What client project management actually involves
**The contractor's role vs. the client's role**:
A common misconception is that 'project management' is entirely the contractor's responsibility. In reality:
- *The contractor is responsible for*:
- •Site management, supervision, and health and safety
- •Sequencing and programming the trades and sub-contractors
- •Quality of workmanship and materials they supply
- •Compliance with the Building Regulations
- •Communication about progress, issues, and variations
- *The client is responsible for*:
- •Making decisions promptly when decisions are required (tiles, kitchen, ironmongery, floor finish — see below)
- •Supplying materials that are the client's responsibility (per RCB's standard terms, all second-fix materials are client-supplied) on time and in the right quantity
- •Paying stage payments on time when milestones are reached
- •Communicating quality or scope concerns promptly in writing
- •Accessing the site with sufficient frequency to observe progress and catch issues early
When projects go wrong, client-side failures are nearly as common as contractor-side failures — and far less commonly acknowledged.
**The decision timeline — what you must decide, and when**:
The most common cause of programme delay in domestic refurbishments is late client decisions on materials. The contractor needs specific decisions by specific dates — earlier than most clients expect.
| Item | When contractor needs the decision | Lead time reason | |---|---|---| | Kitchen units | 6–10 weeks before kitchen fit-out stage | Order, delivery, and checking lead time | | Worktops (stone/quartz) | 2 weeks after units are fitted (templating) | Cut to measure: 2–3 weeks from template | | Tiles (floor and wall) | 4–6 weeks before tiling stage | Delivery + checking (especially imported tiles) | | Sanitaryware (bath, toilet, basin, shower valve) | 4–6 weeks before plumbing second fix | Delivery; some items made to order | | Flooring (LVT, hardwood, carpet) | 4 weeks before flooring stage | Delivery + acclimatisation (hardwood: 1–2 weeks) | | Ironmongery (door handles, hinges) | 4 weeks before second-fix carpentry | Delivery; some items made to order | | Structural steel specification | At SE appointment — before work starts | Fabrication + delivery: 4–8 weeks | | Windows and doors | At frame measurement — typically week 2–3 | Fabrication + delivery: 6–12 weeks | | Appliances | 4 weeks before kitchen installation | Delivery; some items ex-stock, others 6+ weeks |
A construction project that is waiting for client material decisions is a project that is standing still — at the homeowner's cost in time and the contractor's cost in programme disruption.
**Site visits — how often and what to look for**:
The single most effective client project management activity is regular site visits. Minimum recommended: once per week during active construction.
- What to look for on a site visit:
- •Is the work progressing as expected against the programme?
- •Is the site clean, organised, and safely managed?
- •Are the materials stored correctly (not left in rainwater, not blocking access)?
- •Are all workers on site appropriately supervised?
- •Are there any visible defects (cracked blockwork, inconsistent bedding joints, poor junction between new and existing, inadequate insulation coverage) that should be raised before they are covered up?
Raising a quality concern on a site visit before the work is plastered or tiled costs nothing to resolve. Raising the same concern after the finishes are complete may require demolition and reinstatement.
The communication protocol — how to raise issues effectively
**The golden rule: put it in writing**:
All significant communications with a contractor during a project should be in writing — email is preferred over WhatsApp for formal matters because it provides a permanent, searchable record. Verbal instructions ('tell them on site to move the socket') are the most common source of miscommunication and disputed variations.
- What must be in writing:
- •Any variation to the scope (additional work, changed specification, changed position)
- •Any quality concern or defect notification
- •Any instruction to stop work
- •Any notification of a stage payment being withheld and the reason
- •Any extension of time request from the contractor
- •Any change to the programme or start/completion dates
**How to raise a quality concern without creating unnecessary conflict**:
Quality concerns on a live project are best raised: promptly (as soon as observed), specifically (citing the relevant drawing, specification, or building regulation), and constructively (asking the contractor to attend and inspect rather than making accusatory statements).
Example: 'Hi [contractor], I visited site today and I noticed the party wall insulation between the new floor joists and the party wall does not appear to be continuous — there appear to be gaps at the joist ends. I'd like us to look at this together before the plasterboarding goes over. Can we arrange a walk-around this week?'
This approach: is factual (describes what was observed); references the issue clearly; does not escalate prematurely; and requests a prompt practical response.
**Variation management**:
- Variations (changes to the agreed scope) are the primary source of cost overruns in domestic construction. The client's role in variation management:
- •Do not instruct additional works verbally on site — always confirm in writing
- •Before instructing a variation, ask the contractor to provide a written price for the additional works before they are carried out
- •Accept or reject the variation price in writing before work starts
- •Keep a variation log — a simple spreadsheet noting each variation, its agreed price, and its impact on the total contract value
A contractor who carries out additional works without a written instruction from the client has a weaker claim to payment for those works. A client who verbally instructs additional works then disputes the cost is in a similarly weak position. Written variation instructions protect both parties.
**What to do when problems arise**:
*Contractor is behind programme*: 1. Raise in writing, citing the current programme and the estimated completion date 2. Ask the contractor for a revised programme showing how they intend to recover the delay 3. If delay is contractor-caused (not weather, ground conditions, client-caused change, or other neutral risk), the homeowner is not obliged to pay for contractor costs associated with the delay; the contract may give the homeowner rights to recover losses caused by delay
*Quality is below standard*: 1. Document the defect with photographs and a written description 2. Notify the contractor in writing, referencing the relevant specification or building regulation requirement 3. Allow the contractor a reasonable opportunity to remedy (under most standard forms, the contractor has a 'right to remedy' before the homeowner can engage others at the contractor's cost) 4. If the contractor fails to remedy within a reasonable period, seek a professional assessment and take legal advice
*Contractor makes additional payment demands not agreed in advance*: 1. Request a written breakdown of the claimed additional works and the basis for the claim 2. Check against your variation log — was this work agreed in writing? 3. Do not make payment for additional works not supported by a written variation instruction 4. If genuinely disputed, the adjudication route provides a 28-day binding decision
When to appoint a professional project manager or contract administrator
**When professional project management is worthwhile**:
For most standard domestic extensions and refurbishments, a hands-on homeowner who follows the approach described above can manage the project without appointing a separate professional project manager. However, professional project management or contract administration is strongly recommended in the following scenarios:
*Large or complex projects* (£150,000+): Projects at this scale involve significant financial exposure and multiple sub-contractor packages that benefit from professional coordination and independent certification of stage payments.
*Projects where the homeowner is not based locally or cannot regularly visit site*: Remote project management by a homeowner who can only visit every 2–3 weeks significantly reduces quality oversight. A professional site representative provides the regular eyes-on-site that is needed.
*Difficult contractor relationships or late-stage appointments*: Where the homeowner has lost confidence in the contractor mid-project, an experienced contract administrator can help manage communications, assess what has been done, and structure the exit if necessary.
*Projects with a formal JCT contract*: The JCT Minor Works Contract (MW) requires a 'contract administrator' — typically the architect — to certify milestones, issue instructions, and value variations. Without a contract administrator, the JCT MW contract cannot function as intended.
**What a professional contract administrator or project manager does**:
- •Reviews contractor progress against programme
- •Certifies stage payment milestones (issues Interim Certificates confirming payment is due)
- •Issues formal Architect's Instructions for scope changes
- •Values and assesses variation claims
- •Inspects works for quality compliance against specification
- •Manages the Building Control inspection process
- •Issues the Certificate of Practical Completion (triggering the DLP and retention release)
- •Issues the Making Good Defects Certificate at the end of the DLP (triggering final retention release)
*Fee*: A contract administrator role for a domestic project typically costs 2–5% of the construction cost. For a £100,000 project, this is £2,000–£5,000 — modest compared with the risk mitigation it provides.
Frequently Asked Questions
Do I need a project manager if I'm using a design-and-build contractor?▼
How do I handle a situation where the contractor is doing something I wasn't expecting?▼
What should I include in a site visit checklist?▼
Important Note
This guide is for general information only. Building regulations, planning rules, and legal requirements change regularly and vary by local authority. Always seek professional advice specific to your project and location. RCB Design & Build offers free initial consultations — book your free survey.