P (GEN 4 — THE MORE COMMON CURRENT SPECIFICATION USED BY GOOD CONTRACTORS FOR LONDON RESIDENTIAL SLABS — BETTER DURABILITY, LOWER W/C RATIO, SLIGHTLY HIGHER STRENGTH — RECOMMENDED WHERE SULPHATE EXPOSURE CLASS DS-1 OR DS-2 IS APPLICABLE — LONDON CLAY GROUNDWATER IS TYPICALLY IN ACEC CLASS AC-1 OR AC-2 — THE BUILDING CONTROL OFFICER OR STRUCTURAL ENGINEER WILL ADVISE ON SULPHATE CLASS); WORKABILITY: SLUMP CLASS S3 (100-150MM SLUMP) IS APPROPRIATE FOR A GROUND-BEARING SLAB POURED AROUND MESH REINFORCEMENT — TOO STIFF (S1 OR S2) MAKES COMPACTION AND LEVELLING DIFFICULT; VOLUME: CALCULATE VOLUME (LENGTH X WIDTH X 0.1M) + 5-10% WASTE ALLOWANCE — ORDER FROM READY-MIX SUPPLIER — DO NOT MIX SITE-MIXED CONCRETE FOR A STRUCTURAL SLAB (INCONSISTENT QUALITY); CASTING PROCEDURE: (1) PLACE READY-MIX CONCRETE IN SECTIONS — DO NOT OVERFILL OR DUMP FULL LOAD IN ONE PLACE (MOVES MESH AND INSULATION); (2) COMPACT CONCRETE WITH A POKER VIBRATOR (TYPICALLY 38MM OR 50MM DIAMETER — USED IN OVERLAPPING INSERTIONS NOT MORE THAN 600MM APART) — CRITICAL FOR ELIMINATING VOIDS AND ACHIEVING FULL COMPACTION AROUND MESH; (3) SCREED LEVEL WITH STRAIGHT EDGE OR SCREED RAIL (DATUM PEGS OR LASER LEVEL) TO ACHIEVE FLAT LEVEL FORMATION FOR INSULATION AND SCREED; (4) FLOAT SURFACE FLAT WITH A BULL FLOAT OR HAND FLOAT — DO NOT OVER-TROWEL WHILE WET (SURFACE LAITANCE RISK); (5) PROTECT FROM FROST AND DRYING (COVER WITH POLYTHENE SHEET FOR MINIMUM 3 DAYS IN COLD WEATHER — MINIMUM CURING PERIOD 7 DAYS BEFORE LOADING OR SCREED APPLICATION).

Liquid Screed and Sand-Cement Screed Over Concrete Slab

THE SCREED LAYER OVER THE CONCRETE SLAB (AND WHERE APPLICABLE OVER THE INSULATION ABOVE THE SLAB) PROVIDES THE LEVEL, SMOOTH, HIGH-TOLERANCE SURFACE REQUIRED FOR THE FLOOR FINISH — AND (WHERE UFH IS INSTALLED) ENCAPSULATES THE UFH PIPEWORK AND PROVIDES THERMAL MASS FOR HEAT EMISSION.

LIQUID SCREED (CALCIUM SULPHATE ANHYDRITE SCREED — ALSO CALLED FLOW SCREED OR POURED SCREED — THE DOMINANT CHOICE FOR UFH FLOOR SYSTEMS AND LARGE-AREA INSTALLATIONS IN LONDON): MAIN PRODUCTS: HANSON CEMFLOOR (HANSON UK — A READY-MIX CALCIUM SULPHATE SCREED DELIVERED IN A MIXER TRUCK OR PUMP TRUCK — THE MOST WIDELY USED LIQUID SCREED IN THE UK RESIDENTIAL MARKET); LAFARGE THERMIA FLOOR (SAINT-GOBAIN — CALCIUM SULPHATE LIQUID SCREED WITH ENHANCED THERMAL CONDUCTIVITY — 1.6-2.0 W/MK — PARTICULARLY SUITED TO UFH APPLICATIONS); ADVANTAGES OF LIQUID SCREED: FASTER INSTALLATION (A TEAM OF TWO CAN INSTALL 200-300M² PER DAY VS 30-50M²/DAY FOR HAND-APPLIED SAND AND CEMENT SCREED — SIGNIFICANT SAVING IN LABOUR TIME ON LARGE FLOOR AREAS); SELF-LEVELLING (FLOWS AND LEVELS ITSELF TO A FLAT SURFACE — FLATNESS TOLERANCE SR2 IS ACHIEVABLE — SR1 WITH SURFACE GRINDING); ENCAPSULATES UFH PIPES WITHOUT VOIDS (FLOWS AROUND ALL PIPEWORK); DEPTH: MINIMUM 50MM ABOVE TOP OF UFH PIPE FOR LIQUID SCREED OVER UFH (TYPICALLY UFH PIPE IS 16MM OD — MINIMUM TOTAL SCREED DEPTH 65-70MM); CURING TIME: LIQUID SCREED IS TYPICALLY WALKABLE AT 24-48 HOURS — FULL CURE FOR HARD FLOOR FINISHES 28-42 DAYS — CALCIUM SULPHATE SCREED IS SENSITIVE TO MOISTURE DURING CURING (MUST BE COVERED AND PROTECTED FROM RAIN); SURFACE TREATMENT: CALCIUM SULPHATE SCREED MUST BE SANDED (ABRADED) AFTER INITIAL CURE TO REMOVE THE LAITANCE LAYER (A WEAK CALCIUM SULPHATE SURFACE SKIN) BEFORE APPLICATION OF ADHESIVE FLOOR TILES OR TIMBER — IF NOT SANDED, ADHESION OF FLOOR FINISH MAY FAIL; SAND AND CEMENT SCREED (TRADITIONAL — SEMI-DRY CONSISTENCY — TROWELLED AND TAMPED BY HAND — LOWER MATERIAL COST BUT HIGHER LABOUR COST PER M² FOR LARGE AREAS): MIX: 1 PART OPC : 3.5 PARTS SHARP SAND (SEMI-DRY MIX — CONSISTENCY OF DAMP SAND — SHOULD HOLD ITS SHAPE WHEN SQUEEZED BUT NOT SQUEEZE OUT WATER) — MINIMUM DEPTH 65MM (UNBONDED OR FLOATING — NOT BONDED TO CONCRETE SLAB); OVER UFH: MINIMUM 65MM ABOVE TOP OF PIPE; CURING: 28 DAYS MINIMUM FOR HARD FLOOR FINISH APPLICATION; SHRINKAGE CRACKING: SAND AND CEMENT SCREED IS MORE PRONE TO SHRINKAGE CRACKING THAN LIQUID SCREED — BAY SIZES SHOULD BE CONTROLLED (MAX 40M² OR MAX DIMENSION 8M UNLESS MOVEMENT JOINTS ARE FORMED — SIKA JOINT SEALANT AT ALL MOVEMENT JOINTS).

Concrete Slab Floor Costs for London Extensions

CONCRETE GROUND-BEARING SLAB AND SCREED COSTS FOR LONDON VICTORIAN TERRACE EXTENSIONS AND GROUND FLOOR REFURBISHMENTS (LONDON 2025 — APPROXIMATE RANGE — SUPPLY AND FIT — GROUNDWORKS/FLOORING CONTRACTOR — LABOUR AND MATERIALS).

GROUND PREPARATION AND EXCAVATION (DIG OUT TO FORMATION LEVEL — REMOVE EXISTING MATERIAL — HAND EXCAVATION WHERE ACCESS IS RESTRICTED — PER M² OF FLOOR AREA): APPROXIMATELY £15-35/M² (MECHANICALLY ASSISTED — MINI EXCAVATOR ACCESS THROUGH PROPERTY OR SIDE GATE — LONDON RATES); APPROXIMATELY £30-60/M² (FULL HAND EXCAVATION WHERE NO MECHANICAL ACCESS — TYPICAL FOR INNER-LONDON TERRACE WITH NO SIDE GATE ACCESS — ALL MATERIAL CARRIED THROUGH PROPERTY — LONDON PREMIUM). HARDCORE COMPACTION (TYPE 1 COMPACTED — 150MM MINIMUM DEPTH — SUPPLY AND COMPACT — WACKER PLATE COMPACTION — PER M²): APPROXIMATELY £12-22/M² (SUPPLY AND COMPACT). DPM (1200 GAUGE VISQUEEN SUPER FLEXIBLE PLUS — SUPPLY AND LAY — PER M²): APPROXIMATELY £3-6/M² (SUPPLY AND LAY FLAT). PIR INSULATION (100MM KINGSPAN KOOLTHERM K3 OR CELOTEX GA4000 — SUPPLY AND LAY — PER M²): APPROXIMATELY £22-38/M² (100MM DEPTH — SUPPLY AND LAY). CONCRETE SLAB (100MM C25/P OR C30/P — READY-MIX — SUPPLY, PUMP/PLACE, COMPACT, AND FLOAT — PER M²): APPROXIMATELY £20-38/M² (SUPPLY AND PLACE — LONDON RATES — CONCRETE PUMP TYPICALLY REQUIRED FOR RESTRICTED-ACCESS REAR EXTENSIONS — PUMP HIRE ADDS APPROXIMATELY £400-700 PER POUR). LIQUID SCREED OVER UFH (HANSON CEMFLOOR OR LAFARGE THERMIA — MINIMUM 65MM ABOVE PIPE — SUPPLY AND POUR — PER M²): APPROXIMATELY £18-30/M² (SUPPLY AND POUR — PUMP-APPLIED). TOTAL CONCRETE SLAB FLOOR PACKAGE (GROUND PREPARATION + HARDCORE + DPM + 100MM PIR INSULATION + 100MM CONCRETE SLAB + LIQUID SCREED — EXCLUDING UFH PIPEWORK AND SCREED SURFACE PREPARATION — PER M²): APPROXIMATELY £90-190/M² (MECHANICALLY ASSISTED EXCAVATION — TYPICAL LONDON EXTENSION WITH SOME MECHANICAL ACCESS); APPROXIMATELY £120-240/M² (FULL HAND EXCAVATION — RESTRICTED ACCESS — INNER-LONDON TERRACE — LONDON PREMIUM FOR HAND WORK). NOTE: THESE RATES ARE FOR GROUNDWORK AND SLAB CONSTRUCTION ONLY — THEY EXCLUDE FLOOR FINISH, UFH MANIFOLD AND PIPEWORK, PLUMBING AND HEATING CONNECTIONS, AND ANY STRUCTURAL ELEMENT OF THE EXTENSION WALLS, ROOF, OR FOUNDATIONS.

Frequently Asked Questions

What thickness should a concrete slab floor be in a London extension?
The standard minimum thickness for a concrete ground-bearing slab in a residential rear extension on a London Victorian terrace is 100mm (C25/P or C30/P structural concrete with A193 reinforcing mesh at mid-depth) — this is the typical Building Control minimum for a ground-bearing residential slab: however, the actual thickness required for a specific project depends on: (1) the nature of the bearing ground (made ground, London clay, or hardcore-compacted fill — the structural engineer or Building Control officer will advise on whether a thicker slab or additional reinforcement is needed for weaker ground conditions); (2) the applied loading (domestic residential floor loading — 1.5 kN/m² imposed load per BS EN 1991-1-1 — is the standard design case for a residential extension slab — heavier point loads from structural columns or heavy plant require a thicker or differently reinforced slab); (3) the span (where the slab spans over a reduced-bearing area or void); COMPLETE SLAB BUILD-UP FOR A LONDON EXTENSION (total depth from sub-base to finished floor level, not including floor finish): approximately 100mm vibro-compacted hardcore blinding + 50mm sharp sand blinding + DPM (1200 gauge Visqueen, negligible thickness) + 100mm PIR insulation (Kingspan Kooltherm K3 or Celotex GA4000) + 100mm C25/P concrete slab with A193 mesh + 65-75mm liquid screed (Hanson Cemfloor or Lafarge Thermia) + floor finish — TOTAL SLAB BUILD-UP DEPTH: approximately 415-475mm below finished floor level (excluding floor finish thickness) — this must be accommodated in the excavation depth and in the step at the threshold where the extension connects to the existing building.
Do I need a DPM under the concrete slab?
Yes — a damp-proof membrane (DPM) under the concrete slab is a mandatory requirement of Building Regulations Part C (Site Preparation and Resistance to Contaminants and Moisture) for all new ground floors in residential buildings — the DPM prevents moisture from the ground rising through the slab into the floor construction and the living space: SPECIFICATION: the minimum DPM specification for a new extension slab in London is 1000 gauge (250 micron) polythene sheet — the standard specification used by quality contractors is 1200 gauge (300 micron) — Visqueen Super Flexible Plus 1200 gauge is the most widely used product; POSITION: the DPM can be placed either under the concrete slab (most common for new construction — DPM laid directly on blinding sand over compacted hardcore, with insulation above DPM and below concrete) or over the concrete slab and below the insulation (valid alternative — protects the insulation from ground moisture, but the concrete slab itself is unprotected from ground moisture and must therefore be a minimum C30 concrete with appropriate sulphate resistance for the site); FOR AN EXTENSION SLAB, THE PREFERRED POSITION IS UNDER THE SLAB AND INSULATION: DPM below insulation below concrete — the insulation is protected from ground moisture (critical — PIR insulation should not be exposed to prolonged moisture) and the slab is protected; CONNECTIONS: DPM must be lapped to the DPC in all surrounding walls (existing rear wall DPC and new extension wall DPC) to form a continuous horizontal moisture barrier beneath the floor — gaps or tears in the DPM are a common defect that leads to rising damp-related problems — particularly important in inner-London terrace extensions where the water table can be relatively high; WHERE RADON IS A CONSIDERATION (CHECK RADON MAP FOR THE SPECIFIC PROPERTY ADDRESS — PUBLIC HEALTH ENGLAND / UKHSA RADON MAPPING): the DPM must also act as a radon barrier — all joints must be taped and sealed rather than just overlapped.
What is the difference between a liquid screed and a sand-cement screed?
Liquid screed (calcium sulphate anhydrite screed, also called flow screed or poured screed) and sand-cement screed (semi-dry screed, traditional mortar screed) are the two main screed types used over concrete ground-bearing slabs in London extension and ground floor refurbishment projects: LIQUID SCREED (calcium sulphate anhydrite — main products: Hanson Cemfloor, Lafarge Thermia Floor, Knauf Flooring Solutions): delivered as a ready-mix liquid and pump-applied or gravity-fed through a hose to the floor — flows and self-levels to a flat surface — installation rate 200-300m² per day for a 2-person team (vs 30-50m²/day for sand-cement); encapsulates UFH pipework without voids (critical for good thermal contact between pipe and screed); minimum depth 50mm above top of UFH pipe (total typically 65-70mm with 16mm OD UFH pipe); achieves good flatness (SR2 as poured, SR1 with grinding); curing time walkable 24-48 hours but full cure 28-42 days; surface laitance must be abraded/sanded before adhesive floor finishes are applied; calcium sulphate screed is sensitive to moisture during curing and must not get wet; SAND AND CEMENT SCREED (traditional semi-dry screed — 1:3.5 OPC:sharp sand mix by volume): trowelled and tamped by hand — lower material cost but higher labour cost per m² for large areas; installation rate 30-50m²/day; minimum depth 65mm (floating/unbonded); over UFH minimum 65mm above pipe top; more prone to shrinkage cracking than liquid screed — bay sizes should be limited to maximum 40m² or 8m in any direction; curing time 28 days minimum; does not require sanding before floor finish; WHICH TO USE: for UFH — liquid screed is strongly preferred (better thermal contact, fewer voids, flat surface, faster installation for large areas); for areas without UFH — both are suitable — liquid screed preferred for large areas; sand-cement screed may be preferred for small areas or areas requiring specific depth control.
How long does a concrete slab floor take to dry before laying flooring?
Concrete slab and screed drying and curing times for a London extension floor: CONCRETE SLAB (C25/P or C30/P — 100mm thickness): structural curing (achieving minimum specified compressive strength): 28 days (the standard 28-day concrete cube test — building control will not allow loading of the slab until minimum curing has been achieved, typically 7 days for initial loading); the slab should be kept damp/covered for the first 3-7 days to prevent surface drying and cracking (curing); SCREED DRYING TIME (the time required for the screed to reach sufficiently low moisture content for floor finish application — different from structural curing): LIQUID SCREED (Hanson Cemfloor, Lafarge Thermia): typical drying rate approximately 1mm per day for the first 40mm of depth, then approximately 0.5mm per day — a 70mm liquid screed may take 50-80 days to dry to the 75% RH (relative humidity) threshold required for most floor finishes — this can be reduced by: forced air drying (fans running continuously from day 7 after installation — most liquid screed suppliers recommend starting forced air drying at 7 days); underfloor heating commissioning (UFH should be used for forced drying: day 7-14 after screed installation, set to 25°C, increase by 5°C per day to maximum 55°C, hold for 7 days, decrease by 5°C per day back to ambient — this drying cycle is mandated by most UFH manufacturers); SAND AND CEMENT SCREED: approximate drying rate 1mm per day (for 65mm screed: approximately 65 days to reach the 75% RH threshold); MOISTURE TESTING BEFORE FLOOR FINISH: a calibrated hygrometer or Tramex Concrete Moisture Encounter meter should confirm screed/concrete RH ≤75% before any adhesive or impermeable floor finish is applied — this is a critical step and skipping it leads to floor finish adhesive failure.
How much does a concrete slab floor cost in London?
Concrete ground-bearing slab and screed costs for London Victorian terrace extensions (London 2025, supply and fit, groundworks/flooring contractor, labour and materials): ground preparation and excavation (to formation level, remove existing material): ~£15-35/m² (mini excavator access); ~£30-60/m² (full hand excavation, restricted access, inner-London terrace); hardcore compaction (Type 1, 150mm minimum compacted, supply and compact): ~£12-22/m²; DPM (1200 gauge Visqueen Super Flexible Plus, supply and lay): ~£3-6/m²; PIR insulation (100mm Kingspan Kooltherm K3 or Celotex GA4000, supply and lay): ~£22-38/m²; concrete slab (100mm C25/P or C30/P, ready-mix, supply, pump, place, compact, and float): ~£20-38/m² (concrete pump typically required for restricted-access rear extensions — pump hire ~£400-700 per pour, add to overall cost); liquid screed over UFH (Hanson Cemfloor or Lafarge Thermia, minimum 65mm above UFH pipe, supply and pour, pump-applied): ~£18-30/m²; TOTAL PACKAGE (ground preparation + hardcore + DPM + 100mm PIR insulation + 100mm concrete slab + liquid screed, excluding UFH pipework and floor finish): approximately £90-190/m² (mechanically assisted excavation — some mechanical access); approximately £120-240/m² (full hand excavation — restricted access — inner-London premium); EXAMPLE: 20m² rear extension concrete slab floor package (mechanically assisted excavation): approximately £1,800-3,800 total (slab and screed, not including floor finish, UFH manifold and pipework, or plumbing connections); note: these costs cover structural slab and screed only — they EXCLUDE floor finish installation, UFH pipework supply and installation, heating connections, and any structural element of the extension walls, roof, or foundations.

Important Note

This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.

Ready to Discuss Your Project?

Free site survey. No obligation. Covering all Greater London & M25.

📞 Call now💬 WhatsAppFree Quote