Contents
What to Check in a London New Build Snagging Survey
A comprehensive snagging survey of a London new build flat or house should cover all areas of the property systematically. Key areas and items to inspect:
- External (where accessible):
- โขRoof: visible tile or slate condition; flashings and soakers to all abutments, valleys, and verges; condition of ridge tiles and pointing; gutters level and fall correct, no overflows or blockages; downpipes connected and draining to correct outlet
- โขDrainage: gully pots clean and drained; inspection chambers accessible and correctly sealed; external surface drainage falls correctly to outlets
- โขExternal walls: render or brickwork condition; pointing quality; external sill levels and drainage; window and door frames sealed and weather-tight; external taps and hose connections
- โขLandscaping and hard surfacing: paths level and draining; steps, ramps, and thresholds to Part M access standards; boundary walls and fences complete to specification
- Internal โ all rooms:
- โขWalls and ceilings: flat and smooth (no lumps, shadows, or scratched plaster); paint even coverage (no holidays, runs, or uneven sheen); ceilings free from cracks; skirtings and architraves aligned, mitres tight, no gaps at wall or floor; coving or cornice continuous and well-fixed
- โขFloors: level (no humps, dips, or springy boards); flooring condition (no scratches, chips, or poorly fitted sections); floor-to-wall junctions finished (no gaps, no missing beading); thresholds between floor types flush and secured
- โขWindows: open, close, and lock correctly; trickle vents installed and operational; glass clean and undamaged (no scratches, chips, or double-glazed seal failures); window boards level and sealed; reveals painted evenly
- โขDoors: hang correctly (gaps even on all four sides); close and latch without sticking; locks and handles operate smoothly; fire doors close fully on the door closer; ironmongery complete and correctly fixed; door frames plumb and square
- โขJoinery: kitchen unit doors aligned and hinges adjusted correctly; drawer runners operate smoothly; plinth panels secure; kitchen worktops: joints tight and sealed, no chips; silicone seals to upstands and sinks without gaps
- โขSanitary ware: basins, WCs, and baths level and secure; silicone seals to all joints (bath/wall, basin/wall) complete and even; taps operate correctly and close off without drip; waste outlets flow freely
- โขTiling: tiles level and aligned; grout even and complete; no cracked or chipped tiles; silicone joints at internal angles (not grouted โ grout cracks at movement joints); grouting colour consistent
- Mechanical and electrical:
- โขHeating: all radiators or underfloor heating zones heat up; thermostatic controls function correctly; boiler (if applicable) commissioned and manual provided; pressure gauge at correct reading; no visible leaks at pipework connections
- โขElectrical: all sockets test live (socket tester is useful); lighting circuits operate on each switch; two-way switching works correctly; extractor fans operate in kitchens and bathrooms; smoke alarms and heat detectors present and test correctly; consumer unit: no MCBs tripped; EV charge point (if included) operational; TV and data points wired; doorbell/video entry operational
- โขVentilation: MVHR or dMEV (decentralised mechanical extract ventilation) commissioned; extract rates measured at kitchen and bathroom outlets (compare to specification)
How to Use a Professional Snagging Company in London
A professional snagging inspection company provides an independent, expert assessment of the property's condition at completion โ more thorough than a buyer's own visual inspection and more credible with a developer's customer care team than a buyer's own list.
- What a professional snagging company provides:
- โขA systematic inspection of all accessible areas of the property using specialist tools (moisture meter, spirit level, light torch, socket tester, thermal imaging camera in some cases)
- โขA written report with photographs documenting each snag, typically in numbered format matching the room/area layout of the property
- โขCategorisation of each snag by severity (cosmetic/minor; functional; serious) and by trade responsible (plastering, painting, carpentry, plumbing, electrical, groundworks)
- โขIn some cases, advice on which items are the developer's responsibility under the warranty and which may be considered acceptable tolerance under NHBC Technical Standards
Cost of a professional snagging survey: Typically ยฃ300โยฃ600 for a 1โ2 bedroom flat; ยฃ400โยฃ700 for a 3-bedroom house; ยฃ600โยฃ1,000+ for a larger property. The cost is typically recovered many times over through the value of defects identified and required to be rectified at the developer's cost.
Selecting a snagging company: Look for companies with: experienced surveyors who have backgrounds in new build construction (former NHBC inspectors, building surveyors, or main contractor site managers); clear written reports with photographs; professional indemnity insurance; good reviews from previous clients; and willingness to attend a re-inspection after snags have been reportedly rectified.
Using the snag list with the developer: Submit the snag list to the developer's customer care team in writing (email, with the full report attached). Request written acknowledgement and a schedule for rectification. Follow up in writing at each stage โ keep a paper trail of all communications. Where the developer fails to rectify notified snags within a reasonable time (NHBC guidance suggests 30 days for notified defects), escalate to NHBC's resolution service.
Dealing with a Developer Who Is Slow to Fix Snags
Unfortunately, the experience of many London new build buyers is that developer customer care teams are understaffed relative to the volume of completions, and snag rectification can be slow, incomplete, or poor quality. Practical steps to manage a slow developer:
Keep a log: Maintain a written log of all communications โ every email, letter, and call to the customer care team, with dates, names, and the substance of the conversation. This log will be essential if you need to escalate to NHBC, the NHOS, or a solicitor.
Set reasonable deadlines: Each time you submit a snag or follow up on a notified snag, specify a reasonable deadline for the developer to respond and act. A "reasonable time" in the context of snag rectification is typically 4โ8 weeks for non-urgent defects, less for urgent functional or safety-related issues.
Escalate systematically: If the customer care team is not responding adequately, escalate to: the developer's customer service manager; the site manager; the developer's senior management or head office; NHBC (by registering a formal complaint through the NHBC Resolution service at nhbc.co.uk); the New Homes Ombudsman Service (if the developer is registered with the NHQB); and ultimately a solicitor's letter if other routes are exhausted.
Emergency defects: Where a defect is an emergency (a water leak, a heating failure in winter, a drainage failure, an electrical fault, or a security breach โ a lock that will not secure the property), the developer is required to respond urgently. Where the developer does not respond urgently to an emergency, you may have the right to arrange emergency repairs yourself and recover the cost from the developer โ document the emergency, notify the developer in writing (email with a read receipt), and if you must arrange emergency repairs, keep all receipts and documentation.
Using NHBC: NHBC's Resolution service provides a mediation and assessment service for disputes between buyers and registered developers in the Developer's Period (years 1โ2). NHBC can visit the property, assess the disputed defects, and issue a binding decision on which items must be repaired. NHBC can also arrange for emergency works where the developer fails to respond to urgent defects.
Frequently Asked Questions
Can I refuse to complete on my new build London property until snags are fixed?โผ
Does the NHBC cover white goods and kitchen appliances in my London new build?โผ
Is a snagging survey the same as a structural survey or RICS Home Survey for a new build?โผ
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. rcbGroup offers free initial consultations โ book your free survey.
Was this guide helpful? Share it:
Have a question about your project?
Chat with us on WhatsApp โ Faith usually replies within the hour.